Permit #2019060276
Permit Details
Status: COED
| Parcel Id: 07-11-31-7029-00380-0060 |
| CONDITIONED SPACE: 1983 sqft |
| GARAGE: 516 sqft |
| OPENED PORCH (WITH ROOF) : 106 sqft |
| OPENED PORCH (WITH ROOF) : 48 sqft |
| Total Square Footage: 2653 sqft |
| Block: 00380 |
| Subdivision: 2209 - SECTION 29-ROYAL PALMS |
| Job Phone: 407-307-4753 |
| Location Address: 4 RYDER DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 07/31/2019 |
| NOC: RECORDED |
| Applicant name: SHAWN VIRAG |
| Owner: BRITE PROPERTIES OF FLORIDA LLC |
|
Address 7345 GREENBRIAR PKWY ORLANDO, FL 32819 |
| Lot: 0060 |
| Contracted Stated Job Value: ¤135,076.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
SHAWNTELLE CONSULTING AND DESIGN LLC
| Status | Location Address | State License Number | Phone |
| CANCEL |
611 LARGOVISTA DR OAKLAND, FL 34787 |
CBC1261160 (Exp: 08/31/2020) | 407-307-4753 |
Sub Contractors
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
ROBERT G DELLO RUSSO
| Status | Location Address | State License Number | Phone | Fax |
| DECEASED |
531 CODISCO WAY SANFORD, FL 32771 |
CAC032448 (Exp: 08/31/2022) | (407)831-2665 | (407)333-3853 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 03/31/2020 | FINAL APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION A/C Unit not started. Fresh air pipe still wrapped and Safety Switch Not Connected. | |||
| BLD - BUILDING FINAL | 03/27/2020 | Disapproved - NO FEE | FWILLIS |
| Note: A/C Unit not started. Fresh air pipe still wrapped and Safety Switch Not Connected. | |||
| U -UTILITY RESIDENTIAL FINAL | 03/27/2020 | FINAL APPROVED | LFITZGERALD |
| ROW - STORMWATER FINAL | 03/26/2020 | APPROVED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION | |||
| SEWER SERVICE | 03/25/2020 | CANCELLED BY INSPECTOR | JGIBSON |
| Note: NOT NEEDED FOR RESIDENTIAL | |||
| ELECTRIC - EARLY POWER | 03/25/2020 | APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Contractor needs to meet on site at next inspection to take lights down to verify boxs. Need boxs behind vanity lights NEC 2014 art 300.15. No work has been done since previous inspection. Once again Contractor needs to be on site. | |||
| ROW - STORMWATER FINAL | 03/24/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: THIS IS A REINSPECTION DRIANAGE CONVEYANCE ON RIGHT SIDE OF PROPERTY WAS DUG UP . WILL NEED TO BE REGRADED AND RESODDED | |||
| ROW - STORMWATER FINAL | 03/13/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: GARBAGE ALONG RIGHT SIDE OF PROPERTY LINE NEEDS TO BE PICKED UP DUMPSTER NEEDS TO BE REMOVED AND ANY DAMAGE TO THE SWALE WILL NEED TO BE REPAIRED | |||
| ELECTRIC - EARLY POWER | 03/13/2020 | Disapproved -FEE REQUIRED | JMUNSON |
| Note: THIS IS A REINSPECTION Contractor needs to meet on site at next inspection to take lights down to verify boxs. Need boxs behind vanity lights NEC 2014 art 300.15. No work has been done since previous inspection. Once again Contractor needs to be on site. | |||
| ROW - FINAL APRON (AFTER POUR) | 03/13/2020 | APPROVED | MMAJEWSKI |
| ELECTRIC - EARLY POWER | 03/09/2020 | Disapproved - NO FEE | JMUNSON |
| Note: Contractor needs to meet on site at next inspection to take lights down to verify boxs. Need boxs behind vanity lights NEC 2014 art 300.15. | |||
| FINAL SURVEY (OFFICE USE ONLY) | 03/09/2020 | APPROVED | MMAJEWSKI |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/09/2020 | APPROVED | MMAJEWSKI |
| ROW- PRE-APRON (PRE-POUR) | 01/27/2020 | APPROVED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION IT IS THE BUILDER’S RESPONSIBILITY: TO RECHECK ELEVATIONS AND PIPE SIZE, TO INSURE THAT AN OBSTRUCTION DOES NOT EXIST UPSTREAM AND OR DOWNSTREAM, THAT THE CULVERT PIPE IS SET TO AND OR FOLLOWS THE SWALE PLAN, FORM THE DRIVEWAY TO THE APPROVEDSITE PLAN AND FOLLOW THE APPROVED DRIVEWAY DETAIL SHEET PROVIDED BY THE CITY OF PALM COAST. PRIOR TO PLACEMENT OF CONCRETE. | |||
| ROW- PRE-APRON (PRE-POUR) | 01/24/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: CULVERT PIPE IS CROOKED, NEEDS TO BE 8 FEET FROM EDGE OF PAVEMENT | |||
| U - SEWER TIE IN | 01/23/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 01/23/2020 | APPROVED | JGIBSON |
| LATH/BRICK/ WATER BARRIER | 12/31/2019 | APPROVED | JCOLASANTI |
| PEP TANK INSTALLATION REQUEST | 12/20/2019 | APPROVED | CSTONE |
| INSULATION | 12/19/2019 | APPROVED | FWILLIS |
| ALL ROUGH | 12/19/2019 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ALL ROUGH | 12/16/2019 | Disapproved -FEE REQUIRED | WMILLER |
| Note: 1. 5ft HEAD OF WATER, 6TH EDITION FBC CHAPTER 25 SECTION P2503.5.1 (1) 2. DOOR SHIMS, SHIM DOOR IN ACCORDANCE WITH MANUFACTURER INSTALLATION SPECS (NO MORE THAN .25 inch GAP AND SHIMMED). OR PROVIDE SPECS FOR INSTALATION METHOD USED. 3. MISSING TRAM WINDOW AT MASTER SHOWER (WINDOWS MUST BE IN FOR ALL-ROUGH) 4. MISSING DUCT DRAWINGS AND ENERGY CALCS... FBC R 107.3,1. | |||
| ELECTRIC-TUG | 12/05/2019 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 11:40 | |||
| ROOF VALLEY & METAL | 12/04/2019 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ROOF VALLEY & METAL | 12/02/2019 | CANCELLED BY APPLICANT | JDELBONIS |
| ELECTRIC-TUG | 11/27/2019 | CANCELLED BY APPLICANT | WEB |
| Note: THIS IS A REINSPECTION | |||
| ELECTRIC-TUG | 11/26/2019 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: STILL NOT READY | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/26/2019 | APPROVED | JDELBONIS |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/25/2019 | Disapproved - NO FEE | FWILLIS |
| Note: META straps on rear CMU not secured on TRUSS. | |||
| ELECTRIC-TUG | 11/21/2019 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: NOT READY | |||
| ELECTRIC-TUG | 11/15/2019 | CANCELLED BY APPLICANT | WEB |
| TIE BEAM / LINTEL | 11/15/2019 | APPROVED | FWILLIS |
| MONOLITHIC SLAB | 11/08/2019 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| FOUND SURVEY APPROVED (OFFICE) | 11/05/2019 | APPROVED | JMUNSON |
| MONOLITHIC SLAB | 11/01/2019 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: No Dowels or rebar are installed as per approved drawings. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 10/29/2019 | APPROVED | JDELBONIS |
| Note: THIS IS A REINSPECTION | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 10/28/2019 | Disapproved -FEE REQUIRED | JDELBONIS |
| Note: not even started yet | |||
| WATER METER INSTALLATION REQUEST | 10/01/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 11/05/2019 | 11/05/2019 |
| Note: Released By: JMUNSON Foundation Survey | |||
| SW1 | COMPLETE | 07/02/2019 | 07/02/2019 |
| Note: Released By: JMUNSON | |||
| ZON | COMPLETE | 07/02/2019 | 07/02/2019 |
| Note: Released By: AMOBLEY | |||
| PLUM | COMPLETE | 06/20/2019 | 06/27/2019 |
| Note: Released By: JHINDMAN | |||
| SW1 | HOLD | 06/20/2019 | 06/20/2019 |
| Note: Held By: JMUNSON Show proposed drainage in 10ft interverls. ULDC Tech Manual Sec 5 300 | |||
| ZON | HOLD | 06/20/2019 | 06/20/2019 |
| Note: Held By: TDOAK REPEAT COMMENT: This property has two flood panel numbers. Both must be listed on site plan/survey. | |||
| SWALE | COMPLETE | 06/11/2019 | 07/01/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 06/07/2019 | 06/14/2019 |
| Note: Released By: JHINDMAN | |||
| CUSVC | COMPLETE | 06/07/2019 | 06/07/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 06/07/2019 | 06/14/2019 |
| Note: Released By: JHINDMAN | |||
| ENGIN1 | COMPLETE | 06/07/2019 | 06/11/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 06/07/2019 | 06/11/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 06/07/2019 | 06/14/2019 |
| Note: Released By: JHINDMAN | |||
| PLUM | HOLD | 06/07/2019 | 06/14/2019 |
| Note: Held By: JHINDMAN 1. provide a plumbing riser signed by the plumbing contractor with their license number th ed. FBC 107.1 | |||
| SW1 | HOLD | 06/07/2019 | 06/07/2019 |
| Note: Held By: JMUNSON 1. Remove septic and drainfield. 2. Show elevations on each side of the house and front and back for proposed drainage. 3. show proposed grade on each corner of the house. per ULDC Tech Manual Sec5 300 | |||
| UD1 | COMPLETE | 06/07/2019 | 06/12/2019 |
| Note: Released By: AHALL | |||
| ZON | HOLD | 06/07/2019 | 06/07/2019 |
| Note: Held By: ELENS Provide driveway width and material on Site Plan. | |||
| ZON | HOLD | 06/07/2019 | 06/07/2019 |
| Note: Held By: TDOAK Provide driveway width and material on Site Plan. This property has two flood panel numbers. Both must be listed on site plan/survey. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/04/2020 |
| REINSPECTION FEE | ¤40.00 | 01/08/2020 |
| REINSPECTION FEE | ¤40.00 | 01/08/2020 |
| REINSPECTION FEE | ¤40.00 | 01/08/2020 |
| REINSPECTION FEE | ¤40.00 | 01/08/2020 |
| REINSPECTION FEE | ¤40.00 | 01/08/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤494.00 | 07/31/2019 |
| SITE PLAN 20 | ¤20.00 | 07/31/2019 |
| SURCHARGE FS 533.721 | ¤11.59 | 07/31/2019 |
| SURCHARGE - FS 468.631 | ¤17.38 | 07/31/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 07/31/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 07/31/2019 |
| SEWER INSPECTION | ¤25.00 | 07/31/2019 |
| SEWER CAPITAL FACILITY | ¤4,515.25 | 07/31/2019 |
| WATER CAPITAL FACILITY FEE | ¤3,314.84 | 07/31/2019 |
| METER - DEPOSIT | ¤60.00 | 07/31/2019 |
| WATER- TURN ON | ¤25.00 | 07/31/2019 |
| ADMIN FEE | ¤20.00 | 07/31/2019 |
| CONNECTION FEES | ¤985.25 | 07/31/2019 |
| ELECTRIC FEE | ¤208.20 | 07/31/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 07/31/2019 |
| IMPACT FEE FIRE | ¤223.38 | 07/31/2019 |
| IMPACT FEE PARKS | ¤849.24 | 07/31/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 07/31/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 07/31/2019 |
| MECHANICAL FEE | ¤208.20 | 07/31/2019 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 07/31/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 07/31/2019 |
| PLAN CHECK FEE | ¤98.80 | 07/31/2019 |
| PLUMBING FEE | ¤208.20 | 07/31/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤16,780.19 |