Permit #2019080520
Permit Details
Status: COED
| Parcel Id: 07-11-31-7035-00650-0130 |
| CONDITIONED SPACE: 1767 sqft |
| GARAGE: 484 sqft |
| OPENED PORCH (WITH ROOF) : 43 sqft |
| OPENED PORCH (WITH ROOF) : 269 sqft |
| Total Square Footage: 2563 sqft |
| Block: 00650 |
| Subdivision: 2172 - SECTION 35-BELLE TERRE |
| Job Phone: 386-447-4151 |
| Location Address: 59 BURROUGHS DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 08/22/2019 |
| NOC: RECORDED |
| Applicant name: GENE WARREN SLONE |
| Owner: FLORIDA GREEN CONSTRUCTION INC |
|
Address 50 LEANNI WAY STE C1 PALM COAST, FL 32137 |
| Lot: 0130 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
FLORIDA GREEN CONSTRUCTION INC.
| Status | Location Address | State License Number | Phone |
| INACTIVE |
870 E RETTA STREET DELEON SPRINGS, FL 32130 |
CBC1260957 (Exp: 08/31/2026) | 407-580-2657 |
Sub Contractors
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
GREGG A MCANALLY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE PALM COAST, FL 32092 |
CAC1815760 (Exp: 08/31/2022) | 904-829-8898 |
JOHN EDWARD GAMBONE
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 06/22/2020 | FINAL APPROVED | JCOLASANTI |
| U -UTILITY RESIDENTIAL FINAL | 05/29/2020 | APPROVED | AHALL |
| ROW - DRAINAGE | 05/28/2020 | APPROVED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION | |||
| ROW - STORMWATER FINAL | 05/28/2020 | APPROVED | MMAJEWSKI |
| ROW - FINAL APRON (AFTER POUR) | 05/28/2020 | APPROVED | MMAJEWSKI |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 05/26/2020 | APPROVED | MMAJEWSKI |
| FINAL SURVEY (OFFICE USE ONLY) | 05/26/2020 | APPROVED | MMAJEWSKI |
| ELECTRIC - EARLY POWER | 03/31/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 11:20 | |||
| ROW- PRE-APRON (PRE-POUR) | 03/25/2020 | APPROVED | RGROSS |
| Note: READY TO POUR | |||
| U - SEWER TIE IN | 03/10/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 03/10/2020 | APPROVED | JGIBSON |
| PEP TANK INSTALLATION REQUEST | 02/19/2020 | APPROVED | CSTONE |
| LATH/BRICK/ WATER BARRIER | 02/11/2020 | APPROVED | JCOLASANTI |
| INSULATION | 02/06/2020 | APPROVED | JCOLASANTI |
| ALL ROUGH | 01/29/2020 | APPROVED - AS NOTED | JCOLASANTI |
| Note: smoke det needs to be at least 3' horizontaly for bathroom with tub or shower FBC 314,,, need nail plate above electrical panel at ceiling | |||
| ROOF VALLEY & METAL | 12/17/2019 | APPROVED | JCOLASANTI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 12/11/2019 | APPROVED - AS NOTED | JCOLASANTI |
| Note: need collar ties each rafter at rear garage per plan...strap rafter to bottom truss rear left porch (marked on plans) will check at all rough | |||
| TIE BEAM / LINTEL | 11/15/2019 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| TIE BEAM / LINTEL | 11/14/2019 | CANCELLED BY APPLICANT | JCOLASANTI |
| Note: THIS IS A REINSPECTION per phne call | |||
| ROW - DRAINAGE | 11/14/2019 | Disapproved -FEE REQUIRED | RGROSS |
| Note: THIS IS A REINSPECTION. SWALE IN FRONT OF THE NEW HOME CONSTRUCTION NEEDS A ROUGH REGRADE OR TEMPORARY CULVERT TO ALLOW FOR DRAINAGE. SPOKE TO JOB SITE CONTACT. NEXT INSPECTION 11/21/19 | |||
| TIE BEAM / LINTEL | 11/12/2019 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: need dowels left wall at change nof height cells FBC 301.1.2 continous load path | |||
| FOUND SURVEY APPROVED (OFFICE) | 11/07/2019 | APPROVED | JMUNSON |
| ROW - DRAINAGE | 11/07/2019 | Disapproved -FEE REQUIRED | RGROSS |
| Note: SILT FENCE NEEDED. COMPLAINTS FROM NEIGHBORS PER SHELLEY FROM CODE. NO CULVERT OR REGRADE PERFORMED TO ALLOW FOR OPEN DRAINAGE ACROSS THE SITE. NEXT INSPECTION 11.14.19. | |||
| MONOLITHIC SLAB | 10/25/2019 | APPROVED | WMILLER |
| Note: THIS IS A REINSPECTION | |||
| MONOLITHIC SLAB | 10/23/2019 | Disapproved -FEE REQUIRED | WMILLER |
| Note: need compation report PER APPROVED PLANS FBC. [A] 107.3.1 | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 10/14/2019 | APPROVED | JGIBSON |
| ELECTRIC TEMP POLE | 09/23/2019 | APPROVED - AS NOTED | RMARTIN |
| Note: SPOKE TO FPL RELEASED POWER 3:40 | |||
| WATER METER INSTALLATION REQUEST | 09/19/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 11/06/2019 | 11/07/2019 |
| Note: Released By: JMUNSON | |||
| BLD | COMPLETE | 08/14/2019 | 08/22/2019 |
| Note: Released By: MGARRETT | |||
| CUSVC | COMPLETE | 08/14/2019 | 08/15/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 08/14/2019 | 08/16/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 08/14/2019 | 08/14/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 08/14/2019 | 08/21/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 08/14/2019 | 08/22/2019 |
| Note: Released By: MGARRETT | |||
| PLUM | COMPLETE | 08/14/2019 | 08/22/2019 |
| Note: Released By: MGARRETT | |||
| SW1 | COMPLETE | 08/14/2019 | 08/14/2019 |
| Note: Released By: JMUNSON | |||
| UD1 | COMPLETE | 08/14/2019 | 08/21/2019 |
| Note: Released By: LFITZGERALD PEP Tank areas new home This is a PEP Tank area. The panel and pep tank is to be placed on the same side of the building based on the Utility Marked Locations. Pep Panel will be placed 5 feet from the front corner of the building on the same side of the building as the PEP tank that is marked on the Utility marked Site plan. Make sure the electrician places the PEP power wire between 3 feet and 5 feet from the ground. The plumber should exit the slab with the sewer pipe on the side of the building the tank will be on and matching the utility marked site plan, this will reduce any piping under driveways or sidewalks and minimize the fall required. The sewer tie-in inspection must be called in the day before the tie-in. The morning of the tie-in the inspector should be contacted to coordinate the time of the tie-in visual inspection so he can witness the tie-in. All new Concrete work including Driveway Pavers must maintain at least a 4.5 feet clear zone from all Water / Reuse Meter Pits, sewer clean caps or Pep Tank lids and 9 feet behind the pep tank lids. All sewer cleanouts or valves located within the concrete area must be raised flush with the grade and sewer cleanouts must have a flush brass cap. | |||
| ZON | COMPLETE | 08/14/2019 | 08/14/2019 |
| Note: Released By: AMOBLEY | |||
| SWALE | COMPLETE | 08/14/2019 | 09/06/2019 |
| Note: Released By: TBAKER |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤500.00 | 08/22/2019 |
| SITE PLAN 20 | ¤20.00 | 08/22/2019 |
| SURCHARGE FS 533.721 | ¤11.70 | 08/22/2019 |
| SURCHARGE - FS 468.631 | ¤17.55 | 08/22/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 08/22/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 08/22/2019 |
| SEWER CREDIT | (¤850.00) | 08/22/2019 |
| SEWER INSPECTION | ¤25.00 | 08/22/2019 |
| SEWER CAPITAL FACILITY | ¤4,515.25 | 08/22/2019 |
| WATER CAPITAL FACILITY FEE | ¤3,314.84 | 08/22/2019 |
| METER - DEPOSIT | ¤60.00 | 08/22/2019 |
| WATER- TURN ON | ¤25.00 | 08/22/2019 |
| ADMIN FEE | ¤20.00 | 08/22/2019 |
| CONNECTION FEES | ¤985.25 | 08/22/2019 |
| ELECTRIC FEE | ¤210.00 | 08/22/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 08/22/2019 |
| IMPACT FEE FIRE | ¤223.38 | 08/22/2019 |
| IMPACT FEE PARKS | ¤849.24 | 08/22/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 08/22/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 08/22/2019 |
| MECHANICAL FEE | ¤210.00 | 08/22/2019 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 08/22/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 08/22/2019 |
| PLAN CHECK FEE | ¤100.00 | 08/22/2019 |
| PLUMBING FEE | ¤210.00 | 08/22/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,863.07 |