Permit #2019110145
Permit Details
Status: COED
| Parcel Id: 35-11-31-4075-00000-1220 |
| CONDITIONED SPACE: 2395 sqft |
| GARAGE: 548 sqft |
| OPENED PORCH (WITH ROOF) : 239 sqft |
| OPENED PORCH (WITH ROOF) : 126 sqft |
| Total Square Footage: 3308 sqft |
| Block: 0 |
| Subdivision: 2296 - MARINA DEL PALMA SUBDIVISION |
| Job Phone: 386-947-4481 |
| Location Address: 17 RIO VISTA DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 11/21/2019 |
| NOC: RECORDED |
| Applicant name: ERIC CHRISTOPHER OLSEN |
| Owner: MASTIN DONA |
|
Address 4000 ISLAND BLVD, #2903 AVENTURA, FL 33160 |
| Lot: 1220 |
| Contracted Stated Job Value: ¤430,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
OLSEN CUSTOM HOMES AND CONSULTING INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
CGC1508852 (Exp: 08/31/2026) | 386-947-4481 | (386)947-4484 |
Sub Contractors
BERT S MCLAUGHLIN
| Status | Location Address | State License Number | Phone |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
EC13006455 (Exp: 08/31/2026) | 386-265-2687 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
JEFFREY DALE KNIGHT
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
923 ASHMEADE CT PORT ORANGE, FL 32127 |
CFC057351 (Exp: 08/31/2026) | 386-345-3857 | 386-345-4443 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
Inspection History
| Type | Request Date | Result | Inspector |
| FINAL SURVEY (OFFICE USE ONLY) | 05/15/2020 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION NOT ENOUGH ELEVATION GRADE SHOTS ALONG THE SIDE OF THE HOUSE TO SHOW THE DRAINAGE CONVEYANCE. | |||
| ROW - FINAL APRON (AFTER POUR) | 05/15/2020 | APPROVED | RGROSS |
| ROW - STORMWATER FINAL | 05/15/2020 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION SECOND PART OF THE PRE POUR INSPECTION MUST BE APPROVED BEFORE FINAL STORMWATER CAN BE APPROVED. | |||
| U -UTILITY RESIDENTIAL FINAL | 05/15/2020 | APPROVED | AHALL |
| FINAL SURVEY (OFFICE USE ONLY) | 05/13/2020 | Disapproved - NO FEE | RGROSS |
| Note: NOT ENOUGH ELEVATION GRADE SHOTS ALONG THE SIDE OF THE HOUSE TO SHOW THE DRAINAGE CONVEYANCE. ON SITE WITH SUPER. | |||
| BLD - BUILDING FINAL | 05/13/2020 | Approval - Private Provider | PPROVIDER |
| ROW - FINAL APRON (AFTER POUR) | 05/07/2020 | CANCELLED BY APPLICANT | WEB |
| Note: THIS IS A REINSPECTION SECOND PART OF THE PRE POUR MUST BE APPROVED BEFORE FINAL APRON INSPECTION. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/07/2020 | APPROVED - AS NOTED | RGROSS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION APPROVED FOR CONRETE APRON, SIDEWALK, AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY PAVERS ALREADY PLACED. SECOND PART OF THE PRE POUR MUST BE CALLED IN BEFORE THE PAVERS ARE PLACED TO VERIFY PAVER BASE IS THICK ENOUGH AND PAVER RESTRAINTS IN PLACE TO CODE. sSITE MEET WITH BUILDER EXPLAINING THE REASON AND IMPORTANCE OF THE 2ND PART OF THE PRE POUR. | |||
| ROW- PRE-APRON (PRE-POUR) | 05/04/2020 | Disapproved -FEE REQUIRED | RGROSS |
| Note: THIS IS A REINSPECTION APPROVED FOR CONRETE APRON, SIDEWALK, AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY PAVERS ALREADY PLACED. SECOND PART OF THE PRE POUR MUST BE CALLED IN BEFORE THE PAVERS ARE PLACED TO VERIFY PAVER BASE IS THICK ENOUGH AND PAVER RESTRAINTS IN PLACE TO CODE. | |||
| ROW - FINAL APRON (AFTER POUR) | 05/04/2020 | Disapproved -FEE REQUIRED | RGROSS |
| Note: SECOND PART OF THE PRE POUR MUST BE APPROVED BEFORE FINAL APRON INSPECTION. | |||
| ROW - STORMWATER FINAL | 05/04/2020 | Disapproved - NO FEE | RGROSS |
| Note: SECOND PART OF THE PRE POUR INSPECTION MUST BE APPROVED BEFORE FINAL STORMWATER CAN BE APPROVED. | |||
| ELECTRIC - EARLY POWER | 04/20/2020 | Approval - Private Provider | PPROVIDER |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/20/2020 | CANCELLED BY INSPECTOR | RGROSS |
| Note: INSPECTOR CANCLED BECAUSE INSPECTION WAS ADDED BY INSPECTOR PREMATURELY | |||
| ROW- PAVER RESTRAINTS | 03/20/2020 | APPROVED | RGROSS |
| ROW- PRE-APRON (PRE-POUR) | 03/20/2020 | PARTIALLY APPROVED | RGROSS |
| Note: APPROVED FOR CONRETE APRON, SIDEWALK, AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY | |||
| INSULATION | 03/05/2020 | Approval - Private Provider | PPROVIDER |
| LATH/BRICK/ WATER BARRIER | 03/03/2020 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 03/03/2020 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 03/03/2020 | Approval - Private Provider | PPROVIDER |
| ELECTRIC-TUG | 02/19/2020 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 02/12/2020 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/06/2020 | Approval - Private Provider | BBEMBRY |
| FOUND SURVEY APPROVED (OFFICE) | 01/17/2020 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 12/27/2019 | CANCELLED BY APPLICANT | WEB |
| MONOLITHIC SLAB | 12/27/2019 | Approval - Private Provider | PPROVIDER |
| GRAVITY SEWER TEST | 12/18/2019 | APPROVED | JGIBSON |
| U - SEWER TIE IN | 12/18/2019 | CANCELLED BY APPLICANT | WEB |
| U - SEWER TIE IN | 12/18/2019 | APPROVED | JGIBSON |
| PLUMBING 1ST ROUGH UNDERGROUND | 12/16/2019 | Approval - Private Provider | PPROVIDER |
| WATER METER INSTALLATION REQUEST | 12/02/2019 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 01/16/2020 | 01/17/2020 |
| Note: Released By: TBAKER Foundation Survey | |||
| SW1 | COMPLETE | 11/18/2019 | 11/18/2019 |
| Note: Released By: CTROHA | |||
| ZON | COMPLETE | 11/18/2019 | 11/18/2019 |
| Note: Released By: AMOBLEY | |||
| UD1 | COMPLETE | 11/18/2019 | 11/21/2019 |
| Note: Released By: AHALL | |||
| ENGIN1 | COMPLETE | 11/18/2019 | 11/21/2019 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 11/05/2019 | 11/15/2019 |
| Note: Released By: PBUCKLEY | |||
| CUSVC | COMPLETE | 11/05/2019 | 11/06/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 11/05/2019 | 11/08/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 11/05/2019 | 11/05/2019 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 11/05/2019 | 11/07/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 11/05/2019 | 11/06/2019 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 11/05/2019 | 11/15/2019 |
| Note: Released By: PBUCKLEY | |||
| SW1 | HOLD | 11/05/2019 | 11/06/2019 |
| Note: Held By: JMUNSON Need to show the proposed drainage elevations. ULDC Tech Manual Sec 5 300. | |||
| UD1 | COMPLETE | 11/05/2019 | 11/12/2019 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 11/05/2019 | 11/06/2019 |
| Note: Held By: AMOBLEY This lot has two firm panel numbers survey should list them both Survey/Site plan should specify driveway material being used Survey/Site plan must have total lot square footage listed AC pad must be shown on Survey/Site plan |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 05/15/2020 |
| REINSPECTION FEE | ¤40.00 | 05/15/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤860.00 | 11/21/2019 |
| SITE PLAN 20 | ¤20.00 | 11/21/2019 |
| SURCHARGE FS 533.721 | ¤18.54 | 11/21/2019 |
| SURCHARGE - FS 468.631 | ¤27.81 | 11/21/2019 |
| STORM WATER PERMIT FEES | ¤80.00 | 11/21/2019 |
| 3% TRANS IMPACT FEE CREDIT | (¤89.43) | 11/21/2019 |
| SEWER INSPECTION | ¤25.00 | 11/21/2019 |
| SEWER CAPITAL FACILITY | ¤2,389.36 | 11/21/2019 |
| WATER CAPITAL FACILITY FEE | ¤2,234.43 | 11/21/2019 |
| METER - DEPOSIT | ¤60.00 | 11/21/2019 |
| WATER-METER | ¤434.59 | 11/21/2019 |
| ADMIN FEE | ¤20.00 | 11/21/2019 |
| CONNECTION FEES | ¤25.00 | 11/21/2019 |
| ELECTRIC FEE | ¤318.00 | 11/21/2019 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 11/21/2019 |
| IMPACT FEE FIRE | ¤223.38 | 11/21/2019 |
| IMPACT FEE PARKS | ¤849.24 | 11/21/2019 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 11/21/2019 |
| IMPACT FEE TRANSPORTATION | ¤2,981.00 | 11/21/2019 |
| MECHANICAL FEE | ¤318.00 | 11/21/2019 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 11/21/2019 |
| PLAN CHECK FEE | ¤172.00 | 11/21/2019 |
| PLUMBING FEE | ¤318.00 | 11/21/2019 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤14,932.74 |