Permit #2019100838
Permit Details
Status: COED
| Parcel Id: 07-11-31-7018-00130-0080 |
| CONDITIONED SPACE: 1845 sqft |
| GARAGE: 483 sqft |
| OPENED PORCH (WITH ROOF) : 43 sqft |
| OPENED PORCH (WITH ROOF) : 269 sqft |
| Total Square Footage: 2640 sqft |
| Block: 00130 |
| Subdivision: 2181 - SECTION 18-WYNNFIELD |
| Job Phone: 386-447-4151 |
| Location Address: 13 WINCHESTER PL |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 11/12/2019 |
| NOC: RECORDED |
| Applicant name: GENE WARREN SLONE |
| Owner: SANDULESCU STANISLAV |
|
Address 7114 HEALY DR SPRINGFIELD, VA 22150 |
| Lot: 0080 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: Single Family Residence |
| Type: CN |
Contractor
FLORIDA GREEN CONSTRUCTION INC.
| Status | Location Address | State License Number | Phone |
| INACTIVE |
870 E RETTA STREET DELEON SPRINGS, FL 32130 |
CBC1260957 (Exp: 08/31/2026) | 407-580-2657 |
Sub Contractors
GREGG A MCANALLY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE PALM COAST, FL 32092 |
CAC1815760 (Exp: 08/31/2022) | 904-829-8898 |
JOHN EDWARD GAMBONE
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 07/14/2020 | FINAL APPROVED | WMILLER |
| U -UTILITY RESIDENTIAL FINAL | 07/09/2020 | FINAL APPROVED | MBACON |
| ROW - STORMWATER FINAL | 07/08/2020 | APPROVED | RGROSS |
| ROW - FINAL APRON (AFTER POUR) | 07/08/2020 | APPROVED | RGROSS |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 07/02/2020 | APPROVED | RGROSS |
| FINAL SURVEY (OFFICE USE ONLY) | 07/02/2020 | APPROVED | RGROSS |
| ROW- PRE-APRON (PRE-POUR) | 05/22/2020 | APPROVED | RGROSS |
| ELECTRIC - EARLY POWER | 05/14/2020 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 9:30 am | |||
| GRAVITY SEWER TEST | 05/08/2020 | APPROVED | JGIBSON |
| U - SEWER TIE IN | 05/08/2020 | APPROVED | JGIBSON |
| LATH/BRICK/ WATER BARRIER | 03/18/2020 | APPROVED | JCOLASANTI |
| INSULATION | 03/06/2020 | APPROVED | JCOLASANTI |
| ALL ROUGH | 03/03/2020 | APPROVED | JCOLASANTI |
| ROOF VALLEY & METAL | 02/11/2020 | APPROVED | JCOLASANTI |
| LATH/BRICK/ WATER BARRIER | 02/11/2020 | CANCELLED BY APPLICANT | WEB |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/06/2020 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/05/2020 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: engineering not complete | |||
| TIE BEAM / LINTEL | 01/28/2020 | APPROVED | JCOLASANTI |
| FOUND SURVEY APPROVED (OFFICE) | 01/27/2020 | APPROVED | CMORALES |
| MONOLITHIC SLAB | 01/08/2020 | APPROVED | JCOLASANTI |
| Note: THIS IS A REINSPECTION | |||
| MONOLITHIC SLAB | 01/07/2020 | Disapproved -FEE REQUIRED | JCOLASANTI |
| Note: cannot use main footer steel in place of four #5 each way footer steel per plan (rear right and check all) | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 12/31/2019 | APPROVED | JCOLASANTI |
| ELECTRIC TEMP POLE | 12/04/2019 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 11:00 | |||
| WATER METER INSTALLATION REQUEST | 12/02/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 01/23/2020 | 01/27/2020 |
| Note: Released By: CMORALES Foundation Survey | |||
| ZON | COMPLETE | 11/08/2019 | 11/12/2019 |
| Note: Released By: AMOBLEY | |||
| SWALE | COMPLETE | 10/23/2019 | 12/04/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 10/21/2019 | 10/29/2019 |
| Note: Released By: MGARRETT | |||
| CUSVC | COMPLETE | 10/21/2019 | 10/22/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 10/21/2019 | 10/22/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 10/21/2019 | 10/23/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 10/21/2019 | 10/23/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 10/21/2019 | 10/24/2019 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 10/21/2019 | 10/29/2019 |
| Note: Released By: MGARRETT | |||
| SW1 | COMPLETE | 10/21/2019 | 10/25/2019 |
| Note: Released By: JMUNSON | |||
| UD1 | COMPLETE | 10/21/2019 | 10/23/2019 |
| Note: Released By: AHALL | |||
| ZON | HOLD | 10/21/2019 | 10/22/2019 |
| Note: Held By: AMOBLEY Please specify type of magnolia on landscape |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| REINSPECTION FEE | ¤40.00 | 05/28/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤500.00 | 11/12/2019 |
| SITE PLAN 20 | ¤20.00 | 11/12/2019 |
| SURCHARGE FS 533.721 | ¤11.70 | 11/12/2019 |
| SURCHARGE - FS 468.631 | ¤17.55 | 11/12/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 11/12/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤48.96) | 11/12/2019 |
| SEWER CREDIT | (¤1,147.00) | 11/12/2019 |
| SEWER INSPECTION | ¤25.00 | 11/12/2019 |
| SEWER CAPITAL FACILITY | ¤4,515.25 | 11/12/2019 |
| WATER CAPITAL FACILITY FEE | ¤3,314.84 | 11/12/2019 |
| METER - DEPOSIT | ¤60.00 | 11/12/2019 |
| WATER- TURN ON | ¤25.00 | 11/12/2019 |
| ADMIN FEE | ¤20.00 | 11/12/2019 |
| CONNECTION FEES | ¤985.25 | 11/12/2019 |
| ELECTRIC FEE | ¤210.00 | 11/12/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 11/12/2019 |
| IMPACT FEE FIRE | ¤223.38 | 11/12/2019 |
| IMPACT FEE PARKS | ¤849.24 | 11/12/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 11/12/2019 |
| IMPACT FEE TRANSPORTATION | ¤1,632.00 | 11/12/2019 |
| MECHANICAL FEE | ¤210.00 | 11/12/2019 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 11/12/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 11/12/2019 |
| PLAN CHECK FEE | ¤100.00 | 11/12/2019 |
| PLUMBING FEE | ¤210.00 | 11/12/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,486.07 |