I want to search for...

Permit #2020060437

Permit Details

Status: COED

Parcel Id: 07-11-31-7028-00030-0020
CONDITIONED SPACE: 2052 sqft
GARAGE: 407 sqft
OPENED PORCH (WITH ROOF) : 16 sqft
Total Square Footage: 2475 sqft
Block: 00030
Subdivision: 2199 - SECTION 28-WYNNFIELD
Job Phone: 904-268-7730
Location Address: 3 PHOENIX LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 06/30/2020
NOC: RECORDED
Applicant name: SCOTT CHRISTIAN HOWARD
Owner: MARONDA HOMES INC

Address

5220 SHAD ROAD STE 202

JACKSONVILLE, FL 32257

Lot: 0020
Contracted Stated Job Value: ¤130,000.00
Job Description: SINGLE FAMILY DWELLING
Type: CN

Contractor

MARONDA HOMES
Status Location Address State License Number Phone
INACTIVE

4005 MARONDA WAY

,

CRC056762 (Exp: 08/31/2026) 904-268-7730

Sub Contractors

JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113
RONALD KEVIN HAUPT
Status Location Address State License Number Phone
ACTIVE

4005 MARONDA WAY

SANFORD, FL 32771

CAC058534 (Exp: 08/31/2026) 407-321-0064
JEFFREY TROY SABAKA
Status Location Address State License Number Phone Fax
ACTIVE

2191 DEERWOOD ACRES DR

ST AUGUSTINE, FL 32084

CFC1427439 (Exp: 08/31/2026) 904-838-2218 904-819-0965
ANDREW SCOTT DIGAETANO JR
Status Location Address State License Number Phone
ACTIVE

44 FORT CAROLINE

PALM COAST, FL 32137

CCC1331606 (Exp: 08/31/2026) 386-302-9063

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 11/19/2020 FINAL APPROVED MMESSER
U -UTILITY RESIDENTIAL FINAL 11/19/2020 FINAL APPROVED LFITZGERALD
Note: water meter pit installed too far forwards not allowing ball valve to be open more than lass than a third-Rich from utility informed and said he woulod take care of
ROW - STORMWATER FINAL 11/18/2020 APPROVED - AS NOTED GBERTOLA
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION A LOT OF WATER ON THE RIGHT REAR SIDE OF THE HOUSE GOING TO ALL THE WAY TO THE RIGHT SIDE OF THE HOUSE FROM THE SPRINKLER IT'S ALL THE WAY TO THE RIGHT SIDE PLEASE REMOVE THE PIECES THE CONCRETE INSIDE THE PIPE RIGHT SIDE 11/16/2020= COLVERT PIPE IS CLEAN= IT SEEMS THAT THERE WERE NO CHANGES AT ALL IN THE REAR RIGHT SIDE 11/18/2020= CORRECTION MADE IT
ROW - STORMWATER FINAL 11/16/2020 Disapproved -FEE REQUIRED GBERTOLA
Note: THIS IS A REINSPECTION A LOT OF WATER ON THE RIGHT REAR SIDE OF THE HOUSE GOING TO ALL THE WAY TO THE RIGHT SIDE OF THE HOUSE FROM THE SPRINKLER IT'S ALL THE WAY TO THE RIGHT SIDE PLEASE REMOVE THE PIECES THE CONCRETE INSIDE THE PIPE RIGHT SIDE 11/16/2020= COLVERT PIPE IS CLEAN= IT SEEMS THAT THERE WERE NO CHANGES AT ALL IN THE REAR RIGHT SIDE
ROW - FINAL APRON (AFTER POUR) 11/12/2020 APPROVED GBERTOLA
ROW - STORMWATER FINAL 11/12/2020 Disapproved - NO FEE GBERTOLA
Note: A LOT OF WATER ON THE RIGHT REAR SIDE OF THE HOUSE GOING TO ALL THE WAY TO THE RIGHT SIDE OF THE HOUSE FROM THE SPRINKLER IT'S ALL THE WAY TO THE RIGHT SIDE PLEASE REMOVE THE PIECES THE CONCRETE INSIDE THE PIPE RIGHT SIDE
U-CROSS CONNECTION 11/12/2020 APPROVED - AS NOTED JHARDING
Note: Approved. No irrigation. No cross connections
FINAL SURVEY (OFFICE USE ONLY) 11/09/2020 APPROVED GBERTOLA
ROW FIELD SURVEY /GRADING CERTIFICATION 11/09/2020 APPROVED GBERTOLA
ELECTRIC - EARLY POWER 10/16/2020 APPROVED - AS NOTED JMUNSON
Note: Emailed FPL at 8:54 am
U - SEWER TIE IN 10/09/2020 APPROVED JGIBSON
ROW- PRE-APRON (PRE-POUR) 09/23/2020 APPROVED - AS NOTED KHOWELL
Note: *LOWER FORM IS 1 1/2" WIDER THAN THE UPPER. *FIX ROAD FORM THAT IS LOWER. *I WOULD ADD A FORM TO THE BOTTOM OF THE END OF THE MITERS SO CONCRETE DOES NOT GET POURED INTO THE SWALE. *It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ROW- PRE-APRON (PRE-POUR) 09/21/2020 Disapproved -FEE REQUIRED RGROSS
Note: NOT FORMED YET AND FULL OF WATER FROM OVER THE WEEKEND RAIN.
INSULATION 09/08/2020 APPROVED MMESSER
PEP TANK INSTALLATION REQUEST 09/04/2020 APPROVED CSTONE
LATH/BRICK/ WATER BARRIER 08/31/2020 APPROVED FWILLIS
ALL ROUGH 08/31/2020 APPROVED FWILLIS
ROOF SHEATHING / BRACES/TIES/DOWN CELL 08/27/2020 APPROVED MMESSER
ROOF VALLEY & METAL 08/26/2020 APPROVED MMESSER
FOUND SURVEY APPROVED (OFFICE) 08/18/2020 APPROVED TBAKER
TIE BEAM / LINTEL 08/10/2020 APPROVED MMESSER
MONOLITHIC SLAB 08/03/2020 APPROVED MMESSER
PLUMBING 1ST ROUGH UNDERGROUND 07/28/2020 APPROVED JGIBSON
GRAVITY SEWER TEST 07/28/2020 APPROVED JGIBSON
WATER METER INSTALLATION REQUEST 07/02/2020 APPROVED CSTONE

Review History

Department Status Date In Date Out
ZON COMPLETE 08/17/2020 08/17/2020
Note: Released By: ELENS
ENGIN1 COMPLETE 08/17/2020 08/18/2020
Note: Released By: TBAKER
ZON COMPLETE 07/02/2020 07/06/2020
Note: Released By: ELENS
UTL COMPLETE 07/02/2020 07/07/2020
Note: Released By: AHALL
ZON COMPLETE 06/25/2020 06/25/2020
Note: Released By: ELENS
ELEC COMPLETE 06/25/2020 06/26/2020
Note: Released By: JMUNSON
BLD COMPLETE 06/25/2020 06/25/2020
Note: Released By: JPI
MECH COMPLETE 06/25/2020 06/26/2020
Note: Released By: CPISCITELLI
SWALE COMPLETE 06/10/2020 07/07/2020
Note: Released By: TBAKER
ZON HOLD 06/10/2020 06/10/2020
Note: Held By: ELENS The site plan and landscape plan are garage right and the floor plan is garage left. They all must match.
BLD HOLD 06/09/2020 06/10/2020
Note: Held By: JPI 1. Provide dutch gable roof details. Provide section cut through with all bracing, attachments and construction details. 2. Provide valley truss attachment details. 3. Provide valley truss gable end details with all construction details. 4. Page 6.0 calls for Detail 3 (?) on page WF18A (?), cannot locate detail/page or note.
CUSVC COMPLETE 06/09/2020 06/10/2020
Note: Released By: HHAND
ELEC HOLD 06/09/2020 06/10/2020
Note: Held By: JMUNSON Need smoke alarms in all bedrooms and need smoke/carbon alarms outside of all bedrooms. FBC 314.3 and 315.1
ENGIN1 COMPLETE 06/09/2020 06/10/2020
Note: Released By: TBAKER
LOCATE COMPLETE 06/09/2020 06/11/2020
Note: Released By: CSTONE
MECH HOLD 06/09/2020 06/11/2020
Note: Held By: CPISCITELLI 1. Heatload does not match the site plan. Revise to match. 2. Duct Drawing needs to be signed by the AC contractor
PLUM COMPLETE 06/09/2020 06/10/2020
Note: Released By: JPI
SW1 COMPLETE 06/09/2020 06/10/2020
Note: Released By: RGROSS
UTL COMPLETE 06/09/2020 06/12/2020
Note: Released By: AHALL

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 11/23/2020
REINSPECTION FEE ¤40.00 11/23/2020
NEW RESIDENTIAL INSPECTIONS ¤490.00 06/30/2020
SITE PLAN 20 ¤20.00 06/30/2020
SURCHARGE FS 533.721 ¤11.51 06/30/2020
SURCHARGE - FS 468.631 ¤17.27 06/30/2020
STORM WATER PERMIT FEES ¤80.00 06/30/2020
3% TRANS IMPACT FEE CREDIT (¤50.22) 06/30/2020
SEWER CREDIT (¤650.00) 06/30/2020
SEWER INSPECTION ¤25.00 06/30/2020
SEWER CAPITAL FACILITY ¤4,596.07 06/30/2020
WATER CAPITAL FACILITY FEE ¤3,374.18 06/30/2020
METER - DEPOSIT ¤60.00 06/30/2020
WATER- TURN ON ¤25.00 06/30/2020
ADMIN FEE ¤20.00 06/30/2020
CONNECTION FEES ¤1,002.88 06/30/2020
ELECTRIC FEE ¤207.00 06/30/2020
3% FIRE IMPACT FEE CREDIT (¤6.70) 06/30/2020
IMPACT FEE FIRE ¤223.38 06/30/2020
IMPACT FEE PARKS ¤849.24 06/30/2020
IMPACT FEE SCHOOL ¤3,600.00 06/30/2020
IMPACT FEE TRANSPORTATION ¤1,674.00 06/30/2020
MECHANICAL FEE ¤207.00 06/30/2020
WATER -IRRIGATION INSPECTION ¤25.00 06/30/2020
3% PARKS IMPACT FEE CREDIT (¤25.48) 06/30/2020
PLAN CHECK FEE ¤98.00 06/30/2020
PLUMBING FEE ¤207.00 06/30/2020
Fees Total Due: ¤0.00 Total Paid: ¤16,160.13