Permit #2020060277

Permit Details

Status: COED

Parcel Id: 07-11-31-7037-00630-0070
CONDITIONED SPACE: 2354 sqft
GARAGE: 784 sqft
OPENED PORCH (WITH ROOF) : 455 sqft
OPENED PORCH (WITH ROOF) : 97 sqft
Total Square Footage: 3690 sqft
Block: 00630
Subdivision: 2176 - SECTION 37-LAKEVIEW
Job Phone: (386) 672-8285
Location Address: 42 LINDSAY DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 06/24/2020
NOC: RECORDED
Applicant name: JOSEPH TODD VANACORE
Owner: LORSHBAUGH ROY LEE & YAJAYRA GESENIA H&W

Address

12901 NITTANY LION CIRCLE

HAGERSTOWN, MD 21740

Lot: 0070
Contracted Stated Job Value: ¤255,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

VANACORE CONSTRUCTION INC.
Status Location Address Mailing Address State License Number Phone
INACTIVE

1451 N US HIGHWAY 1

Ormond Beach, FL 32174

SUITE 13

Ormond Beach, FL 32174

CBC058991 (Exp: 08/31/2024) (386) 672-8285

Sub Contractors

VERNON JACK SMITH III
Status Location Address State License Number Phone Fax
ACTIVE

224 KIRKLAND ROAD

NEW SMYRNA BEACH, FL 32169

EC13004432 (Exp: 08/31/2026) 386-409-3616 386-409-3616
SHAWN MICHAEL HISS
Status Location Address State License Number Phone
ACTIVE

1315 LPGA BLVD

HOLLY HILL, FL 32117

CAC1813585 (Exp: 08/31/2026) (386)672-8688
JEFFREY DALE KNIGHT
Status Location Address State License Number Phone Fax
INACTIVE

923 ASHMEADE CT

PORT ORANGE, FL 32127

CFC057351 (Exp: 08/31/2026) 386-345-3857 386-345-4443
ALFRED N FYOCK JR
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

387 SAULS

ORMOND BEACH, FL 32174

ST

ORMOND BEACH, FL 32174

CCC1329075 (Exp: 08/31/2026) 386-566-6112 386-673-4299

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 01/22/2021 FINAL APPROVED DHANEY
ROW - STORMWATER FINAL 01/20/2021 APPROVED RGROSS
FINAL SURVEY (OFFICE USE ONLY) 01/19/2021 APPROVED - AS NOTED RGROSS
Note: GRADE OFF THE DRIVEWAY STRAIGHT OUT FROM THE GARAGE WILL FLOW TOWARD DRIVEWAY. HOWEVER THE SLOPE AWAY FROM THE GARAGE WILL CAUSE THE WATER TO FLOW DOWN THE DRIVEWAY TOWARD THE SWALE.
PLUMBING FINAL 01/18/2021 Approval - Private Provider PPROVIDER
HVAC FINAL 01/18/2021 Approval - Private Provider PPROVIDER
ELECTRIC FINAL 01/18/2021 Approval - Private Provider PPROVIDER
BLD - BUILDING FINAL 01/18/2021 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 01/11/2021 Approval - Private Provider PPROVIDER
ROW - DRAINAGE 01/06/2021 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION SWALE DRAINAGE COMPLETELY BLOCKED. BUILDER MUST OPEN DRAINAGE ASAP. NEXT INSPECTION 11/16/20. 1/6/21 - DRIVEWAY HAS BEEN POURED AND THERE IS NO LONGER A DRAINAGE ISSUE.
ROW - FINAL APRON (AFTER POUR) 01/05/2021 APPROVED RGROSS
U-CROSS CONNECTION 01/05/2021 APPROVED - AS NOTED DHANEY
Note: Approved No Cross CN.
ROW- PRE-APRON (PRE-POUR) 12/07/2020 APPROVED RGROSS
U - SEWER TIE IN 11/25/2020 Approval - Private Provider PPROVIDER
ELECTRIC - EARLY POWER 11/25/2020 Approval - Private Provider PPROVIDER
ROW - DRAINAGE 11/12/2020 Disapproved - NO FEE RGROSS
Note: SWALE DRAINAGE COMPLETELY BLOCKED. BUILDER MUST OPEN DRAINAGE ASAP. NEXT INSPECTION 11/16/20.
PEP TANK INSTALLATION REQUEST 10/13/2020 APPROVED CSTONE
INSULATION 10/05/2020 Approval - Private Provider PPROVIDER
LATH/BRICK/ WATER BARRIER 10/05/2020 Approval - Private Provider PPROVIDER
ALL ROUGH 09/25/2020 Approval - Private Provider PPROVIDER
Note: All rough (combination framing), exterior door and window installation
EXTERIOR STRAP/CLIP 09/24/2020 Approval - Private Provider PPROVIDER
Note: Exterior door and windows installation
ROOF VALLEY & METAL 09/10/2020 Approval - Private Provider PPROVIDER
Note: Roof Valley and Metal(underlayment) inspection passed.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 09/09/2020 Approval - Private Provider PPROVIDER
TIE BEAM / LINTEL 08/20/2020 Approval - Private Provider PPROVIDER
FOUND SURVEY APPROVED (OFFICE) 08/11/2020 APPROVED TBAKER
MONOLITHIC SLAB 07/30/2020 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH UNDERGROUND 07/27/2020 Approval - Private Provider PPROVIDER
WATER METER INSTALLATION REQUEST 07/09/2020 APPROVED CSTONE

Review History

Department Status Date In Date Out
BADMIN COMPLETE 01/26/2021 01/26/2021
Note: Released By: LMUSGROVE
BADMIN HOLD 01/06/2021 01/06/2021
Note: Held By: LMUSGROVE Please rename your files in accordance with the naming convention outlined in our ‘document requirements’ http://docs.palmcoastgov.com/departments/building/online/document-requirements.pdf It is important that all submittals follow the guidelines for plan review and record retention accuracy. Please do not add anything to the file names ( example – 123 Main Street, Smith Residence, Palm Coast Plans, etc.)
ZON COMPLETE 08/10/2020 08/10/2020
Note: Released By: AMOBLEY
ENGIN1 COMPLETE 08/10/2020 08/11/2020
Note: Released By: TBAKER Foundation Survey
ZON COMPLETE 06/22/2020 06/22/2020
Note: Released By: ELENS
ZON HOLD 06/10/2020 06/11/2020
Note: Held By: ELENS Repeat comments; Right and left side elevations appear to be mislabeled. Square footage on the floor plan totals to 3380 (not 3690). Zoning review and compliance with the Unified Land Development Code, is required per FS 553.791 (1)(h)(4): “Any documents required by the local building official to determine that the fee owner has secured all other government approvals required by law.”
SWALE COMPLETE 06/08/2020 07/06/2020
Note: Released By: TBAKER
CUSVC COMPLETE 06/05/2020 06/05/2020
Note: Released By: HHAND
LOCATE COMPLETE 06/05/2020 06/09/2020
Note: Released By: CSTONE
SW1 COMPLETE 06/05/2020 06/08/2020
Note: Released By: CTROHA
UTL COMPLETE 06/05/2020 06/09/2020
Note: Released By: AHALL
ZON HOLD 06/05/2020 06/08/2020
Note: Held By: ELENS Survey is missing Sheet 1 of 2. Please upload Sheets 1 of 2 and 2 of 2 as one document for the Survey and the Site plan. Please provide driveway width at the garage doors on the site plan. Right and left side elevations appear to be mislabeled. Square footage on the floor plan totals to 3380 (not 3690).
ENGIN1 COMPLETE 06/05/2020 06/08/2020
Note: Released By: TBAKER

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
METER - DEPOSIT ¤60.00 06/24/2020
WATER- TURN ON ¤25.00 06/24/2020
ADMIN FEE ¤145.00 06/24/2020
CONNECTION FEES ¤1,002.88 06/24/2020
3% FIRE IMPACT FEE CREDIT (¤6.70) 06/24/2020
IMPACT FEE FIRE ¤223.38 06/24/2020
IMPACT FEE PARKS ¤849.24 06/24/2020
IMPACT FEE SCHOOL ¤3,600.00 06/24/2020
IMPACT FEE TRANSPORTATION ¤1,674.00 06/24/2020
WATER -IRRIGATION INSPECTION ¤25.00 06/24/2020
3% PARKS IMPACT FEE CREDIT (¤25.48) 06/24/2020
SITE PLAN 20 ¤20.00 06/24/2020
SURCHARGE FS 533.721 ¤2.00 06/24/2020
SURCHARGE - FS 468.631 ¤2.48 06/24/2020
STORM WATER PERMIT FEES ¤80.00 06/24/2020
3% TRANS IMPACT FEE CREDIT (¤50.22) 06/24/2020
SEWER CREDIT (¤3,214.34) 06/24/2020
SEWER INSPECTION ¤25.00 06/24/2020
SEWER CAPITAL FACILITY ¤4,596.07 06/24/2020
WATER CAPITAL FACILITY FEE ¤3,374.18 06/24/2020
Fees Total Due: ¤0.00 Total Paid: ¤12,407.49