I want to search for...
Permit #2019120812
Permit Details
Status: COED
| Parcel Id: 48-11-31-1710-00000-0150 |
| CONDITIONED SPACE: 3021 sqft |
| GARAGE: 792 sqft |
| OPENED PORCH (WITH ROOF) : 440 sqft |
| OPENED PORCH (WITH ROOF) : 71 sqft |
| Total Square Footage: 4324 sqft |
| Block: 00000 |
| Subdivision: 2087 - ESTATES AT GRAND HAVEN PHASE II |
| Job Phone: 386-947-4481 |
| Location Address: 206 WILLOW OAK WAY |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 01/24/2020 |
| NOC: RECORDED |
| Applicant name: ERIC CHRISTOPHER OLSEN |
| Owner: BLINN DONALD & PATRICIA H&W |
|
Address 26 LAKESIDE DRIVE PALM COAST, FL 32137 |
| Lot: 0150 |
| Contracted Stated Job Value: ¤519,200.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
OLSEN CUSTOM HOMES AND CONSULTING INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
CGC1508852 (Exp: 08/31/2026) | 386-947-4481 | (386)947-4484 |
Sub Contractors
BERT S MCLAUGHLIN
| Status | Location Address | State License Number | Phone |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
EC13006455 (Exp: 08/31/2026) | 386-265-2687 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
JEFFREY DALE KNIGHT
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
923 ASHMEADE CT PORT ORANGE, FL 32127 |
CFC057351 (Exp: 08/31/2026) | 386-345-3857 | 386-345-4443 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
MARK A RUGGIERO
| Status | Location Address | State License Number | Phone |
| INACTIVE |
411 6TH STREET HOLLY HILL , FL 32117 |
01612 (Exp: 07/23/2023) | 386-252-5555 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 08/03/2020 | FINAL APPROVED | LFITZGERALD |
| U-CROSS CONNECTION | 07/31/2020 | APPROVED | LFITZGERALD |
| ROW - STORMWATER FINAL | 07/30/2020 | APPROVED | RGROSS |
| ROW - FINAL APRON (AFTER POUR) | 07/30/2020 | APPROVED | RGROSS |
| FINAL SURVEY (OFFICE USE ONLY) | 07/29/2020 | Disapproved - NO FEE | RGROSS |
| Note: THIS IS A REINSPECTION SOD MUST BE PLACED BEFORE FINAL SURVEY CAN BE ACCURATELY COMPLETE. 7/29/20 - Existing interior elevations on a 20’ grid needed. (E). As well as outside finished sod elevations near the foundation. Land Development Code Technical Manual, Section 300.01 (A)(1)(B)(6) | |||
| BLD - BUILDING FINAL | 07/27/2020 | Approval - Private Provider | PPROVIDER |
| Note: THIS IS A REINSPECTION ADDED ON 7/23/2020 2:23:32 PM | |||
| BLD - BUILDING FINAL | 07/23/2020 | Disapproved- Private Provider | PPROVIDER |
| FINAL SURVEY (OFFICE USE ONLY) | 07/20/2020 | Disapproved - NO FEE | RGROSS |
| Note: SOD MUST BE PLACED BEFORE FINAL SURVEY CAN BE ACCURATELY COMPLETE. | |||
| GRAVITY SEWER TEST | 07/16/2020 | APPROVED | JGIBSON |
| U - SEWER TIE IN | 07/16/2020 | APPROVED - AS NOTED | JGIBSON |
| Note: PALM COAST UTILITY DEPARTMENT MADE U-SEWER TIE IN CONNECTION | |||
| ROW- PRE-APRON (PRE-POUR) | 07/10/2020 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION APPROVED FOR THE APRON AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY 7/9/20 7:35am - NO PAVERS SHOULD BE PLACED UNTIL THIS 2ND PART OF THE PRE POUR HAS BEEN APPROVED. 7/10/20 - READY FOR PAVERS | |||
| ROW- PRE-APRON (PRE-POUR) | 07/09/2020 | Disapproved -FEE REQUIRED | RGROSS |
| Note: THIS IS A REINSPECTION APPROVED FOR THE APRON AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY 7/9/20 7:35am - NO PAVERS SHOULD BE PLACED UNTIL THIS 2ND PART OF THE PRE POUR HAS BEEN APPROVED. | |||
| FINAL SURVEY (OFFICE USE ONLY) | 07/03/2020 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION SOD MUST BE PLACED BEFORE FINAL SURVEY CAN BE ACCURATELY COMPLETE. 7/29/20 - Existing interior elevations on a 20’ grid needed. (E). As well as outside finished sod elevations near the foundation. Land Development Code Technical Manual, Section 300.01 (A)(1)(B)(6) | |||
| ROW- PAVER RESTRAINTS | 06/24/2020 | APPROVED | RGROSS |
| ROW- PRE-APRON (PRE-POUR) | 06/24/2020 | PARTIALLY APPROVED | RGROSS |
| Note: APPROVED FOR THE APRON AND PAVER RESTRAINTS ONLY. PAVER DRIVEWAY | |||
| U - SEWER TIE IN | 06/23/2020 | CANCELLED BY APPLICANT | WEB |
| GRAVITY SEWER TEST | 06/23/2020 | CANCELLED BY APPLICANT | WEB |
| Note: THIS IS A REINSPECTION | |||
| ELECTRIC - EARLY POWER | 06/01/2020 | Approval - Private Provider | PPROVIDER |
| ELEV CERT-FOUNDATION APPROVAL | 04/13/2020 | APPROVED | JMYERS |
| LATH/BRICK/ WATER BARRIER | 04/08/2020 | Approval - Private Provider | PPROVIDER |
| INSULATION | 04/08/2020 | Approval - Private Provider | PPROVIDER |
| GAS ROUGH | 04/06/2020 | Approval - Private Provider | PPROVIDER |
| ALL ROUGH | 04/06/2020 | Approval - Private Provider | PPROVIDER |
| ROOF VALLEY & METAL | 03/19/2020 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| FOUND SURVEY APPROVED (OFFICE) | 03/16/2020 | APPROVED | TBAKER |
| ELECTRIC-TUG | 03/16/2020 | Approval - Private Provider | PPROVIDER |
| TIE BEAM / LINTEL | 03/05/2020 | Approval - Private Provider | PPROVIDER |
| GRAVITY SEWER TEST | 02/19/2020 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: P-2503.2 CONCEALMENT OF SEWER SYSYTEM OR BUILDING DRAIN | |||
| MONOLITHIC SLAB | 02/17/2020 | Approval - Private Provider | PPROVIDER |
| PLUMBING 1ST ROUGH UNDERGROUND | 02/06/2020 | Approval - Private Provider | PPROVIDER |
| WATER METER INSTALLATION REQUEST | 01/31/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| PLFM | COMPLETE | 07/31/2020 | 07/31/2020 |
| Note: Released By: JMYERS The Final elevation certificate has been approved. | |||
| PLFM | HOLD | 07/17/2020 | 07/17/2020 |
| Note: Held By: JMYERS There is no finished floor elevation noted for the garage on the Final Survey. Please update the Final Survey to match the elevation for the garage on the Elevation Certificate. | |||
| PLFM | COMPLETE | 04/13/2020 | 04/13/2020 |
| Note: Released By: JMYERS The Building elevation certificate has been accepted. Please provide Final prior to receiving CO. | |||
| PLFM | HOLD | 04/08/2020 | 04/09/2020 |
| Note: Held By: JMYERS In Section C2, the measurement boxes must be checked if there is a measurement. C2 a,d,e,f,g,h are all missing the measurement box check. In Section D there must be a date on top of the seal inside the box along with the signature. There must also be a signature and current date where it notes Signature below the surveyors information. | |||
| PLFM | HOLD | 04/06/2020 | 04/06/2020 |
| Note: Held By: JMYERS All pages of the elevation certificate must be turned in. In Section C2, the measurement boxes must be checked if there is a measurement. C2 a,d,e,f,g,h are all missing the measurement box check. Please write the date on top of the seal in the provided box in Section D. If you have questions about these comments please call 386-986-2320. | |||
| PLFM | HOLD | 03/24/2020 | 03/24/2020 |
| Note: Held By: JMYERS Comments not addressed. The Construction elevation certificate has already been turned in, if this is supposed to be a Foundation elevation certificate the Building Under Construction box must be checked. Also FEMA released a new elevation certificate that must be used. | |||
| ENGIN1 | COMPLETE | 03/12/2020 | 03/16/2020 |
| Note: Released By: TBAKER | |||
| PLFM | HOLD | 03/12/2020 | 03/13/2020 |
| Note: Held By: JMYERS The Construction elevation certificate has already been turned in, if this is supposed to be a Foundation elevation certificate the Building Under Construction box must be checked. Also FEMA released a new elevation certificate that must be used. | |||
| BLD | COMPLETE | 03/11/2020 | 03/18/2020 |
| Note: Released By: FREODICA Revision: Truss repair | |||
| ZON | COMPLETE | 02/05/2020 | 02/06/2020 |
| Note: Released By: AMOBLEY | |||
| BLD | COMPLETE | 01/30/2020 | 01/30/2020 |
| Note: Released By: JPI | |||
| ZON | HOLD | 01/30/2020 | 01/30/2020 |
| Note: Held By: ELENS Revision sheet states the house is being moved back 30 feet but the survey/site plan submitted shows the house in the same place as previously approved. | |||
| SW1 | COMPLETE | 01/30/2020 | 02/04/2020 |
| Note: Released By: CTROHA | |||
| PLFM | COMPLETE | 01/30/2020 | 01/30/2020 |
| Note: Released By: JMYERS No comments | |||
| PLFM | COMPLETE | 01/22/2020 | 01/22/2020 |
| Note: Released By: DBEVAN The 01-21-20 dated elevation certificate was found sufficient. Note that elevation certificates will be required for "Building Under Construction" and "Finished Construction. | |||
| BLD | COMPLETE | 01/15/2020 | 01/23/2020 |
| Note: Released By: PBUCKLEY | |||
| ZON | COMPLETE | 01/15/2020 | 01/15/2020 |
| Note: Released By: ELENS | |||
| ZON | HOLD | 01/15/2020 | 01/15/2020 |
| Note: Held By: ELENS Repeat comments: 1. Site plan must note material for proposed driveway. 2. Site plan must show width of proposed driveway at garage doors. Note that it must be a minimum of 24' wide. | |||
| PLFM | HOLD | 01/15/2020 | 01/15/2020 |
| Note: Held By: JMYERS On the Elevation Certificate: In Section C2, there are no elevations noted for the proposed structure. These elevations must be included to show that the finished floor elevation will be at least 1ft above BFE. Also in Section C2, please do not check the measurement box if the elevation is N/A. In Section D it must be signed both on top of the raised seal inside the provided box as well as where a signature is noted. Only the actual Elevation Certificate document is required, not all of the instructions. Elevation certificates must be turned in hard copy. On the Survey: in the Flood Zone Information it notes that there is no Base Flood Elevation, this is incorrect as Zone AE has an established BFE. Please correct the Flood Zone Information. | |||
| SW1 | COMPLETE | 01/15/2020 | 01/16/2020 |
| Note: Released By: CTROHA | |||
| PLUM | COMPLETE | 01/15/2020 | 01/15/2020 |
| Note: Released By: JPI | |||
| BLD | HOLD | 01/02/2020 | 01/02/2020 |
| Note: Held By: PBUCKLEY SPOKE WITH SARAH AND TOLD HER THE TRUSS LAYOUT PLAN SIGNED AND SEALED B THE ENGINEER IS ACCEPTABLE AND SATISFIES THE COMMENT ABOUT TRUSSES. THAT COMMENT NOW REMOVED. PLEASE MAKE REMAINING PLAN REVISIONS AS NOTED BELOW. 1. Please complete the product approval listing for siding, soffits, all structural components, and other information for the project. . 2. On the roofing worksheet, for underlayment weight, please enter the the mils if using peel and stick (application says tile roof). 3. Add label with note at garage walls. R302.5.2 Duct penetration. Ducts in the garage and ducts penetrating the walls or ceilings separating the dwelling from the garage shall be constructed of a minimum No. 26 gage (0.48 mm) sheet steel, 1 inch (25.4 mm) minimum rigid nonmetallic Class 0 or Class 1 duct board, or other approved material and shall not have openings into the garage. 4. Please add the label for a Vacuum Breaker on the hose bib. (R2902.4) | |||
| BLD | HOLD | 12/23/2019 | 12/31/2019 |
| Note: Held By: JPI 1. Please complete the product approval listing for siding, soffits, all structural components, and other information for the project. The truss layout sheet is not the signed and sealed package which typically would list the structural components. 2. On the roofing worksheet, for underlayment weight, please enter the the mils if using peel and stick (application says tile roof). 3. Add label with note at garage walls. R302.5.2 Duct penetration. Ducts in the garage and ducts penetrating the walls or ceilings separating the dwelling from the garage shall be constructed of a minimum No. 26 gage (0.48 mm) sheet steel, 1 inch (25.4 mm) minimum rigid nonmetallic Class 0 or Class 1 duct board, or other approved material and shall not have openings into the garage. 4. Please add the label for a Vacuum Breaker on the hose bib. (R2902.4) | |||
| CUSVC | COMPLETE | 12/23/2019 | 12/31/2019 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 12/23/2019 | 12/27/2019 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 12/23/2019 | 01/03/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 12/23/2019 | 12/27/2019 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 12/23/2019 | 12/23/2019 |
| Note: Released By: CPISCITELLI | |||
| PLUM | HOLD | 12/23/2019 | 12/31/2019 |
| Note: Held By: PBUCKLEY Released By: LFITZGERALD Held By: JPI 1. Please provide a vent for the kitchen sink or show an AAV. FPC 905.1 2. Please show the exterior cleanout location and label the sewer pipe size. The diagram does not show the sewer. Typical legend for the c/o is a circle at the cleanout location. | |||
| SW1 | HOLD | 12/23/2019 | 12/30/2019 |
| Note: Held By: CTROHA Applicant needs to provide FFE on adjacent improved lots and elevations 10' ouside of the property lines Applicant needs to show proposed elevations on a 20' grid also show proposed drainage elevations. Applicant must match existing elevations at the property line of improved lots and show proposed drainage conveyance inside the property line. Applicant needs to provide final sod elevations at all four corners of the foundation | |||
| UD1 | COMPLETE | 12/23/2019 | 01/03/2020 |
| Note: Released By: AHALL | |||
| ZON | HOLD | 12/23/2019 | 12/23/2019 |
| Note: Held By: TDOAK 1. Site plan must note material for proposed driveway. 2. Site plan must show width of proposed driveway at garage doors. Note that it must be a minimum of 24' wide. | |||
| URB | COMPLETE | 12/23/2019 | 01/13/2020 |
| Note: Released By: JBEAUDET | |||
| PLFM | HOLD | 12/23/2019 | 12/23/2019 |
| Note: Held By: JMYERS The entire property is located in an AE Zone. Elevation Certificates will be required at 3 stages: Construction Drawings, Foundation, and Final. Elevation Certificates must be turned in hard copy. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 07/31/2020 |
| REINSPECTION FEE | ¤40.00 | 07/31/2020 |
| REVISION | ¤40.00 | 07/31/2020 |
| SITE PLAN 20 | ¤20.00 | 01/24/2020 |
| SURCHARGE FS 533.721 | ¤21.96 | 01/24/2020 |
| SURCHARGE - FS 468.631 | ¤32.94 | 01/24/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 01/24/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤89.43) | 01/24/2020 |
| SEWER INSPECTION | ¤25.00 | 01/24/2020 |
| METER - DEPOSIT | ¤60.00 | 01/24/2020 |
| WATER-METER | ¤434.59 | 01/24/2020 |
| WATER-METER | ¤361.04 | 01/24/2020 |
| ADMIN FEE | ¤20.00 | 01/24/2020 |
| CONNECTION FEES | ¤25.00 | 01/24/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 01/24/2020 |
| IMPACT FEE FIRE | ¤223.38 | 01/24/2020 |
| IMPACT FEE PARKS | ¤849.24 | 01/24/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 01/24/2020 |
| IMPACT FEE TRANSPORTATION | ¤2,981.00 | 01/24/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 01/24/2020 |
| PLAN CHECK FEE | ¤208.00 | 01/24/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤8,940.54 |