I want to search for...
Permit #2020060991
Permit Details
Status: COED
| Parcel Id: 07-11-31-7029-00630-0010 |
| CONDITIONED SPACE: 1527 sqft |
| GARAGE: 410 sqft |
| OPENED PORCH (WITH ROOF) : 54 sqft |
| Total Square Footage: 1991 sqft |
| Block: 00630 |
| Subdivision: 2209 - SECTION 29-ROYAL PALMS |
| Job Phone: (386)437-1508 |
| Location Address: 29 RYARBOR DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 06/25/2020 |
| NOC: RECORDED |
| Applicant name: TAMMI SUE MARQUIS |
| Owner: YOUNG JOE |
|
Address PO BOX 9 CISSNA PARK, IL 60924 |
| Lot: 0010 |
| Contracted Stated Job Value: ¤150,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
GULFSTREAM HOMES & CONSTRUCTION, LLC
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
PO BOX 1092 BUNNELL, FL 32110 |
CRC1326418 (Exp: 08/31/2026) | (386)437-1508 | 386-437-9769 |
Sub Contractors
JAMES CRAIG FISHER
| Status | Location Address | State License Number | Phone |
| ACTIVE |
PO BOX 451 BUNNELL, FL 32110 |
CAC1819807 (Exp: 08/31/2026) | 386-222-9549 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
ARTHUR J PASCOE
| Status | Location Address | State License Number | Phone |
| ACTIVE |
PO BOX 730007 ORMOND BEACH, FL 32174 |
EC13007168 (Exp: 08/31/2026) | 386-547-6439 |
DANIEL DAVID RUTKOWSKI III
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
1687 STATE AVENUE HOLLY HILL, FL 32117 |
CCC1328639 (Exp: 08/31/2026) | 386-290-7490 | 386-256-0001 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 02/09/2021 | FINAL APPROVED | MMESSER |
| U -UTILITY RESIDENTIAL FINAL | 02/08/2021 | FINAL APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION no power into pep panel | |||
| U -UTILITY RESIDENTIAL FINAL | 02/04/2021 | Disapproved - NO FEE | LFITZGERALD |
| Note: no power into pep panel | |||
| ROW - FINAL APRON (AFTER POUR) | 02/02/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: 02/02/2021= CULVERT PIPE IS GOOD | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 02/02/2021 | APPROVED | GBERTOLA |
| ROW - DRAINAGE | 02/02/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION 12/8/2020 a silt fence needs to be installed When necessary, an Erosion Control Inspection will be required if the subject property is adjacent to significantly lower property, such as a ditch, canal, water body or any other stormwater conveyance. A silt fence is required on the downstream end of the swale, at the property line, adjacent to a ditch, or at the discretion of the Stormwater Inspector. The Builder will be notified if additional Erosion Control Measures are required at the time the permit is issued. Lot clearing cannot begin prior to the permit being issued. 12/11/2020 reinspection datE CORRECTION MADE | |||
| ROW - STORMWATER FINAL | 02/02/2021 | APPROVED | GBERTOLA |
| FINAL SURVEY (OFFICE USE ONLY) | 02/02/2021 | APPROVED | GBERTOLA |
| U-CROSS CONNECTION | 01/04/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation | |||
| ELECTRIC - EARLY POWER | 12/29/2020 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 9:11 am | |||
| ROW - DRAINAGE | 12/08/2020 | Disapproved - NO FEE | KRUTH |
| Note: 12/8/2020 a silt fence needs to be installed When necessary, an Erosion Control Inspection will be required if the subject property is adjacent to significantly lower property, such as a ditch, canal, water body or any other stormwater conveyance. A silt fence is required on the downstream end of the swale, at the property line, adjacent to a ditch, or at the discretion of the Stormwater Inspector. The Builder will be notified if additional Erosion Control Measures are required at the time the permit is issued. Lot clearing cannot begin prior to the permit being issued. 12/11/2020 reinspection date | |||
| ROW- PRE-APRON (PRE-POUR) | 11/25/2020 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION TOO MUCH WATER IN THE POUR AREA AND IN THE PIPE. BUTTER SOFT MUD ALL ALONG THE PIPE'S OUTSIDE EDGE MATERIAL IS NOT COMPACTED= MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. I DIDN'T CHECK THE ELEVATION TOO MUCH WATER INSIDE 11/25/2020=CORRECTION MADE IT PLEASE IF A RAIN BEFORE POUR CONCRETE, CHECK THE PIPE ELEVATION AGAIN, | |||
| ROW- PRE-APRON (PRE-POUR) | 11/23/2020 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: TOO MUCH WATER IN THE POUR AREA AND IN THE PIPE. BUTTER SOFT MUD ALL ALONG THE PIPE'S OUTSIDE EDGE MATERIAL IS NOT COMPACTED= MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. I DIDN'T CHECK THE ELEVATION TOO MUCH WATER INSIDE FOOTERS HAVE WASHED IN NEED TO BE DUG OUT. | |||
| U - SEWER TIE IN | 11/09/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 11/09/2020 | APPROVED | JGIBSON |
| INSULATION | 10/12/2020 | APPROVED | MMESSER |
| PEP TANK INSTALLATION REQUEST | 10/08/2020 | APPROVED | CSTONE |
| LATH/BRICK/ WATER BARRIER | 10/07/2020 | APPROVED | MMESSER |
| ALL ROUGH | 10/06/2020 | APPROVED - AS NOTED | MMESSER |
| Note: Fire block needed on sides of range hood vent. | |||
| ALL ROUGH | 10/05/2020 | CANCELLED BY APPLICANT | WEB |
| ROOF VALLEY & METAL | 09/28/2020 | APPROVED | TSTAUFFACHER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/21/2020 | APPROVED | TSTAUFFACHER |
| FOUND SURVEY APPROVED (OFFICE) | 09/17/2020 | APPROVED | AMOBLEY |
| TIE BEAM / LINTEL | 09/04/2020 | APPROVED | MMESSER |
| MONOLITHIC SLAB | 08/14/2020 | APPROVED | MMESSER |
| PLUMBING 1ST ROUGH UNDERGROUND | 08/10/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 07/28/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 09/16/2020 | 09/17/2020 |
| Note: Released By: AMOBLEY | |||
| ENGIN1 | COMPLETE | 09/16/2020 | 09/17/2020 |
| Note: Released By: TBAKER | |||
| MECH | COMPLETE | 06/24/2020 | 06/24/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 06/24/2020 | 06/24/2020 |
| Note: Released By: ELENS | |||
| SWALE | COMPLETE | 06/22/2020 | 07/14/2020 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 06/22/2020 | 06/22/2020 |
| Note: Released By: ELENS | |||
| BLD | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 06/19/2020 | 06/23/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: CSTONE | |||
| MECH | HOLD | 06/19/2020 | 06/22/2020 |
| Note: Held By: CPISCITELLI 1. Energy Calcs and EPL Card need to be signed by the builder 2. Duct Drawing needs to have company name and signature. (signature is not legible on current drawing) | |||
| PLUM | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 06/19/2020 | 06/22/2020 |
| Note: Released By: RGROSS | |||
| UTL | COMPLETE | 06/19/2020 | 06/23/2020 |
| Note: Released By: AHALL |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 02/09/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤376.00 | 06/25/2020 |
| SITE PLAN 20 | ¤20.00 | 06/25/2020 |
| SURCHARGE FS 533.721 | ¤9.34 | 06/25/2020 |
| SURCHARGE - FS 468.631 | ¤14.02 | 06/25/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 06/25/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 06/25/2020 |
| SEWER INSPECTION | ¤25.00 | 06/25/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 06/25/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 06/25/2020 |
| METER - DEPOSIT | ¤60.00 | 06/25/2020 |
| WATER- TURN ON | ¤25.00 | 06/25/2020 |
| ADMIN FEE | ¤20.00 | 06/25/2020 |
| CONNECTION FEES | ¤1,002.88 | 06/25/2020 |
| ELECTRIC FEE | ¤172.80 | 06/25/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 06/25/2020 |
| IMPACT FEE FIRE | ¤223.38 | 06/25/2020 |
| IMPACT FEE PARKS | ¤849.24 | 06/25/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 06/25/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 06/25/2020 |
| MECHANICAL FEE | ¤172.80 | 06/25/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 06/25/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 06/25/2020 |
| PLAN CHECK FEE | ¤75.20 | 06/25/2020 |
| PLUMBING FEE | ¤172.80 | 06/25/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤16,525.31 |