Permit #2019060590

Permit Details

Status: COED

Parcel Id: 07-11-31-7059-00090-0060
CONDITIONED SPACE: 1767 sqft
GARAGE: 484 sqft
OPENED PORCH (WITH ROOF) : 156 sqft
OPENED PORCH (WITH ROOF) : 43 sqft
Total Square Footage: 2450 sqft
Block: 00090
Subdivision: 2211 - SECTION 59-SEMINOLE PARK
Job Phone: 386-447-4151
Location Address: 6 SEA SHARK PATH
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 07/08/2019
NOC: RECORDED
Applicant name: GENE WARREN SLONE
Owner: FLORIDA GREEN CONSTRUCTION INC

Address

50 LEANNI WAY UNIT C1

PALM COAST, FL 32137

Lot: 0060
Contracted Stated Job Value: ¤250,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

FLORIDA GREEN CONSTRUCTION INC.
Status Location Address State License Number Phone
INACTIVE

870 E RETTA STREET

DELEON SPRINGS, FL 32130

CBC1260957 (Exp: 08/31/2026) 407-580-2657

Sub Contractors

JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
JOHN EDWARD GAMBONE
Status Location Address Mailing Address State License Number Phone
ACTIVE

15 HARGROVE LN

PALM COAST, FL 32137

1G

PALM COAST, FL 32137

EC13006037 (Exp: 08/31/2026) 386-586-9144
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
GREGG A MCANALLY
Status Location Address State License Number Phone
INACTIVE

3370 AGRICULTURAL CENTER DRIVE

PALM COAST, FL 32092

CAC1815760 (Exp: 08/31/2022) 904-829-8898

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 04/08/2020 FINAL APPROVED WMILLER
U -UTILITY RESIDENTIAL FINAL 02/21/2020 APPROVED AHALL
Note: THIS IS A REINSPECTION
U -UTILITY RESIDENTIAL FINAL 02/10/2020 Disapproved - NO FEE AHALL
Note: improper pep tank breaker in service panel 20amp dedicated non gfi breaker required.
ROW - STORMWATER FINAL 02/07/2020 APPROVED MMAJEWSKI
ROW - FINAL APRON (AFTER POUR) 02/07/2020 APPROVED MMAJEWSKI
SEWER SERVICE 02/07/2020 CANCELLED BY INSPECTOR BBEMBRY
ROW FIELD SURVEY /GRADING CERTIFICATION 02/05/2020 APPROVED MMAJEWSKI
Note: THIS IS A REINSPECTION
ROW FIELD SURVEY /GRADING CERTIFICATION 01/31/2020 Disapproved - NO FEE MMAJEWSKI
Note: THERE IS A LOW AEREA OFF THE RIGHT REAR CORNER OF THE HOUSE. ELEVATIONS DOWN THE SIDE OF THE YARD ARE HIGHER THAN THE LOW SPOT, WATER WILL NOT BE ABLE TO DRAIN
FINAL SURVEY (OFFICE USE ONLY) 01/31/2020 APPROVED MMAJEWSKI
ELECTRIC - EARLY POWER 01/29/2020 APPROVED - AS NOTED JMUNSON
Note: Emailed FPL at 9:00 am
ROW- PRE-APRON (PRE-POUR) 01/02/2020 APPROVED - AS NOTED MMAJEWSKI
Note: THIS IS A REINSPECTION. It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ROW- PRE-APRON (PRE-POUR) 12/30/2019 Disapproved -FEE REQUIRED RGROSS
Note: THIS IS A REINSPECTION. CULVERT HAS WATER RUNNING CLEAR THROUGH IT AND ENDS ARE FULL. GROUND WAY TO SOFT TO POUR.
ROW- PRE-APRON (PRE-POUR) 12/23/2019 Disapproved - NO FEE MMAJEWSKI
U - SEWER TIE IN 12/16/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION DEFICIENCIES NOTED BY INSPECTOR MG PRIOR RESOLVED
GRAVITY SEWER TEST 12/16/2019 APPROVED WMILLER
Note: THIS IS A REINSPECTION DEFICIENCIES NOTED BY INSPECTOR MG PRIOR RESOLVED
GRAVITY SEWER TEST 12/13/2019 Disapproved -FEE REQUIRED JGIBSON
Note: P-2503.4 BUILDING SEWER TESTING TEST NOT HOLDING
U - SEWER TIE IN 12/13/2019 Disapproved - NO FEE JGIBSON
Note: P-2503.4 TEST NOT HOLDING
PEP TANK INSTALLATION REQUEST 11/12/2019 APPROVED CSTONE
Note: Once you request your pep tank we ask that you keep the site clear until the tank is in. You will have 72 hours after pep tank request has been approved to get the site ready. Site ready means area is clear without driveway, sod, paint, sidewalks, or irrigation in the way. If you have underground power where the pep tank will be located you will need to have that moved.
INSULATION 10/30/2019 APPROVED FWILLIS
LATH/BRICK/ WATER BARRIER 10/29/2019 APPROVED JDELBONIS
ALL ROUGH 10/21/2019 APPROVED FWILLIS
Note: THIS IS A REINSPECTION
ALL ROUGH 10/18/2019 Disapproved -FEE REQUIRED JDELBONIS
Note: panel not phased out or tied in
ROOF VALLEY & METAL 09/25/2019 APPROVED DROCKWELL
ROOF SHEATHING / BRACES/TIES/DOWN CELL 09/20/2019 APPROVED - AS NOTED FWILLIS
Note: Could not see connections on top of 6X6 post. Open for viewing on the All Rough.
TIE BEAM / LINTEL 09/09/2019 APPROVED DROCKWELL
Note: THIS IS A REINSPECTION
TIE BEAM / LINTEL 09/06/2019 Disapproved - NO FEE FWILLIS
Note: Dowel layout not matching these plans. Possibly wrong plans on site. Plans highlighted on page 4.
FOUND SURVEY APPROVED (OFFICE) 09/05/2019 APPROVED JMUNSON
MONOLITHIC SLAB 08/15/2019 APPROVED DROCKWELL
PLUMBING 1ST ROUGH UNDERGROUND 07/30/2019 APPROVED JGIBSON
ELECTRIC TEMP POLE 07/24/2019 APPROVED - AS NOTED RMARTIN
Note: SPOKE TO SUSAN FPL RELEASED POWER 3:50
WATER METER INSTALLATION REQUEST 07/12/2019 APPROVED CSTONE
Note: Daniel Wieland asked for this inspection

Review History

Department Status Date In Date Out
SW1 COMPLETE 09/05/2019 09/05/2019
Note: Released By: JMUNSON
SW1 HOLD 08/29/2019 08/29/2019
Note: Held By: JMUNSON Foundation S Need to put FFE on Foundation Survey.
BLD COMPLETE 08/23/2019 08/31/2019
Note: Released By: MGARRETT
BLD COMPLETE 08/12/2019 08/19/2019
Note: Released By: MGARRETT
ENGIN1 COMPLETE 08/12/2019 08/13/2019
Note: Released By: TBAKER
ZON COMPLETE 08/12/2019 08/13/2019
Note: Released By: TDOAK
ZON COMPLETE 06/20/2019 06/20/2019
Note: Released By: TDOAK
BLD COMPLETE 06/20/2019 06/27/2019
Note: Released By: RLEE
SWALE COMPLETE 06/18/2019 07/11/2019
Note: Released By: TBAKER
BLD HOLD 06/13/2019 06/18/2019
Note: Held By: RLEE Footing detail minimum overall deppth does not match wall detail of minimum 20". Minimum depth below grade/compact soil to comply with FBCR 403.1.4
CUSVC COMPLETE 06/13/2019 06/13/2019
Note: Released By: HHAND
ELEC COMPLETE 06/13/2019 06/18/2019
Note: Released By: RLEE
ENGIN1 COMPLETE 06/13/2019 06/18/2019
Note: Released By: TBAKER
LOCATE COMPLETE 06/13/2019 06/17/2019
Note: Released By: CSTONE
MECH COMPLETE 06/13/2019 06/17/2019
Note: Released By: RLEE
PLUM COMPLETE 06/13/2019 06/18/2019
Note: Released By: RLEE
SW1 COMPLETE 06/13/2019 06/13/2019
Note: Released By: JMUNSON
UD1 COMPLETE 06/13/2019 06/18/2019
Note: Released By: AHALL
ZON HOLD 06/13/2019 06/13/2019
Note: Held By: ELENS Identify sod type and whether irrigation will be provided on landscape plan

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 04/21/2020
REINSPECTION FEE ¤40.00 04/21/2020
REINSPECTION FEE ¤40.00 04/21/2020
NEW RESIDENTIAL INSPECTIONS ¤500.00 07/08/2019
SITE PLAN 20 ¤20.00 07/08/2019
SURCHARGE FS 533.721 ¤11.70 07/08/2019
SURCHARGE - FS 468.631 ¤17.55 07/08/2019
STORM WATER PERMIT FEES ¤80.00 07/08/2019
3% TRANS IMPACT FEE CREDIT (¤48.96) 07/08/2019
SEWER CREDIT (¤2,455.03) 07/08/2019
SEWER INSPECTION ¤25.00 07/08/2019
SEWER CAPITAL FACILITY ¤4,515.25 07/08/2019
WATER CREDIT (¤10.72) 07/08/2019
WATER CAPITAL FACILITY FEE ¤3,314.84 07/08/2019
METER - DEPOSIT ¤60.00 07/08/2019
WATER- TURN ON ¤25.00 07/08/2019
ADMIN FEE ¤20.00 07/08/2019
CONNECTION FEES ¤985.25 07/08/2019
ELECTRIC FEE ¤210.00 07/08/2019
3% FIRE IMPACT FEE CREDIT (¤6.70) 07/08/2019
IMPACT FEE FIRE ¤223.38 07/08/2019
IMPACT FEE PARKS ¤849.24 07/08/2019
IMPACT FEE SCHOOL ¤3,600.00 07/08/2019
IMPACT FEE TRANSPORTATION ¤1,632.00 07/08/2019
MECHANICAL FEE ¤210.00 07/08/2019
WATER -IRRIGATION INSPECTION ¤25.00 07/08/2019
3% PARKS IMPACT FEE CREDIT (¤25.48) 07/08/2019
PLAN CHECK FEE ¤100.00 07/08/2019
PLUMBING FEE ¤210.00 07/08/2019
Fees Total Due: ¤0.00 Total Paid: ¤14,207.32