I want to search for...
Permit #2020050976
Permit Details
Status: COED
| Parcel Id: 07-11-31-7026-00020-0210 |
| CONDITIONED SPACE: 1280 sqft |
| CONDITIONED SPACE: 1280 sqft |
| GARAGE: 250 sqft |
| GARAGE: 250 sqft |
| OPENED PORCH (WITH ROOF) : 144 sqft |
| OPENED PORCH (WITH ROOF) : 144 sqft |
| OPENED PORCH (WITH ROOF) : 36 sqft |
| OPENED PORCH (WITH ROOF) : 36 sqft |
| Total Square Footage: 3420 sqft |
| Block: 00020 |
| Subdivision: 2153 - SECTION 26-PINE GROVE |
| Job Phone: 386-864-2199 |
| Location Address: 41 PINE HURST LN |
| Type: DU - DUPLEX |
| Issue Date: 07/09/2020 |
| NOC: RECORDED |
| Applicant name: MAXIM TARANNIK |
| Owner: SANTOS VICTOR M & MARISOL M H&W |
|
Address 545 JUNIPER LANE BRIDGEWATER, NJ 08807 |
| Lot: 0210 |
| Contracted Stated Job Value: ¤300,000.00 |
| Job Description: Duplex Construction |
| Type: CN |
Contractor
GOLDEN MAGNOLIA, INC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1 ROCKEFELLER DRIVE PALM COAST, FL 32164 |
RR282811984 (Exp: 08/31/2025) | 386-447-7007 |
Sub Contractors
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
ARTUR ROBERT SMIETANOWSKI
| Status | Location Address | State License Number | Phone |
| ACTIVE |
11 ABACUS AVE ORMOND BEACH, FL 32174 |
CAC1817498 (Exp: 08/31/2026) | 386-316-8333 |
FERNANDO MEZA SR
| Status | Location Address | State License Number | Phone |
| CANCEL |
457 CHELSEA PLACE AV ORMOND BEACH, FL 32174 |
EC13003906 (Exp: 08/31/2022) | 570-575-8139 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 04/29/2021 | FINAL APPROVED | MMESSER |
| Note: THIS IS A REINSPECTION AC condenser calls for 25 amp max fuse, 30 amp in panel - both units. | |||
| U-CROSS CONNECTION | 04/26/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation | |||
| BLD - BUILDING FINAL | 04/26/2021 | Disapproved - NO FEE | MMESSER |
| Note: AC condenser calls for 25 amp max fuse, 30 amp in panel - both units. | |||
| U -UTILITY RESIDENTIAL FINAL | 04/26/2021 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL INSPECTION | 04/23/2021 | APPROVED | GBERTOLA |
| Note: THIS IS A REINSPECTION SUPER ON SITE NEED TO REPAIER THE SWALE ON THE RIGHT SIDE SWALE DAMAGE NEED TO BE COMPLETELY REPAIR AND RE-SOD. ALL RUTTS AND BARE SPOTS MUST BE FILLED AND SODDED, NOT SEEDED OR COVERED W/STRAW AND/OR PINE NEEDLE IN THE EMPTY LOTS OF TRASH AND DEBRIS CAN NOT BE LEFTED IN VACANTS OR SURROUNDING LOTS 4/22/2021=AS A COURTESY INSPECTOR WENT BACK AND RE INSPECTED AT THE TIME OF THE INSPECTION EVERYTHING IS GOOD. 4/23/2021: approved earlier in the office should be done yesterday i don't know what happen yesterday | |||
| FINAL SURVEY (OFFICE USE ONLY) | 04/21/2021 | APPROVED | GBERTOLA |
| Note: Walkway in front of the house is different from the site plan. New changes will reflect on final survey | |||
| ROW - FINAL APRON (AFTER POUR) | 04/21/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: Walkway in front of the house is different from the site plan. New changes will reflect on final survey CORRECTION WERE MADE | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 04/21/2021 | APPROVED | GBERTOLA |
| Note: | |||
| ROW - FINAL INSPECTION | 04/21/2021 | Disapproved - NO FEE | GBERTOLA |
| Note: SUPER ON SITE NEED TO REPAIER THE SWALE ON THE RIGHT SIDE SWALE DAMAGE NEED TO BE COMPLETELY REPAIR AND RE-SOD. ALL RUTTS AND BARE SPOTS MUST BE FILLED AND SODDED, NOT SEEDED OR COVERED W/STRAW AND/OR PINE NEEDLE IN THE EMPTY LOTS OF TRASH AND DEBRIS CAN NOT BE LEFTED IN VACANTS OR SURROUNDING LOTS | |||
| ROW- PRE-APRON (PRE-POUR) | 02/26/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: New inspection due to canceled inspection THIS IS A REINSPECTION THIS IS A REINSPECTION NOT ALL FORMED AT TIME OF INSPECTION. BOTH COLVERTS ARE GOOD. NEED TO CHIP THE CONCRETE LIP AT THE END OF THE GARAGE DOOR BOTH SIDE AND BOTH SIDE WALKS NEED TO SHAVE DOWN I LEFT EVRETHING PAINTED WITH PINK SPRAY EASY TO SEE IT, PICTURE ATTACHED 02/26/2021=CORRECTION WERE MADE | |||
| ROW- PRE-APRON (PRE-POUR) | 02/08/2021 | CANCELLED BY APPLICANT | WEB |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION NOT ALL FORMED AT TIME OF INSPECTION. BOTH COLVERTS ARE GOOD. NEED TO CHIP THE CONCRETE LIP AT THE END OF THE GARAGE DOOR BOTH SIDE AND BOTH SIDE WALKS NEED TO SHAVE DOWN I LEFT EVRETHING PAINTED WITH PINK SPRAY EASY TO SEE IT, PICTURE ATTACHED | |||
| ROW- PRE-APRON (PRE-POUR) | 02/04/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION NOT ALL FORMED AT TIME OF INSPECTION. BOTH COLVERTS ARE GOOD. NEED TO CHIP THE CONCRETE LIP AT THE END OF THE GARAGE DOOR BOTH SIDE AND BOTH SIDE WALKS NEED TO SHAVE DOWN I LEFT EVRETHING PAINTED WITH PINK SPRAY EASY TO SEE IT, PICTURE ATTACHED | |||
| ROW- PRE-APRON (PRE-POUR) | 02/03/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: NOT ALL FORMED AT TIME OF INSPECTION. | |||
| U - SEWER TIE IN | 01/27/2021 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION SEWER NOT TIED IN TO PEP TANK | |||
| GRAVITY SEWER TEST | 01/27/2021 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION NO TEST | |||
| GRAVITY SEWER TEST | 01/25/2021 | Disapproved - NO FEE | JGIBSON |
| Note: NO TEST | |||
| U - SEWER TIE IN | 01/25/2021 | Disapproved - NO FEE | JGIBSON |
| Note: SEWER NOT TIED IN TO PEP TANK | |||
| ELECTRIC - EARLY POWER | 01/12/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 10:40 | |||
| PEP TANK INSTALLATION REQUEST | 12/14/2020 | APPROVED | CSTONE |
| PEP TANK INSTALLATION REQUEST | 12/11/2020 | CANCELLED BY APPLICANT | WEB |
| LATH/BRICK/ WATER BARRIER | 12/09/2020 | APPROVED | MMESSER |
| INSULATION | 12/01/2020 | APPROVED | MMESSER |
| ALL ROUGH | 11/30/2020 | APPROVED | MMESSER |
| ROOF VALLEY & METAL | 11/10/2020 | APPROVED | MMESSER |
| FIREWALL | 11/10/2020 | APPROVED | MMESSER |
| Note: | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/04/2020 | APPROVED | MMESSER |
| TIE BEAM / LINTEL | 10/22/2020 | APPROVED | MMESSER |
| Note: THIS IS A REINSPECTION Dowels missing at back porch. | |||
| TIE BEAM / LINTEL | 10/20/2020 | Disapproved - NO FEE | MMESSER |
| Note: Dowels missing at back porch. | |||
| ROW- PROJECT STATUS | 10/20/2020 | APPROVED | GBERTOLA |
| Note: CORRECTIONS MADE IT | |||
| ROW - DRAINAGE | 10/13/2020 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: I just got off the phone with a homeowner on this block complaining about the Duplex being built by Golden Magnolia. He claims the swale area is being blocked, so the water is backing up on his property. Could you please check this out, thank you I DID TALK TO SERGEI THE SUPER HE SAID HE IS GOING TO FIXED I BE BACK ON 10/20/2020 I DID TOLD HIM PU THE PIPE ON THE GROUND PIPE IS BENDING IN THE MIDDLE AND BOTH CORNERS ARE UP AT LIST 10 IONCH HIGH FROM THE SWALE | |||
| FOUND SURVEY APPROVED (OFFICE) | 09/16/2020 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 09/04/2020 | APPROVED - AS NOTED | MMESSER |
| Note: THIS IS A REINSPECTION Clean washout around rebar. | |||
| MONOLITHIC SLAB | 09/02/2020 | CANCELLED BY APPLICANT | MMESSER |
| PLUMBING 1ST ROUGH UNDERGROUND | 08/26/2020 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION P-2503.5.1 HEAD TEST ON ''B'' SIDE NOT HOLDING | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 08/25/2020 | Disapproved -FEE REQUIRED | JGIBSON |
| Note: P-2503.5.1 HEAD TEST ON ''B'' SIDE NOT HOLDING | |||
| WATER METER INSTALLATION REQUEST | 08/05/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| MECH | HOLD | 12/28/2020 | 12/28/2020 |
| Note: Held By: CPISCITELLI Provide heatload and duct layout signed by the AC contractor | |||
| MECH | HOLD | 12/28/2020 | 12/28/2020 |
| Note: Held By: CPISCITELLI Provide heatload (Second Request) | |||
| MECH | COMPLETE | 12/28/2020 | 12/29/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 09/15/2020 | 09/15/2020 |
| Note: Released By: ELENS | |||
| ENGIN1 | COMPLETE | 09/15/2020 | 09/16/2020 |
| Note: Released By: TBAKER | |||
| ELEC | COMPLETE | 06/05/2020 | 06/05/2020 |
| Note: Released By: JMUNSON | |||
| ZON | COMPLETE | 06/03/2020 | 06/03/2020 |
| Note: Released By: AMOBLEY | |||
| MECH | COMPLETE | 06/03/2020 | 06/03/2020 |
| Note: Released By: CPISCITELLI | |||
| ELEC | HOLD | 06/03/2020 | 06/03/2020 |
| Note: Held By: JMUNSON 2. Need outlets in back bathroom on both sides. NEC 2014 art 210.52 (D) | |||
| BLD | COMPLETE | 06/03/2020 | 06/04/2020 |
| Note: Released By: JPI | |||
| BLD | HOLD | 05/21/2020 | 05/26/2020 |
| Note: Held By: JPI 1. Provide the following basic/required design criteria: Design wind speed, Risk category, Exposure Category, Occupancy, Type of construction, Applicable Codes, etc.. R301. It appears that a cover page might be missing Page 1 of 9. 2. Smoke and Carbon monoxide detectors to maintain clearances from ductwork, bathrooms, etc… And to be installed in proper locations per R314/315. 3. Missing items from PA spec sheet: roof underlayment, roof vent, Single hung window, Zip system. 4. Provide full UL Design detail cut sheets for rated wall between units. 5. Identify egress windows – FRC 310. 6. For all attachment of wood framing to masonry, please call out distance from edge of member for first fastener. IE: Fastener start @ 6” from splice and edge of wood member. 7. Provide written response to comments with clouded revisions on plan. | |||
| CUSVC | COMPLETE | 05/21/2020 | 05/22/2020 |
| Note: Released By: HHAND | |||
| ELEC | HOLD | 05/21/2020 | 05/26/2020 |
| Note: Held By: JMUNSON 1. Submit load calculations 2. Need outlets in back bathroom on both sides. NEC 2014 art 210.52 (D) | |||
| ENGIN1 | COMPLETE | 05/21/2020 | 05/21/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 05/21/2020 | 05/21/2020 |
| Note: Released By: CSTONE | |||
| MECH | HOLD | 05/21/2020 | 05/26/2020 |
| Note: Held By: CPISCITELLI Duct Drawing needs to be signed by the Ac contractor | |||
| PLUM | COMPLETE | 05/21/2020 | 05/26/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 05/21/2020 | 05/27/2020 |
| Note: Released By: CTROHA | |||
| UD1 | COMPLETE | 05/21/2020 | 05/22/2020 |
| Note: Released By: AHALL | |||
| ZON | HOLD | 05/21/2020 | 05/22/2020 |
| Note: Held By: AMOBLEY Elevations labeled as floor plans on elevation page | |||
| SWALE | COMPLETE | 05/21/2020 | 06/29/2020 |
| Note: Released By: TBAKER |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 11/17/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 11/17/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 11/17/2021 |
| REINSPECTION FEE | ¤40.00 | 11/17/2021 |
| REINSPECTION FEE | ¤40.00 | 11/17/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/17/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/17/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤77.94) | 07/09/2020 |
| SEWER CREDIT | (¤2,294.00) | 07/09/2020 |
| SEWER INSPECTION | ¤25.00 | 07/09/2020 |
| SEWER CAPITAL FACILITY | ¤9,192.14 | 07/09/2020 |
| WATER CAPITAL FACILITY FEE | ¤6,748.36 | 07/09/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤638.00 | 07/09/2020 |
| SITE PLAN 20 | ¤20.00 | 07/09/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 07/09/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 07/09/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 07/09/2020 |
| METER - DEPOSIT | ¤120.00 | 07/09/2020 |
| WATER- TURN ON | ¤50.00 | 07/09/2020 |
| ADMIN FEE | ¤20.00 | 07/09/2020 |
| CONNECTION FEES | ¤2,005.76 | 07/09/2020 |
| BUILDING DISCOUNT 100% | (¤1,539.80) | 07/09/2020 |
| ELECTRIC FEE | ¤251.40 | 07/09/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤13.40) | 07/09/2020 |
| IMPACT FEE FIRE | ¤446.76 | 07/09/2020 |
| IMPACT FEE PARKS | ¤1,698.48 | 07/09/2020 |
| IMPACT FEE SCHOOL | ¤7,200.00 | 07/09/2020 |
| IMPACT FEE TRANSPORTATION | ¤2,598.00 | 07/09/2020 |
| MECHANICAL FEE | ¤251.40 | 07/09/2020 |
| WATER -IRRIGATION INSPECTION | ¤50.00 | 07/09/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤50.95) | 07/09/2020 |
| PLAN CHECK FEE | ¤127.60 | 07/09/2020 |
| PLUMBING FEE | ¤251.40 | 07/09/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤28,082.21 |