I want to search for...
Permit #2020071509
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7019-00270-0050 |
| CONDITIONED SPACE: 2367 sqft |
| OPENED PORCH (WITH ROOF) : 107 sqft |
| OPENED PORCH (WITH ROOF) : 278 sqft |
| GARAGE: 839 sqft |
| Total Square Footage: 3591 sqft |
| Block: 00270 |
| Subdivision: 2214 - SECTION 19-WYNNFIELD |
| Job Phone: (386)445-9393 |
| Location Address: 81 WATERS DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 08/24/2020 |
| NOC: RECORDED |
| Applicant name: ANTONIO JR AMARAL |
| Owner: SALZA MARIA CARMEN TRUSTEE |
|
Address 81 WATERS DRIVE PALM COAST, FL 32164 |
| Lot: 0050 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
AMARAL HOMES & POOLS, LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
13 Utility Drive PALM COAST, FL 32137 |
CBC058062 (Exp: 08/31/2026) | (386)445-9393 |
Sub Contractors
RICHARD H SIMMONS JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 1963 BUNNELL, FL 32110 |
ES12001217 (Exp: 08/31/2026) | 386-437-0607 | 386-437-1847 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
THOMAS A REGULA
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
11320 PHILLIPS PKWY DRIVE E JACKSONVILLE, FL 32256 |
CMC1250075 (Exp: 08/31/2026) | 904-278-0339 | 904-278-0366 |
ANTONIO AMARAL JR
| Status | Location Address | State License Number |
| ACTIVE |
1370 PALM HARBOR PKWY PALM COAST, FL 32137 |
CCC058004 (Exp: 08/31/2026) |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 11/12/2021 | FINAL APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION Water heater not wired in. Insulation placard needs to be mounted in attic | |||
| ROW - FINAL APRON (AFTER POUR) | 11/12/2021 | APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION NEED TO CLEAN THE CULVERT PIPE IS FULL THE SAND | |||
| U-CROSS CONNECTION | 11/10/2021 | APPROVED | DHANEY |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION -please install a brass pressure vaume breaker not the plastic spoke with Tony JR who stated that they will be doing either a well or potable irrigation installed at a later date. I informed him to reschedule when irrigation does go in. Corrections have been made- 11/10/21 | |||
| ROW - FINAL APRON (AFTER POUR) | 11/10/2021 | Disapproved - NO FEE | GBERTOLA |
| Note: NEED TO CLEAN THE CULVERT PIPE IS FULL THE SAND | |||
| ROW - STORMWATER FINAL | 11/10/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: ON THE LEFT SIDE OF THE DRIVEWAY THE SAME NOT MATCHING EXISTING GRADE NEED TO REPAIRD THIS BEFORE ROW FINAL CLEAN THE CULVERTS FULL OF SAND. SWALE DAMAGE NEED TO BE COMPLETELY REPAIR AND RE-SOD. ALL RUTTS AND BARE SPOTS MUST BE FILLED AND SODDED, NOT SEEDED OR COVERED W/STRAW AND/OR PINE NEEDLE AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| U -UTILITY RESIDENTIAL FINAL | 11/10/2021 | FINAL APPROVED | DHANEY |
| BLD - BUILDING FINAL | 11/10/2021 | Disapproved - NO FEE | KSANDOE |
| Note: Water heater not wired in. Insulation placard needs to be mounted in attic | |||
| U-CROSS CONNECTION | 11/03/2021 | Disapproved - NO FEE | LFITZGERALD |
| Note: THIS IS A REINSPECTION -please install a brass pressure vaume breaker not the plastic spoke with Tony JR who stated that they will be doing either a well or potable irrigation installed at a later date. I informed him to reschedule when irrigation does go in. | |||
| ROW- PRE-APRON (PRE-POUR) | 11/03/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION ADDED ON 9/15/2021 11:04:42 AM AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. DRIVEWAY IS POUR ALREADY | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 10/27/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: SWALE ON THE RIGTH SIDE ON WYNNFIELD SOD IS NOT MATCHING EXISTING GRADE ON THE LEFT SIDE OF THE DRIVEWAY THE SAME NOT MATCHING EXISTING GRADE NEED TO REPAIRD THIS BEFORE ROW FINAL CLEAN THE CULVERTS FULL OF SAND. SWALE DAMAGE NEED TO BE COMPLETELY REPAIR AND RE-SOD. ALL RUTTS AND BARE SPOTS MUST BE FILLED AND SODDED, NOT SEEDED OR COVERED W/STRAW AND/OR PINE NEEDLE | |||
| FINAL SURVEY (OFFICE USE ONLY) | 10/27/2021 | APPROVED | GBERTOLA |
| ROW- PAVER RESTRAINTS | 09/15/2021 | APPROVED | GBERTOLA |
| ROW- PRE-APRON (PRE-POUR) | 09/15/2021 | PARTIALLY APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. | |||
| ELECTRIC - EARLY POWER | 08/17/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 9:08 am | |||
| GRAVITY SEWER TEST | 06/09/2021 | APPROVED | JGIBSON |
| U-CROSS CONNECTION | 06/09/2021 | CANCELLED BY APPLICANT | LFITZGERALD |
| Note: spoke with Tony JR who stated that they will be doing either a well or potable irrigation installed at a later date. I informed him to reschedule when irrigation does go in. | |||
| U - SEWER TIE IN | 06/09/2021 | APPROVED | JGIBSON |
| INSULATION | 04/22/2021 | APPROVED | MMESSER |
| Note: THIS IS A REINSPECTION Where insulation foam board was cut out for outlets, ect. cut out areas need to be filled in. | |||
| INSULATION | 04/20/2021 | Disapproved - NO FEE | JWALKER |
| Note: Where insulation foam board was cut out for outlets, ect. cut out areas need to be filled in. | |||
| LATH/BRICK/ WATER BARRIER | 03/18/2021 | APPROVED | FWILLIS |
| ROOF VALLEY & METAL | 03/11/2021 | APPROVED | JBODEN |
| ALL ROUGH | 03/11/2021 | APPROVED | JBODEN |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/24/2021 | APPROVED | FWILLIS |
| TIE BEAM / LINTEL | 01/26/2021 | APPROVED | MMESSER |
| FOUND SURVEY APPROVED (OFFICE) | 01/19/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 12/18/2020 | APPROVED | JBODEN |
| PLUMBING 1ST ROUGH UNDERGROUND | 10/28/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 10/20/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 01/15/2021 | 01/19/2021 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 01/15/2021 | 01/15/2021 |
| Note: Released By: TDOAK | |||
| MECH | COMPLETE | 12/03/2020 | 12/04/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 12/03/2020 | 12/03/2020 |
| Note: Released By: AMOBLEY | |||
| SW1 | COMPLETE | 11/24/2020 | 11/25/2020 |
| Note: Released By: CTROHA Stormwater review not requested on Permit Correction/Revision Form | |||
| BADMIN | COMPLETE | 11/24/2020 | 11/24/2020 |
| Note: Released By: STHOMAS | |||
| BLD | COMPLETE | 11/24/2020 | 12/03/2020 |
| Note: Released By: FREODICA Revision - Extended study/bedroom 3. | |||
| ELEC | COMPLETE | 11/24/2020 | 12/01/2020 |
| Note: Released By: JMUNSON | |||
| MECH | HOLD | 11/24/2020 | 11/24/2020 |
| Note: Held By: CPISCITELLI 1.Energy calcs and EPL card need to be signed by the builder. 2. Square footage of living space on floor plan does not reflect added space. | |||
| ZON | HOLD | 11/24/2020 | 11/24/2020 |
| Note: Held By: AMOBLEY Please provide a new site plan/survey showing changes | |||
| BADMIN | HOLD | 11/23/2020 | 11/23/2020 |
| Note: Held By: STHOMAS REMOVE 'SALZA, 81 WATERS DRIVE' FROM ALL FILE NAMES | |||
| SW1 | HOLD | 10/12/2020 | 10/12/2020 |
| Note: Held By: GBERTOLA please check the residential site plan reviews Lot drainage features and patterns must be clearly depicted and include flow arrows. Unless specifically stated the subject lot must drain from back to front or a portion STILL NOTHING CHANGE WE NEED FLOW ARROWS, MUST TO DRAIN TO THE FRONT | |||
| ZON | COMPLETE | 10/09/2020 | 10/09/2020 |
| Note: Released By: AMOBLEY | |||
| BLD | COMPLETE | 10/09/2020 | 10/16/2020 |
| Note: Released By: FREODICA Revision 2: Modified foundation detail on Sheet A7. | |||
| ENGIN1 | COMPLETE | 10/09/2020 | 10/13/2020 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 08/14/2020 | 08/14/2020 |
| Note: Released By: AMOBLEY | |||
| ELEC | COMPLETE | 08/14/2020 | 08/17/2020 |
| Note: Released By: JMUNSON | |||
| MECH | COMPLETE | 08/14/2020 | 08/14/2020 |
| Note: Released By: CPISCITELLI | |||
| BLD | COMPLETE | 08/14/2020 | 08/18/2020 |
| Note: Released By: JPI | |||
| PLUM | COMPLETE | 08/14/2020 | 08/18/2020 |
| Note: Released By: JPI | |||
| SWALE | COMPLETE | 08/03/2020 | 08/13/2020 |
| Note: Released By: TBAKER | |||
| BLD | HOLD | 07/31/2020 | 08/08/2020 |
| Note: Held By: JPI 1. Missing items from PA spec sheet: vents, and mullions. | |||
| CUSVC | COMPLETE | 07/31/2020 | 08/04/2020 |
| Note: Released By: HHAND | |||
| ELEC | HOLD | 07/31/2020 | 08/03/2020 |
| Note: Held By: JMUNSON Submit electrical load calculations. NEC 2014 art 220 | |||
| ENGIN1 | COMPLETE | 07/31/2020 | 08/03/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 07/31/2020 | 08/05/2020 |
| Note: Released By: CSTONE | |||
| MECH | HOLD | 07/31/2020 | 08/03/2020 |
| Note: Held By: CPISCITELLI 1. Plans call for R20 at roof deck. Energy calcs say R30. Revise to match. 2. Energy calcs and EPL card need to be signed by the builder | |||
| PLUM | HOLD | 07/31/2020 | 08/08/2020 |
| Note: Held By: JPI 1. No plumbing riser located, no review performed. | |||
| SW1 | COMPLETE | 07/31/2020 | 08/05/2020 |
| Note: Released By: CTROHA Read the information packet and look over the checklist for future site plans | |||
| UTL | COMPLETE | 07/31/2020 | 08/06/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 07/31/2020 | 08/03/2020 |
| Note: Held By: AMOBLEY Lot needs a total of 5 replacement trees AC Pad must be screened with 7 gallon shrubs |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REVISION | ¤40.00 | 11/12/2021 |
| REVISION | ¤40.00 | 11/12/2021 |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 11/12/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 08/24/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 08/24/2020 |
| SEWER CREDIT | (¤1,147.00) | 08/24/2020 |
| SEWER INSPECTION | ¤25.00 | 08/24/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 08/24/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 08/24/2020 |
| SITE PLAN 20 | ¤20.00 | 08/24/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 08/24/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 08/24/2020 |
| METER - DEPOSIT | ¤60.00 | 08/24/2020 |
| WATER- TURN ON | ¤25.00 | 08/24/2020 |
| ADMIN FEE | ¤20.00 | 08/24/2020 |
| CONNECTION FEES | ¤1,002.88 | 08/24/2020 |
| BUILDING DISCOUNT 100% | (¤1,514.60) | 08/24/2020 |
| ELECTRIC FEE | ¤247.80 | 08/24/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 08/24/2020 |
| IMPACT FEE FIRE | ¤223.38 | 08/24/2020 |
| IMPACT FEE PARKS | ¤849.24 | 08/24/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 08/24/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 08/24/2020 |
| MECHANICAL FEE | ¤247.80 | 08/24/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 08/24/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 08/24/2020 |
| PLAN CHECK FEE | ¤125.20 | 08/24/2020 |
| PLUMBING FEE | ¤247.80 | 08/24/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤626.00 | 08/24/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤14,429.35 |