I want to search for...

Permit #2020030256

Permit Details

Status: COED

Parcel Id: 48-11-31-1710-00000-0820
CONDITIONED SPACE: 2584 sqft
GARAGE: 677 sqft
OPENED PORCH (WITH ROOF) : 44 sqft
OPENED PORCH (WITH ROOF) : 435 sqft
Total Square Footage: 3740 sqft
Block: 00000
Subdivision: 2087 - ESTATES AT GRAND HAVEN PHASE II
Job Phone: 386-445-2012
Location Address: 215 WILLOW OAK WAY
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/18/2020
NOC: RECORDED
Applicant name: JOHN NICHOLAS CORDASCI
Owner: FL HOUSE LLC

Address

2298 COLBERT LANE

PALM COAST, FL 32137

Lot: 0820
Contracted Stated Job Value: ¤327,134.00
Job Description: Single Family Residence
Type: CN

Contractor

SKYWAY BUILDERS INC
Status Location Address State License Number Phone
INACTIVE

PO BOX 354786

PALM COAST, FL 32135

CBC1263769 (Exp: 08/31/2024) 386-445-2012

Sub Contractors

MARK JOHN LUTCZA
Status Location Address State License Number Phone
ACTIVE

26 ROYAL LEAF LANE

PALM COAST, FL 32164

EC13005145 (Exp: 08/31/2026) 386-586-0770
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
THOMAS A REGULA
Status Location Address State License Number Phone Fax
INACTIVE

11320 PHILLIPS PKWY DRIVE E

JACKSONVILLE, FL 32256

CMC1250075 (Exp: 08/31/2026) 904-278-0339 904-278-0366
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 11/13/2020 FINAL APPROVED TSTAUFFACHER
U -UTILITY RESIDENTIAL FINAL 11/13/2020 FINAL APPROVED DHANEY
U-CROSS CONNECTION 11/12/2020 APPROVED - AS NOTED DHANEY
Note: No Cross CN.
ROW - FINAL APRON (AFTER POUR) 11/12/2020 APPROVED RGROSS
ROW - STORMWATER FINAL 11/12/2020 Disapproved - NO FEE RGROSS
Note: PER SUPER, OWNER OF THE ADJACENT LOT NEEDING REPAIRED WITH SOD IS NEGOTIATING WITH THE BUILDER TO HAVE A HOME BUILT ON THE PROPERTY AND THE DETENTION RUN OFF WOULD BE SODDED AFTER THAT CONSTRUCTION. HOWEVER, NO WRITTEN DOCUMENTATION HAS BEEN PRODUCED YET FROM THE ADJACENT PROPERTY OWNER.
ROW - STORMWATER FINAL 11/12/2020 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION PER SUPER, OWNER OF THE ADJACENT LOT NEEDING REPAIRED WITH SOD IS NEGOTIATING WITH THE BUILDER TO HAVE A HOME BUILT ON THE PROPERTY AND THE DETENTION RUN OFF WOULD BE SODDED AFTER THAT CONSTRUCTION. HOWEVER, NO WRITTEN DOCUMENTATION HAS BEEN PRODUCED YET FROM THE ADJACENT PROPERTY OWNER. NOTE: THIS INSPECTION WAS SCHEDULED THE SAME DAY BY THE INSPECTOR BECAUSE THE DOCUMENT MENTIONED ABOVE WAS PRODUCED AND DATED 11/10/20 FROM THE ADJACENT LOT OWNER.
ROW FIELD SURVEY /GRADING CERTIFICATION 11/10/2020 APPROVED - AS NOTED RGROSS
Note: THE DETENTION SYSTEM ON THE ADJACENT LOT ON THE RIGHT WHERE EXTRA FILL WAS DUMPED ILLEGALLY NEEDS RESHAPED AND THE BANK COMPLETELY SODDED. BARE EARTH AREA ON THE DETENTION SYSTEM ON THE LEFT ALSO NEEDS SOD TO PREVENT WASHOUT.
FINAL SURVEY (OFFICE USE ONLY) 11/10/2020 APPROVED RGROSS
ROW- PRE-APRON (PRE-POUR) 08/12/2020 APPROVED RGROSS
Note: READY TO POUR.
ELECTRIC - EARLY POWER 06/18/2020 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 2:50
GRAVITY SEWER TEST 05/21/2020 APPROVED JGIBSON
LATH/BRICK/ WATER BARRIER 05/21/2020 APPROVED JDELBONIS
U - SEWER TIE IN 05/21/2020 APPROVED JGIBSON
INSULATION 05/19/2020 APPROVED JDELBONIS
ALL ROUGH 05/13/2020 APPROVED JDELBONIS
ROOF VALLEY & METAL 05/07/2020 APPROVED JDELBONIS
LATH/BRICK/ WATER BARRIER 05/06/2020 CANCELLED BY INSPECTOR JDELBONIS
ELEV CERT-FOUNDATION APPROVAL 05/06/2020 APPROVED JMYERS
ROOF SHEATHING / BRACES/TIES/DOWN CELL 05/01/2020 APPROVED JDELBONIS
Note: JC from Skyway called in this inspection
ELECTRIC-TUG 04/14/2020 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 1:40
FOUND SURVEY APPROVED (OFFICE) 04/13/2020 APPROVED TBAKER
TIE BEAM / LINTEL 04/13/2020 APPROVED JDELBONIS
MONOLITHIC SLAB 04/01/2020 APPROVED JDELBONIS
PLUMBING 1ST ROUGH UNDERGROUND 03/31/2020 APPROVED JGIBSON
Note: THIS IS A REINSPECTION PREVIOUS CORRECTION MADE
PLUMBING 1ST ROUGH UNDERGROUND 03/30/2020 Disapproved - NO FEE JGIBSON
Note: PIPES PASSING THROUGH FOOTER
WATER METER INSTALLATION REQUEST 03/19/2020 APPROVED CSTONE

Review History

Department Status Date In Date Out
PLFM COMPLETE 11/09/2020 11/09/2020
Note: Released By: JMYERS The Final elevation certificate has been approved.
PLFM COMPLETE 05/06/2020 05/06/2020
Note: Released By: JMYERS The Foundation elevation certificate has been approved. Please provide Final prior to receiving CO.
ENGIN1 COMPLETE 04/09/2020 04/13/2020
Note: Released By: TBAKER
MECH COMPLETE 03/16/2020 03/16/2020
Note: Released By: CPISCITELLI
PLFM COMPLETE 03/16/2020 03/16/2020
Note: Released By: JMYERS The Construction elevation certificate has been accepted. Please provide Building and Final prior to receiving CO.
PLFM HOLD 03/13/2020 03/13/2020
Note: Held By: JMYERS In Section C2c the elevation of the garage from the elevation certificate notes 11.68' while the Site Plan notes 11.34'. Please clarify the correct elevation of the garage on either the Site Plan or the elevation certificate.
PLFM HOLD 03/09/2020 03/09/2020
Note: Held By: JMYERS The entire property is located in an AE Zone. Elevation Certificates will be required at 3 stages: Construction Drawings, Foundation, and Final. Elevation Certificates must be turned in hard copy and on the new 2019 edition.
BLD COMPLETE 03/06/2020 03/16/2020
Note: Released By: PBUCKLEY
CUSVC COMPLETE 03/06/2020 03/09/2020
Note: Released By: HHAND
ELEC COMPLETE 03/06/2020 03/09/2020
Note: Released By: JMUNSON
ENGIN1 COMPLETE 03/06/2020 03/10/2020
Note: Released By: TBAKER
LOCATE COMPLETE 03/06/2020 03/09/2020
Note: Released By: CSTONE
MECH HOLD 03/06/2020 03/09/2020
Note: Held By: CPISCITELLI Orientation on Energy calcs and site plans do not match the survey. Revise to both to match the survey
PLUM COMPLETE 03/06/2020 03/16/2020
Note: Released By: PBUCKLEY
SW1 HOLD 03/06/2020 03/06/2020
Note: Held By: CTROHA Applicant needs to show proposed elevations on a 20' grid also show proposed drainage elevations.
UD1 COMPLETE 03/06/2020 03/10/2020
Note: Released By: LFITZGERALD
ZON COMPLETE 03/06/2020 03/09/2020
Note: Released By: AMOBLEY
SW1 COMPLETE 03/06/2020 03/06/2020
Note: Released By: CTROHA

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 11/13/2020
ELECTRIC FEE ¤260.40 03/18/2020
3% FIRE IMPACT FEE CREDIT (¤6.70) 03/18/2020
IMPACT FEE FIRE ¤223.38 03/18/2020
IMPACT FEE PARKS ¤849.24 03/18/2020
IMPACT FEE SCHOOL ¤3,600.00 03/18/2020
IMPACT FEE TRANSPORTATION ¤3,059.00 03/18/2020
MECHANICAL FEE ¤260.40 03/18/2020
3% PARKS IMPACT FEE CREDIT (¤25.48) 03/18/2020
PLAN CHECK FEE ¤133.60 03/18/2020
PLUMBING FEE ¤260.40 03/18/2020
NEW RESIDENTIAL INSPECTIONS ¤668.00 03/18/2020
SITE PLAN 20 ¤20.00 03/18/2020
SURCHARGE FS 533.721 ¤14.89 03/18/2020
SURCHARGE - FS 468.631 ¤22.34 03/18/2020
STORM WATER PERMIT FEES ¤80.00 03/18/2020
3% TRANS IMPACT FEE CREDIT (¤91.77) 03/18/2020
SEWER INSPECTION ¤25.00 03/18/2020
METER - DEPOSIT ¤60.00 03/18/2020
WATER-METER ¤434.59 03/18/2020
WATER-METER ¤361.04 03/18/2020
ADMIN FEE ¤20.00 03/18/2020
CONNECTION FEES ¤25.00 03/18/2020
Fees Total Due: ¤0.00 Total Paid: ¤10,293.33