I want to search for...

Permit #2020080109

Permit Details

Status: COED

Parcel Id: 07-11-31-7057-00660-0070
CONDITIONED SPACE: 2052 sqft
GARAGE: 407 sqft
OPENED PORCH (WITH ROOF) : 16 sqft
Total Square Footage: 2475 sqft
Block: 00660
Subdivision: -
Job Phone: 904-268-7730
Location Address: 85 ULYSSES TR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/08/2020
NOC: RECORDED
Applicant name: SCOTT CHRISTIAN HOWARD
Owner: MARONDA HOMES INC

Address

5220 SHAD ROAD STE 202

JACKSONVILLE, FL 32257

Lot: 0070
Contracted Stated Job Value: ¤125,000.00
Job Description: SINGLE FAMILY DWELLING
Type: CN

Contractor

MARONDA HOMES
Status Location Address State License Number Phone
INACTIVE

4005 MARONDA WAY

,

CRC056762 (Exp: 08/31/2026) 904-268-7730

Sub Contractors

JOSEPH H STRADA JR
Status Location Address State License Number Phone
CANCEL

3400 ST JOHNS PKWY

SANFORD, FL 32771

EC13003715 (Exp: 08/31/2022) 877-906-1113
RONALD KEVIN HAUPT
Status Location Address State License Number Phone
ACTIVE

4005 MARONDA WAY

SANFORD, FL 32771

CAC058534 (Exp: 08/31/2026) 407-321-0064
JEFFREY TROY SABAKA
Status Location Address State License Number Phone Fax
ACTIVE

2191 DEERWOOD ACRES DR

ST AUGUSTINE, FL 32084

CFC1427439 (Exp: 08/31/2026) 904-838-2218 904-819-0965
CLINTON J HULSLANDER SR
Status Location Address State License Number Phone Fax
ACTIVE

4005 MARONDA WAY

SANFORD, FL 32771

CFC1430632 (Exp: 08/31/2026) 407-321-0064 407-688-8534
ANDREW SCOTT DIGAETANO JR
Status Location Address State License Number Phone
ACTIVE

44 FORT CAROLINE

PALM COAST, FL 32137

CCC1331606 (Exp: 08/31/2026) 386-302-9063

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 02/18/2021 FINAL APPROVED TSTAUFFACHER
U -UTILITY RESIDENTIAL FINAL 02/18/2021 FINAL APPROVED JHARDING
ROW - STORMWATER FINAL 02/16/2021 APPROVED - AS NOTED KRUTH
Note: THIS IS A REINSPECTION 5. All disturbed areas of the site shall be stabilized with seed and straw or pine needles. The dumpster needs to be removed before the Stormwater Final will be passed. corrections made
ROW - STORMWATER FINAL 02/01/2021 Disapproved -FEE REQUIRED KRUTH
Note: 5. All disturbed areas of the site shall be stabilized with seed and straw or pine needles. The dumpster needs to be removed before the Stormwater Final will be passed.
ROW - FINAL APRON (AFTER POUR) 02/01/2021 APPROVED KRUTH
ELECTRIC - EARLY POWER 02/01/2021 APPROVED - AS NOTED JMUNSON
Note: Emailed FPL at 8:36 am
FINAL SURVEY (OFFICE USE ONLY) 01/27/2021 APPROVED KRUTH
ROW FIELD SURVEY /GRADING CERTIFICATION 01/27/2021 APPROVED KRUTH
U - SEWER TIE IN 01/11/2021 APPROVED JGIBSON
ROW- PRE-APRON (PRE-POUR) 12/17/2020 CANCELLED BY APPLICANT WEB
ROW- PRE-APRON (PRE-POUR) 12/17/2020 APPROVED - AS NOTED KRUTH
Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. pipe elevation is good
INSULATION 12/14/2020 APPROVED TSTAUFFACHER
LATH/BRICK/ WATER BARRIER 12/09/2020 APPROVED TSTAUFFACHER
ALL ROUGH 12/09/2020 APPROVED TSTAUFFACHER
Note: Super Note:: Fire block at hood vent in kitchen. Check at insulation.
U-CROSS CONNECTION 12/09/2020 APPROVED - AS NOTED JHARDING
Note: No irrigation. No cross connections.
ROOF VALLEY & METAL 12/08/2020 APPROVED JBODEN
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/30/2020 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION DOCUMENTS MUST BE APPROVED AND KEPT ON SITE 107.3,1. AND SHALL BE OPEN TO INSPECTION BY THE BUILDING OFFICIAL (need the APPROVED paperwork on site at time of inspection) truss plans not on site.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/24/2020 Disapproved - NO FEE TSTAUFFACHER
Note: DOCUMENTS MUST BE APPROVED AND KEPT ON SITE 107.3,1. AND SHALL BE OPEN TO INSPECTION BY THE BUILDING OFFICIAL (need the APPROVED paperwork on site at time of inspection) truss plans not on site.
FOUND SURVEY APPROVED (OFFICE) 10/29/2020 APPROVED TBAKER
TIE BEAM / LINTEL 10/26/2020 APPROVED FWILLIS
MONOLITHIC SLAB 10/13/2020 APPROVED FWILLIS
PLUMBING 1ST ROUGH UNDERGROUND 10/02/2020 APPROVED JGIBSON
GRAVITY SEWER TEST 10/02/2020 APPROVED JGIBSON
WATER METER INSTALLATION REQUEST 09/17/2020 APPROVED CSTONE

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 10/28/2020 10/29/2020
Note: Released By: TBAKER
ZON COMPLETE 10/28/2020 10/28/2020
Note: Released By: TDOAK
MECH COMPLETE 09/03/2020 09/03/2020
Note: Released By: CPISCITELLI
MECH HOLD 08/27/2020 08/28/2020
Note: Held By: CPISCITELLI R403.7.1.2.1 FBC Energy Conservation 2017 6TH Edition- Chosen equipment exceeds the maximum of 1.15 times the load calculated.
ZON COMPLETE 08/19/2020 08/19/2020
Note: Released By: AMOBLEY
MECH HOLD 08/19/2020 08/19/2020
Note: Held By: CPISCITELLI Orientation of Heat load does not match the site plan. Revise to match the site plan.
UTL COMPLETE 08/19/2020 08/25/2020
Note: Released By: LFITZGERALD
ENGIN1 COMPLETE 08/19/2020 08/19/2020
Note: Released By: TBAKER
SW1 COMPLETE 08/19/2020 08/21/2020
Note: Released By: CTROHA Stormwater review not requested on the Permit Correction form
SWALE COMPLETE 08/05/2020 08/21/2020
Note: Released By: TBAKER
BLD COMPLETE 08/04/2020 08/05/2020
Note: Released By: JPI
CUSVC COMPLETE 08/04/2020 08/05/2020
Note: Released By: HHAND
ELEC COMPLETE 08/04/2020 08/05/2020
Note: Released By: JMUNSON
ENGIN1 COMPLETE 08/04/2020 08/05/2020
Note: Released By: TBAKER
LOCATE COMPLETE 08/04/2020 08/05/2020
Note: Released By: CSTONE
MECH HOLD 08/04/2020 08/06/2020
Note: Held By: CPISCITELLI 1. Design Location on Energy calcs needs to be closer to palm coast, I E Daytona Beach or St.Augustine 2. Duct Drawing needs to be signed by the AC contractor
PLUM COMPLETE 08/04/2020 08/05/2020
Note: Released By: JPI
SW1 COMPLETE 08/04/2020 08/07/2020
Note: Released By: CTROHA
UTL COMPLETE 08/04/2020 08/06/2020
Note: Released By: LFITZGERALD
ZON HOLD 08/04/2020 08/05/2020
Note: Held By: AMOBLEY Survey/Site plan missing AC Pad location Garage Door missing banding on plans

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
STORMWATER REINSPECTION FEE ¤40.00 02/22/2021
3% TRANS IMPACT FEE CREDIT (¤50.22) 09/08/2020
SEWER CREDIT (¤850.00) 09/08/2020
SEWER INSPECTION ¤25.00 09/08/2020
SEWER CAPITAL FACILITY ¤4,596.07 09/08/2020
WATER CAPITAL FACILITY FEE ¤3,374.18 09/08/2020
METER - DEPOSIT ¤60.00 09/08/2020
WATER- TURN ON ¤25.00 09/08/2020
ADMIN FEE ¤20.00 09/08/2020
CONNECTION FEES ¤1,002.88 09/08/2020
BUILDING DISCOUNT 100% (¤1,229.00) 09/08/2020
ELECTRIC FEE ¤207.00 09/08/2020
3% FIRE IMPACT FEE CREDIT (¤6.70) 09/08/2020
IMPACT FEE FIRE ¤223.38 09/08/2020
IMPACT FEE PARKS ¤849.24 09/08/2020
IMPACT FEE SCHOOL ¤3,600.00 09/08/2020
IMPACT FEE TRANSPORTATION ¤1,674.00 09/08/2020
MECHANICAL FEE ¤207.00 09/08/2020
WATER -IRRIGATION INSPECTION ¤25.00 09/08/2020
3% PARKS IMPACT FEE CREDIT (¤25.48) 09/08/2020
PLAN CHECK FEE ¤98.00 09/08/2020
PLUMBING FEE ¤207.00 09/08/2020
NEW RESIDENTIAL INSPECTIONS ¤490.00 09/08/2020
SITE PLAN 20 ¤20.00 09/08/2020
SURCHARGE FS 533.721 ¤2.00 09/08/2020
SURCHARGE - FS 468.631 ¤2.00 09/08/2020
STORM WATER PERMIT FEES ¤80.00 09/08/2020
Fees Total Due: ¤0.00 Total Paid: ¤14,666.35