I want to search for...
Permit #2019070431
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7034-01130-0100 |
| Block: 01130 |
| Subdivision: 2165 - SECTION 34-EASTHAMPTON |
| Job Phone: 386-586-8265 |
| Location Address: 23 EDGEWATER DR |
| Type: DR - DRIVEWAY |
| Issue Date: 07/17/2019 |
| NOC: Unknown |
| Applicant name: PATRICIA BARTON |
| Owner: GWYNN, CHARLES E & JOANN D |
|
Address 23 EDGEWATER DRIVE PALM COAST, FL 32164 |
| Lot: 0100 |
| Contracted Stated Job Value: ¤2,485.00 |
| Job Description: REPLACE DRIVEWAY W/ NEW CULVERT |
| Type: CN |
Contractor
PRECISION CONCRETE OF PALM COAST INC
| Status | Location Address | Phone | Fax |
| INACTIVE |
PO BOX 351897 PALM COAST, FL 32137 |
386-586-8265 | 386-262-1245 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 09/17/2019 | APPROVED | AHALL |
| ROW - FINAL INSPECTION | 08/14/2019 | FINAL APPROVED | KHOWELL |
| ROW - FINAL APRON (AFTER POUR) | 08/12/2019 | APPROVED - AS NOTED | KHOWELL |
| Note: MOVE / LOWER THE SPRINKLER LINES AT THE ENDS OF THE MITERED END SECTIONS AND FINISH SOD PRIOR TO CALLING IN INSPECTION FOR R.O.W. FINAL | |||
| ROW - FINAL APRON (AFTER POUR) | 08/09/2019 | APPROVED - AS NOTED | KHOWELL |
| Note: MOVE / LOWER THE SPRINKLER LINES AT THE ENDS OF THE MITERED END SECTIONS AND FINISH SOD PRIOR TO CALLING IN INSPECTION FOR R.O.W. FINAL | |||
| ROW- PRE-APRON (PRE-POUR) | 07/29/2019 | APPROVED - AS NOTED | KHOWELL |
| Note: THIS IS A REINSPECTION It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. | |||
| ROW- PRE-APRON (PRE-POUR) | 07/26/2019 | Disapproved -FEE REQUIRED | KHOWELL |
| Note: CULVERT PIPE IS OUT OF TOLERANCE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 07/12/2019 | 07/17/2019 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 07/12/2019 | 07/12/2019 |
| Note: Released By: JMUNSON | |||
| UD1 | COMPLETE | 07/12/2019 | 07/17/2019 |
| Note: Released By: AHALL | |||
| ZON | COMPLETE | 07/12/2019 | 07/12/2019 |
| Note: Released By: TDOAK |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 09/16/2019 |
| SITE PLAN 20 | ¤20.00 | 07/17/2019 |
| SURCHARGE FS 533.721 | ¤2.00 | 07/17/2019 |
| SURCHARGE - FS 468.631 | ¤2.00 | 07/17/2019 |
| STORM WATER PERMIT FEES | ¤40.00 | 07/17/2019 |
| ADMIN FEE | ¤20.00 | 07/17/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤124.00 |