Permit #2020040881

Permit Details

Status: COED

Parcel Id: 07-11-31-7032-00330-0220
CONDITIONED SPACE: 1478 sqft
CONDITIONED SPACE: 1478 sqft
GARAGE: 444 sqft
GARAGE: 444 sqft
OPENED PORCH (WITH ROOF) : 65 sqft
OPENED PORCH (WITH ROOF) : 65 sqft
OPENED PORCH (WITH ROOF) : 70 sqft
OPENED PORCH (WITH ROOF) : 70 sqft
Total Square Footage: 4114 sqft
Block: 00330
Subdivision: 2155 - SECTION 32-ROYAL PALMS
Job Phone: 386-237-5837
Location Address: 5 ROSECROFT LN
Type: DU - DUPLEX
Issue Date: 06/10/2020
NOC: RECORDED
Applicant name: MARSEL GILMANSHIN
Owner: GILMANS DEVELOPMENT CORP

Address

3100 STEEL RAIL DRIVE

BUNNELL, FL 32110

Lot: 0220
Contracted Stated Job Value: ¤220,000.00
Job Description: Duplex
Type: CN

Contractor

GILMANS DEVELOPMENT CORP
Status Location Address State License Number Phone
ACTIVE

4873 PALM COAST PARKWAY NW #4

PALM COAST, FL 32137

CBC1263180 (Exp: 08/31/2026) 386-237-5837

Sub Contractors

MAXIM BUDNIK
Status Location Address State License Number Phone
ACTIVE

9788 HALSEY RD

JACKSONVILLE, FL 32246

EC13007415 (Exp: 08/31/2026) 904-509-7306
MAXIM BUDNIK
Status Location Address State License Number
ACTIVE

3 WAVECREST PL

PALM COAST, FL 32164

CAC1818445 (Exp: 08/31/2026)
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
GLEN WILLIAM KEHLE
Status Location Address State License Number Phone Fax
ACTIVE

P. O. Box 353511

BUNNELL, FL 32110

CFC057241 (Exp: 08/31/2026) (386) 447-4249 (386) 437-8488

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 06/22/2021 FINAL APPROVED JWALKER
Note: THIS IS A REINSPECTION Missing building numbers. Both units Missing termite treatment sticker affixed to the exterior of electrical panesl. Both units Missing energy calculations and blower door test results. Both units Tighten all loose electrical outlests. Both units. Toilet water supply line unit b front bath needs secured. HVAC labeling in Unit B needs to be properly marked. Electrical panel cover in garage not properply secured. Unit B.
BLD - BUILDING FINAL 06/21/2021 Disapproved - NO FEE JWALKER
Note: Missing building numbers. Both units Missing termite treatment sticker affixed to the exterior of electrical panesl. Both units Missing energy calculations and blower door test results. Both units Tighten all loose electrical outlests. Both units. Toilet water supply line unit b front bath needs secured. HVAC labeling in Unit B needs to be properly marked. Electrical panel cover in garage not properply secured. Unit B.
U -UTILITY RESIDENTIAL FINAL 06/21/2021 FINAL APPROVED LFITZGERALD
ROW - FINAL APRON (AFTER POUR) 06/18/2021 APPROVED - AS NOTED RGROSS
Note: Spoke to builder and suggested that more compacted dirt be placed all around the new Apron pour where form boards were pulled.
ROW FIELD SURVEY /GRADING CERTIFICATION 06/18/2021 APPROVED RGROSS
FOUND SURVEY APPROVED (OFFICE) 06/18/2021 APPROVED TBAKER
FINAL SURVEY (OFFICE USE ONLY) 06/18/2021 APPROVED RGROSS
Note: THIS IS A REINSPECTION Survey arrows indicate drainage from rear to front on the left side. Elevation to do reflect proper drainage. Compare 31.55, 31.30, 31.70 on the left rear property line.
FINAL SURVEY (OFFICE USE ONLY) 06/17/2021 Disapproved - NO FEE RGROSS
Note: Survey arrows indicate drainage from rear to front on the left side. Elevation to do reflect proper drainage. Compare 31.55, 31.30, 31.70 on the left rear property line.
U-CROSS CONNECTION 06/17/2021 APPROVED - AS NOTED LFITZGERALD
Note: no irrigation
ROW - FINAL INSPECTION 06/14/2021 APPROVED - AS NOTED RGROSS
Note: Be sure to clean culvert ends before Final Apron.
ROW- PRE-APRON (PRE-POUR) 06/03/2021 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION DRIVEWAY NEED TO BE INSPECTED BEFORE POUR 5/24/2021=meeting with Robert and the builders they need to cut 12 foot from the ROW and re pour new apron and lower the culvert pipe 06/01/2021= I LEFT IT PAINTED WITH PINK SPRAY PAINT NEED TO REMOVE THE FORM BOARD ON TOP OF THE CULVERT PIPE BOTH SIDES FORM BOARD ON THE RIHGT SIDE THEY ARE LOWER THEN THE PIPE NEED TO REMOVE DIRT FROM BOTH SIDE OF THE CULVERT PIPE IN THE ENTIRE AREA TO BE POURED. MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. MISSING REBARS 2 TO AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. FOOTERS NEED TO BE DUG OUT. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. ATTACHED PICTURE 6/3/21 - Culvert is tilted 1/2 tenth more than normally allowed in the right direction. Approved by Robert Gross as set. Culvert is also 1/10th higher on the left side than the swale plan elevation which is approved to the new rule allowing it to be 1/10th higher and still within tolerance. READY TO POUR
ROW- PRE-APRON (PRE-POUR) 06/01/2021 Disapproved -FEE REQUIRED GBERTOLA
Note: THIS IS A REINSPECTION DRIVEWAY NEED TO BE INSPECTED BEFORE POUR 5/24/2021=meeting with Robert and the builders they need to cut 12 foot from the ROW and re pour new apron and lower the culvert pipe 06/01/2021= I LEFT IT PAINTED WITH PINK SPRAY PAINT NEED TO REMOVE THE FORM BOARD ON TOP OF THE CULVERT PIPE BOTH SIDES FORM BOARD ON THE RIHGT SIDE THEY ARE LOWER THEN THE PIPE NEED TO REMOVE DIRT FROM BOTH SIDE OF THE CULVERT PIPE IN THE ENTIRE AREA TO BE POURED. MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. MISSING REBARS 2 TO AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. FOOTERS NEED TO BE DUG OUT. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. ATTACHED PICTURE CULVERT PIPE IS TO HIGHER ON THE LEFT SIDE NEED TO RESET THE PIPE TOLERANCE IS NO MORE THE 1/10
ROW - DRAINAGE 05/24/2021 APPROVED GBERTOLA
Note: meeting with Robert and the builders they need to cut 12 foot from the ROW and re pour new apron and lower the culvert pipe
ROW - DRAINAGE 05/20/2021 APPROVED - AS NOTED GBERTOLA
Note: MEET THE BUILDER RIGHT SIDE DRIVEWAY IS TO HIGHT AFTER 10 AM i have the meeting with Elena and we need to wait for the core test is done and have the results
ROW- PRE-APRON (PRE-POUR) 05/14/2021 Disapproved -FEE REQUIRED GBERTOLA
Note: DRIVEWAY NEED TO BE INSPECTED BEFORE POUR
ELECTRIC - EARLY POWER 02/25/2021 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 8:45
GRAVITY SEWER TEST 02/02/2021 APPROVED JGIBSON
U - SEWER TIE IN 02/02/2021 APPROVED JGIBSON
Note: THIS IS A REINSPECTION NOT RAN YET NO TAP MADE
U - SEWER TIE IN 01/15/2021 Disapproved -FEE REQUIRED JGIBSON
Note: NOT RAN YET NO TAP MADE
INSULATION 12/28/2020 APPROVED TSTAUFFACHER
FIREWALL 12/22/2020 APPROVED MMESSER
ALL ROUGH 12/22/2020 APPROVED MMESSER
Note: THIS IS A REINSPECTION
ALL ROUGH 12/14/2020 CANCELLED BY APPLICANT MMESSER
LATH/BRICK/ WATER BARRIER 10/23/2020 APPROVED MMESSER
ROOF VALLEY & METAL 09/28/2020 APPROVED TSTAUFFACHER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 09/23/2020 APPROVED MMESSER
TIE BEAM / LINTEL 09/08/2020 APPROVED MMESSER
MONOLITHIC SLAB 07/22/2020 APPROVED MMESSER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Need compaction report.
MONOLITHIC SLAB 07/20/2020 Disapproved - NO FEE MMESSER
Note: THIS IS A REINSPECTION Need compaction report.
MONOLITHIC SLAB 07/17/2020 CANCELLED BY APPLICANT MMESSER
MONOLITHIC SLAB 07/16/2020 CANCELLED BY APPLICANT WEB
WATER METER INSTALLATION REQUEST 07/09/2020 APPROVED CSTONE
PLUMBING 1ST ROUGH UNDERGROUND 07/07/2020 APPROVED JGIBSON

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 06/18/2021 06/18/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 06/18/2021 06/18/2021
Note: Released By: ESTELLE LENS - (386)986-3751 -
SW1 COMPLETE 06/09/2021 06/09/2021
Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM
BLD COMPLETE 06/03/2021 06/10/2021
Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM
ZON COMPLETE 06/03/2021 06/03/2021
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM No zoning review required for concrete core test.
ENGIN1 COMPLETE 06/03/2021 06/04/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
BADMIN HOLD 05/12/2021 05/12/2021
Note: Held By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM YOU NEED THE FOUNDATION SURVEY BEFORE YOU CAN SUBMIT THE FINAL SURVEY.
BADMIN COMPLETE 05/12/2021 05/12/2021
Note: Released By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM
ZON COMPLETE 06/04/2020 06/04/2020
Note: Released By: AMOBLEY
ZON HOLD 06/03/2020 06/03/2020
Note: Held By: AMOBLEY Please show on site plan/survey the ac pad dimensions so we can see that they will not encroach in the 5ft easement. What was uploaded was the landscape we need the survey
MECH COMPLETE 06/03/2020 06/03/2020
Note: Released By: CPISCITELLI
ZON HOLD 06/01/2020 06/01/2020
Note: Held By: AMOBLEY Please show on site plan/survey the ac pad dimensions so we can see that they will not encroach in the 5ft easement
MECH HOLD 06/01/2020 06/02/2020
Note: Held By: CPISCITELLI Provide entire energy calc and EPL card signed with duct drawing
BLD COMPLETE 06/01/2020 06/02/2020
Note: Released By: JPI
BADMIN HOLD 06/01/2020 06/01/2020
Note: Held By: STHOMAS 1. PLANS NEED TO BE SEPARATED 2. ONLY RENAME TO 3.PDF, 8.PDF
BADMIN COMPLETE 06/01/2020 06/01/2020
Note: Released By: STHOMAS
SWALE COMPLETE 04/27/2020 06/10/2020
Note: Released By: TBAKER
BLD HOLD 04/24/2020 04/29/2020
Note: Held By: JPI 1. Garage door entrance. R302.5.1 Other openings between the garage and residence shall be equipped with solid wood doors not less than 13/8 inches (35 mm) in thickness, solid or honeycomb core steel doors not less than 13/8 inches (35 mm) thick, or 20-minute fire-rated doors. Please label the door option. Please update D19 in the schedule. 2. Sheet 8. Please add NFPA as a design standard as there is a rated firewall.
CUSVC COMPLETE 04/24/2020 04/27/2020
Note: Released By: HHAND
ELEC COMPLETE 04/24/2020 04/27/2020
Note: Released By: JMUNSON
ENGIN1 COMPLETE 04/24/2020 04/27/2020
Note: Released By: TBAKER
LOCATE COMPLETE 04/24/2020 04/29/2020
Note: Released By: CSTONE
MECH HOLD 04/24/2020 04/27/2020
Note: Held By: CPISCITELLI 1. Energy Calcs and EPL cards need to be signed by the builder. 2. Duct Drawing needs to be signed by the AC Contractor
PLUM COMPLETE 04/24/2020 04/29/2020
Note: Released By: JPI
SW1 COMPLETE 04/24/2020 04/24/2020
Note: Released By: CTROHA
UD1 COMPLETE 04/24/2020 04/30/2020
Note: Released By: AHALL
ZON HOLD 04/24/2020 04/24/2020
Note: Held By: AMOBLEY Please provide a landscape plan showing all required foundation plantings, trees, sod type and if irrigation will be installed Please show on site plan/survey the ac pad dimensions so we can see that they will not encroach in the 5ft easement

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 06/15/2021
STORMWATER REINSPECTION FEE ¤40.00 06/15/2021
STORMWATER REINSPECTION FEE ¤40.00 06/15/2021
CONTRACTOR CHANGE ¤40.00 08/03/2020
ELECTRIC FEE ¤285.00 06/10/2020
3% FIRE IMPACT FEE CREDIT (¤26.81) 06/10/2020
ADMIN FEE ¤20.00 06/10/2020
NEW RESIDENTIAL INSPECTIONS ¤750.00 06/10/2020
SITE PLAN 20 ¤20.00 06/10/2020
MECHANICAL FEE ¤285.00 06/10/2020
3% TRANS IMPACT FEE CREDIT (¤155.88) 06/10/2020
SEWER CREDIT (¤2,294.00) 06/10/2020
SEWER INSPECTION ¤25.00 06/10/2020
3% PARKS IMPACT FEE CREDIT (¤50.95) 06/10/2020
PLUMBING FEE ¤285.00 06/10/2020
WATER CAPITAL FACILITY FEE ¤6,748.36 06/10/2020
SEWER CAPITAL FACILITY ¤9,192.14 06/08/2020
IMPACT FEE SCHOOL ¤7,200.00 06/08/2020
IMPACT FEE TRANSPORTATION ¤2,598.00 06/05/2020
WATER -IRRIGATION INSPECTION ¤50.00 06/05/2020
SURCHARGE FS 533.721 ¤16.45 06/05/2020
SURCHARGE - FS 468.631 ¤24.68 06/05/2020
STORM WATER PERMIT FEES ¤80.00 06/05/2020
CONNECTION FEES ¤2,005.76 06/05/2020
WATER- TURN ON ¤50.00 06/05/2020
IMPACT FEE FIRE ¤446.76 06/05/2020
IMPACT FEE PARKS ¤1,698.48 06/05/2020
PLAN CHECK FEE ¤150.00 06/05/2020
METER - DEPOSIT ¤120.00 06/04/2020
Fees Total Due: ¤0.00 Total Paid: ¤29,682.99