Permit #2019070431

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7034-01130-0100
Block: 01130
Subdivision: 2165 - SECTION 34-EASTHAMPTON
Job Phone: 386-586-8265
Location Address: 23 EDGEWATER DR
Type: DR - DRIVEWAY
Issue Date: 07/17/2019
NOC: Unknown
Applicant name: PATRICIA BARTON
Owner: GWYNN, CHARLES E & JOANN D

Address

23 EDGEWATER DRIVE

PALM COAST, FL 32164

Lot: 0100
Contracted Stated Job Value: ¤2,485.00
Job Description: REPLACE DRIVEWAY W/ NEW CULVERT
Type: CN

Contractor

PRECISION CONCRETE OF PALM COAST INC
Status Location Address Phone Fax
INACTIVE

PO BOX 351897

PALM COAST, FL 32137

386-586-8265 386-262-1245

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 09/17/2019 APPROVED AHALL
ROW - FINAL INSPECTION 08/14/2019 FINAL APPROVED KHOWELL
ROW - FINAL APRON (AFTER POUR) 08/12/2019 APPROVED - AS NOTED KHOWELL
Note: MOVE / LOWER THE SPRINKLER LINES AT THE ENDS OF THE MITERED END SECTIONS AND FINISH SOD PRIOR TO CALLING IN INSPECTION FOR R.O.W. FINAL
ROW - FINAL APRON (AFTER POUR) 08/09/2019 APPROVED - AS NOTED KHOWELL
Note: MOVE / LOWER THE SPRINKLER LINES AT THE ENDS OF THE MITERED END SECTIONS AND FINISH SOD PRIOR TO CALLING IN INSPECTION FOR R.O.W. FINAL
ROW- PRE-APRON (PRE-POUR) 07/29/2019 APPROVED - AS NOTED KHOWELL
Note: THIS IS A REINSPECTION It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ROW- PRE-APRON (PRE-POUR) 07/26/2019 Disapproved -FEE REQUIRED KHOWELL
Note: CULVERT PIPE IS OUT OF TOLERANCE

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 07/12/2019 07/17/2019
Note: Released By: TBAKER
SW1 COMPLETE 07/12/2019 07/12/2019
Note: Released By: JMUNSON
UD1 COMPLETE 07/12/2019 07/17/2019
Note: Released By: AHALL
ZON COMPLETE 07/12/2019 07/12/2019
Note: Released By: TDOAK

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 09/16/2019
SITE PLAN 20 ¤20.00 07/17/2019
SURCHARGE FS 533.721 ¤2.00 07/17/2019
SURCHARGE - FS 468.631 ¤2.00 07/17/2019
STORM WATER PERMIT FEES ¤40.00 07/17/2019
ADMIN FEE ¤20.00 07/17/2019
Fees Total Due: ¤0.00 Total Paid: ¤124.00