Permit #2019080774
Permit Details
Status: COED
| Parcel Id: 07-11-31-7031-00180-0050 |
| CONDITIONED SPACE: 2347 sqft |
| GARAGE: 412 sqft |
| SCREEN PORCH (SOLID ROOF) : 240 sqft |
| OPENED PORCH (WITH ROOF) : 72 sqft |
| Total Square Footage: 3071 sqft |
| Block: 00180 |
| Subdivision: 2166 - SECTION 31-ROYAL PALMS |
| Job Phone: 386-960-7720 |
| Location Address: 2 RIDDLE PL |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/10/2019 |
| NOC: RECORDED |
| Applicant name: LAWRENCE FRED SIETSMA |
| Owner: AVTEC HOMES INC |
|
Address 620 MALABAR ROAD, STE 5 PALM BAY, FL 32907 |
| Lot: 0050 |
| Contracted Stated Job Value: ¤270,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
AVTEC HOMES INC
| Status | Location Address | State License Number | Phone |
| CANCEL |
2405 E GRAVES AVE ORANGE CITY, FL 32763 |
CRC041905 (Exp: 08/31/2024) | 386-960-7720 |
Sub Contractors
STEVEN JAY SMITH
| Status | Location Address | State License Number | Phone |
| INACTIVE |
104 West Cedar Avenue Orange City, FL 32763 |
EC0001542 (Exp: 08/31/2022) | (386)775-7776 |
BRUCE R BOLTON
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| CANCEL |
1982 SR 44 NEW SMYRNA BEACH, FL 32168 |
SUITE 357 NEW SMYRNA BEACH, FL 32168 |
CAC1817407 (Exp: 08/31/2022) | 386-216-5975 | 386-402-4191 |
RUSSELL J CARTER
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 302 DELAND, FL 32721 |
CFC1425938 (Exp: 08/31/2026) | 386-736-4220 | 386-736-4219 |
DOUGLAS EDWARD RICHARDS
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
108 E INDIANA AVENUE DELAND, FL 32724 |
CCC1328824 (Exp: 08/31/2024) | 386-736-4226 | 386-740-0535 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 03/16/2020 | FINAL APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Vacuum Breaker missing on Water Heater as per code. Insulation calc missing Proof of termite bond not posted on electrical panel. | |||
| BLD - BUILDING FINAL | 03/12/2020 | Disapproved - NO FEE | FWILLIS |
| Note: Vacuum Breaker missing on Water Heater as per code. Insulation calc missing Proof of termite bond not posted on electrical panel. | |||
| U -UTILITY RESIDENTIAL FINAL | 03/12/2020 | FINAL APPROVED | LFITZGERALD |
| ROW - STORMWATER FINAL | 03/11/2020 | APPROVED | MMAJEWSKI |
| ROW - FINAL APRON (AFTER POUR) | 03/11/2020 | APPROVED | MMAJEWSKI |
| ROW - STORMWATER FINAL | 03/10/2020 | CANCELLED BY APPLICANT | WEB |
| ROW - FINAL APRON (AFTER POUR) | 03/10/2020 | CANCELLED BY APPLICANT | WEB |
| ROW - FINAL APRON (AFTER POUR) | 03/09/2020 | CANCELLED BY APPLICANT | WEB |
| ROW - STORMWATER FINAL | 03/09/2020 | CANCELLED BY APPLICANT | WEB |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/06/2020 | APPROVED | MMAJEWSKI |
| ROW - STORMWATER FINAL | 03/06/2020 | CANCELLED BY APPLICANT | WEB |
| FINAL SURVEY (OFFICE USE ONLY) | 03/06/2020 | APPROVED | MMAJEWSKI |
| ROW - FINAL APRON (AFTER POUR) | 02/21/2020 | CANCELLED BY APPLICANT | WEB |
| ROW- PRE-APRON (PRE-POUR) | 02/12/2020 | APPROVED - AS NOTED | MMAJEWSKI |
| Note: THIS IS A REINSPECTION. It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. | |||
| ROW- PRE-APRON (PRE-POUR) | 02/11/2020 | Disapproved - NO FEE | MMAJEWSKI |
| Note: TOP OF APRON FORMS NEED TO BE 18 INCHES FROM EDGE OF CULVERT PIPE | |||
| U - SEWER TIE IN | 01/27/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 01/27/2020 | APPROVED | JGIBSON |
| ELECTRIC - EARLY POWER | 01/22/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 10:20 | |||
| PEP TANK INSTALLATION REQUEST | 01/13/2020 | APPROVED | CSTONE |
| PEP TANK INSTALLATION REQUEST | 01/10/2020 | CANCELLED BY APPLICANT | WEB |
| INSULATION | 12/13/2019 | APPROVED | WMILLER |
| LATH/BRICK/ WATER BARRIER | 12/11/2019 | APPROVED | FWILLIS |
| ALL ROUGH | 12/10/2019 | APPROVED - AS NOTED | JDELBONIS |
| Note: nail plats at dryer vent and in closet for tub supply lines | |||
| ALL ROUGH | 12/09/2019 | CANCELLED BY APPLICANT | WEB |
| ROOF VALLEY & METAL | 12/04/2019 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/25/2019 | APPROVED | FWILLIS |
| TIE BEAM / LINTEL | 11/14/2019 | APPROVED | WMILLER |
| FOUND SURVEY APPROVED (OFFICE) | 11/13/2019 | APPROVED | JMUNSON |
| MONOLITHIC SLAB | 10/24/2019 | APPROVED | JDELBONIS |
| MONOLITHIC SLAB | 10/23/2019 | CANCELLED BY APPLICANT | WEB |
| MONOLITHIC SLAB | 10/22/2019 | CANCELLED BY APPLICANT | WEB |
| PLUMBING 1ST ROUGH UNDERGROUND | 10/16/2019 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 09/26/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| SW1 | COMPLETE | 11/12/2019 | 11/12/2019 |
| Note: Released By: CTROHA | |||
| SW1 | HOLD | 11/08/2019 | 11/12/2019 |
| Note: Held By: CTROHA Move drainage conveyance into the property so to maintain a 4:1 slope at rear property line along developed lot | |||
| ZON | COMPLETE | 09/05/2019 | 09/06/2019 |
| Note: Released By: AMOBLEY | |||
| SWALE | COMPLETE | 08/22/2019 | 09/13/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 08/20/2019 | 08/27/2019 |
| Note: Released By: MGARRETT | |||
| CUSVC | COMPLETE | 08/20/2019 | 08/23/2019 |
| Note: Released By: AROSCOE | |||
| ELEC | COMPLETE | 08/20/2019 | 08/22/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 08/20/2019 | 08/22/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 08/20/2019 | 08/26/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 08/20/2019 | 08/27/2019 |
| Note: Released By: MGARRETT | |||
| PLUM | COMPLETE | 08/20/2019 | 08/27/2019 |
| Note: Released By: MGARRETT | |||
| SW1 | COMPLETE | 08/20/2019 | 08/21/2019 |
| Note: Released By: JMUNSON | |||
| UD1 | COMPLETE | 08/20/2019 | 08/27/2019 |
| Note: Released By: AHALL | |||
| ZON | HOLD | 08/20/2019 | 08/21/2019 |
| Note: Held By: ELENS Window banding is required on right elevation facing right of way. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| METER - DEPOSIT | ¤60.00 | 09/10/2019 |
| WATER- TURN ON | ¤25.00 | 09/10/2019 |
| ADMIN FEE | ¤20.00 | 09/10/2019 |
| CONNECTION FEES | ¤985.25 | 09/10/2019 |
| ELECTRIC FEE | ¤234.00 | 09/10/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 09/10/2019 |
| IMPACT FEE FIRE | ¤223.38 | 09/10/2019 |
| IMPACT FEE PARKS | ¤849.24 | 09/10/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 09/10/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 09/10/2019 |
| MECHANICAL FEE | ¤234.00 | 09/10/2019 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 09/10/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 09/10/2019 |
| PLAN CHECK FEE | ¤116.00 | 09/10/2019 |
| PLUMBING FEE | ¤234.00 | 09/10/2019 |
| NEW RESIDENTIAL INSPECTIONS | ¤580.00 | 09/10/2019 |
| SITE PLAN 20 | ¤20.00 | 09/10/2019 |
| SURCHARGE FS 533.721 | ¤13.22 | 09/10/2019 |
| SURCHARGE - FS 468.631 | ¤19.83 | 09/10/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/10/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 09/10/2019 |
| SEWER CREDIT | (¤1,806.00) | 09/10/2019 |
| SEWER INSPECTION | ¤25.00 | 09/10/2019 |
| SEWER CAPITAL FACILITY | ¤4,515.25 | 09/10/2019 |
| WATER CAPITAL FACILITY FEE | ¤3,314.84 | 09/10/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤14,918.87 |