Permit #2019090823
Permit Details
Status: COED
| Parcel Id: 07-11-31-7025-00700-0030 |
| CONDITIONED SPACE: 1675 sqft |
| OPENED PORCH (WITH ROOF) : 112 sqft |
| OPENED PORCH (WITH ROOF) : 45 sqft |
| GARAGE: 442 sqft |
| Total Square Footage: 2274 sqft |
| Block: 00700 |
| Subdivision: 2189 - SECTION 25-PINE GROVE |
| Job Phone: 407-807-0656 |
| Location Address: 55 PALMWOOD DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/28/2019 |
| NOC: RECORDED |
| Applicant name: NAVIN SUGRIM |
| Owner: DLP BRITE HOMES LLC |
|
Address 605 PALENCIA CLUB DRIVE ST AUGUSTINE, FL 32095 |
| Lot: 0030 |
| Contracted Stated Job Value: ¤124,779.00 |
| Job Description: single family residence |
| Type: CN |
Contractor
DLP BUILDERS LLC
| Status | Location Address | State License Number | Phone |
| CANCEL |
7345 GREENBRIAR PKWY ORLANDO, FL 32819 |
CBC1263567 (Exp: 08/31/2022) | 407-807-0656 |
Sub Contractors
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
ROBERT G DELLO RUSSO
| Status | Location Address | State License Number | Phone | Fax |
| DECEASED |
531 CODISCO WAY SANFORD, FL 32771 |
CAC032448 (Exp: 08/31/2022) | (407)831-2665 | (407)333-3853 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 07/14/2020 | FINAL APPROVED | MMESSER |
| U -UTILITY RESIDENTIAL FINAL | 06/24/2020 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL APRON (AFTER POUR) | 06/19/2020 | APPROVED | KHOWELL |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 06/19/2020 | APPROVED | KHOWELL |
| ROW - STORMWATER FINAL | 06/19/2020 | FINAL APPROVED | KHOWELL |
| FINAL SURVEY (OFFICE USE ONLY) | 06/19/2020 | APPROVED | KHOWELL |
| ELECTRIC - EARLY POWER | 05/18/2020 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 11:30 | |||
| ROW- PRE-APRON (PRE-POUR) | 05/11/2020 | APPROVED | RGROSS |
| Note: READY TO POUR | |||
| U - SEWER TIE IN | 04/22/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 04/22/2020 | APPROVED | JGIBSON |
| LATH/BRICK/ WATER BARRIER | 03/26/2020 | APPROVED | JCOLASANTI |
| INSULATION | 03/24/2020 | APPROVED | JDELBONIS |
| ELECTRIC-TUG | 03/20/2020 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 10:05 am. | |||
| ALL ROUGH | 03/19/2020 | APPROVED | JCOLASANTI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/12/2020 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ROOF VALLEY & METAL | 02/25/2020 | APPROVED | JCOLASANTI |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/25/2020 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: need bolts and washers in middle bearing wall per plan | |||
| TIE BEAM / LINTEL | 02/12/2020 | APPROVED | JCOLASANTI |
| FOUND SURVEY APPROVED (OFFICE) | 02/11/2020 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 01/29/2020 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| MONOLITHIC SLAB | 01/27/2020 | Disapproved -FEE REQUIRED | JDELBONIS |
| Note: no compaction report roots in footing dirt tuching rebar COMPACTION AND TERMITE TREATMENT NOTIFICATION IN BOX 1816.1.7 FBC Termite Protection intention of or completion prior to slab. R318.1.7 CLEARANCE ON REBAR FROM EARTH 3” FBC R404.1.3.3.7.4 (6TH EDITION) | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 01/21/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 01/16/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 02/07/2020 | 02/11/2020 |
| Note: Released By: TBAKER | |||
| ENGIN1 | HOLD | 01/31/2020 | 01/31/2020 |
| Note: Held By: TBAKER Please show garage slab elevation on foundation survey | |||
| SWALE | COMPLETE | 09/25/2019 | 10/21/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 09/23/2019 | 09/30/2019 |
| Note: Released By: MGARRETT | |||
| CUSVC | COMPLETE | 09/23/2019 | 09/25/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 09/23/2019 | 09/25/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 09/23/2019 | 09/25/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 09/23/2019 | 09/30/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 09/23/2019 | 09/30/2019 |
| Note: Released By: MGARRETT | |||
| PLUM | COMPLETE | 09/23/2019 | 09/30/2019 |
| Note: Released By: MGARRETT | |||
| SW1 | COMPLETE | 09/23/2019 | 09/24/2019 |
| Note: Released By: JMUNSON | |||
| UD1 | COMPLETE | 09/23/2019 | 10/01/2019 |
| Note: Released By: AHALL | |||
| ZON | COMPLETE | 09/23/2019 | 09/24/2019 |
| Note: Released By: AMOBLEY |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 05/06/2020 |
| REINSPECTION FEE | ¤40.00 | 05/06/2020 |
| REINSPECTION FEE | ¤40.00 | 02/21/2020 |
| METER - DEPOSIT | ¤60.00 | 10/28/2019 |
| WATER- TURN ON | ¤25.00 | 10/28/2019 |
| ADMIN FEE | ¤20.00 | 10/28/2019 |
| CONNECTION FEES | ¤985.25 | 10/28/2019 |
| NEW RESIDENTIAL INSPECTIONS | ¤420.00 | 10/28/2019 |
| SITE PLAN 20 | ¤20.00 | 10/28/2019 |
| SURCHARGE FS 533.721 | ¤10.18 | 10/28/2019 |
| SURCHARGE - FS 468.631 | ¤15.27 | 10/28/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/28/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 10/28/2019 |
| SEWER CREDIT | (¤958.00) | 10/28/2019 |
| SEWER INSPECTION | ¤25.00 | 10/28/2019 |
| SEWER CAPITAL FACILITY | ¤4,515.25 | 10/28/2019 |
| WATER CAPITAL FACILITY FEE | ¤3,314.84 | 10/28/2019 |
| ELECTRIC FEE | ¤186.00 | 10/28/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 10/28/2019 |
| IMPACT FEE FIRE | ¤223.38 | 10/28/2019 |
| IMPACT FEE PARKS | ¤849.24 | 10/28/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 10/28/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 10/28/2019 |
| MECHANICAL FEE | ¤186.00 | 10/28/2019 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/28/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 10/28/2019 |
| PLAN CHECK FEE | ¤84.00 | 10/28/2019 |
| PLUMBING FEE | ¤186.00 | 10/28/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,543.27 |