Permit #2020081237

Permit Details

Status: COED

Parcel Id: 07-11-31-7034-01420-0120
CONDITIONED SPACE: 2055 sqft
GARAGE: 419 sqft
OPENED PORCH (WITH ROOF) : 291 sqft
OPENED PORCH (WITH ROOF) : 50 sqft
Total Square Footage: 2815 sqft
Block: 01420
Subdivision: 2165 - SECTION 34-EASTHAMPTON
Job Phone: (386) 672-8285
Location Address: 74 EDITH POPE DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/14/2020
NOC: RECORDED
Applicant name: JOSEPH TODD VANACORE
Owner: WILLIAMS PATRICK A & MARY C FORTUNE-WILLIAMS H&W

Address

APT 546

SANDY SPRINGS, CA 30328

Address

6919 PEACHTREE DUNWOODY RD

SANDY SPRINGS, CA 30328

Lot: 0120
Contracted Stated Job Value: ¤190,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

VANACORE CONSTRUCTION INC.
Status Location Address Mailing Address State License Number Phone
INACTIVE

1451 N US HIGHWAY 1

Ormond Beach, FL 32174

SUITE 13

Ormond Beach, FL 32174

CBC058991 (Exp: 08/31/2024) (386) 672-8285

Sub Contractors

JEFFREY DALE KNIGHT
Status Location Address State License Number Phone Fax
INACTIVE

923 ASHMEADE CT

PORT ORANGE, FL 32127

CFC057351 (Exp: 08/31/2026) 386-345-3857 386-345-4443
VERNON JACK SMITH III
Status Location Address State License Number Phone Fax
ACTIVE

224 KIRKLAND ROAD

NEW SMYRNA BEACH, FL 32169

EC13004432 (Exp: 08/31/2026) 386-409-3616 386-409-3616
ALFRED N FYOCK JR
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

387 SAULS

ORMOND BEACH, FL 32174

ST

ORMOND BEACH, FL 32174

CCC1329075 (Exp: 08/31/2026) 386-566-6112 386-673-4299
SHAWN MICHAEL HISS
Status Location Address State License Number Phone
ACTIVE

1315 LPGA BLVD

HOLLY HILL, FL 32117

CAC1813585 (Exp: 08/31/2026) (386)672-8688

Inspection History

Type Request Date Result Inspector
PLUMBING FINAL 05/04/2021 Approval - Private Provider PPROVIDER
HVAC FINAL 05/04/2021 Approval - Private Provider PPROVIDER
ELECTRIC FINAL 05/04/2021 Approval - Private Provider PPROVIDER
BLD - BUILDING FINAL 05/04/2021 Approval - Private Provider PPROVIDER
ROW - FINAL APRON (AFTER POUR) 04/16/2021 APPROVED RGROSS
Note: THIS IS A REINSPECTION FOR THE ROW FINAL REPAIR THE SWALE WHERE THE POTTY IS REMOVE THE POTTY FROM THE SWALE AND PLACE ON THE DRIVEWAY
ROW - STORMWATER FINAL 04/16/2021 APPROVED RGROSS
Note: THIS IS A REINSPECTION FOR THE ROW FINAL REPAIR THE SWALE WHERE THE POTTY IS REMOVE THE POTTY FROM THE SWALE AND PLACE ON THE DRIVEWAY NEED TO REMOVE THE CONCRETE OVER POUR ON BOTH SIDE OF THE MINOR END
U -UTILITY RESIDENTIAL FINAL 04/14/2021 FINAL APPROVED JHARDING
ROW - STORMWATER FINAL 04/14/2021 CANCELLED BY APPLICANT WEB
ROW - STORMWATER FINAL 04/14/2021 Disapproved - NO FEE GBERTOLA
Note: FOR THE ROW FINAL REPAIR THE SWALE WHERE THE POTTY IS REMOVE THE POTTY FROM THE SWALE AND PLACE ON THE DRIVEWAY NEED TO REMOVE THE CONCRETE OVER POUR ON BOTH SIDE OF THE MINOR END
ROW - FINAL APRON (AFTER POUR) 04/14/2021 Disapproved - NO FEE GBERTOLA
Note: FOR THE ROW FINAL REPAIR THE SWALE WHERE THE POTTY IS REMOVE THE POTTY FROM THE SWALE AND PLACE ON THE DRIVEWAY NEED TO REMOVE THE CONCRETE OVER POUR ON BOTH SIDE OF THE MINOR END
ROW FIELD SURVEY /GRADING CERTIFICATION 04/13/2021 APPROVED RGROSS
FINAL SURVEY (OFFICE USE ONLY) 04/13/2021 APPROVED RGROSS
U-CROSS CONNECTION 04/09/2021 APPROVED - AS NOTED JHARDING
Note: No cross connections.
ROW- PRE-APRON (PRE-POUR) 03/08/2021 APPROVED - AS NOTED GBERTOLA
Note: AT THE TIME OF THE INSPECTION COLVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. BENCH MARK IS NOT ON THE RIGHT SIDE OF THE PRPERTY. IT'S ON THE LEFT SIDE POWER POLE
ELECTRIC - EARLY POWER 03/08/2021 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 02/17/2021 Approval - Private Provider PPROVIDER
Note: 02/17/2021 Sewer Tie In inspection passed.
U - SEWER TIE IN 02/17/2021 Approval - Private Provider PPROVIDER
Note: 02/17/2021 Sewer Tie In inspection passed.
PEP TANK INSTALLATION REQUEST 01/08/2021 APPROVED CSTONE
FOUND SURVEY APPROVED (OFFICE) 01/07/2021 APPROVED BBEMBRY
LATH/BRICK/ WATER BARRIER 12/30/2020 Approval - Private Provider PPROVIDER
INSULATION 12/22/2020 Approval - Private Provider PPROVIDER
ALL ROUGH 12/17/2020 Approval - Private Provider PPROVIDER
FRAMING 12/17/2020 Approval - Private Provider PPROVIDER
ROOF VALLEY & METAL 12/07/2020 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 12/02/2020 Approval - Private Provider PPROVIDER
TIE BEAM / LINTEL 11/23/2020 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 10/26/2020 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH UNDERGROUND 10/21/2020 Approval - Private Provider PPROVIDER
WATER METER INSTALLATION REQUEST 10/16/2020 APPROVED CSTONE

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 04/12/2021 04/12/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 01/07/2021 01/07/2021
Note: Released By: BBEMBRY foundation survey meets setbacks.
ENGIN1 COMPLETE 01/04/2021 01/05/2021
Note: Released By: TBAKER
ENGIN1 COMPLETE 01/04/2021 01/05/2021
Note: Released By: TBAKER
BADMIN COMPLETE 11/23/2020 11/23/2020
Note: Released By: STHOMAS
ENGIN1 COMPLETE 11/05/2020 11/06/2020
Note: Released By: TBAKER
ZON COMPLETE 11/05/2020 11/05/2020
Note: Released By: TDOAK
BADMIN HOLD 09/17/2020 09/17/2020
Note: Held By: BBEMBRY The NOC has the wrong county and state. The NOC must state which county/state for the location (at the top). It looks like the notary is from a different state and county and made the mistake of entering that instead of Flagler and Florida.
ZON COMPLETE 09/10/2020 09/10/2020
Note: Released By: AMOBLEY
SWALE COMPLETE 08/27/2020 09/21/2020
Note: Released By: TBAKER
CUSVC COMPLETE 08/26/2020 08/26/2020
Note: Released By: HHAND
ENGIN1 COMPLETE 08/26/2020 08/27/2020
Note: Released By: TBAKER
LOCATE COMPLETE 08/26/2020 08/28/2020
Note: Released By: CSTONE
SW1 COMPLETE 08/26/2020 08/28/2020
Note: Released By: CTROHA
UTL COMPLETE 08/26/2020 09/01/2020
Note: Released By: LFITZGERALD
ZON HOLD 08/26/2020 08/28/2020
Note: Held By: AMOBLEY Banding must wrap both corners at least two feet. Right side is missing the wrapped banding

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
METER - DEPOSIT ¤60.00 09/14/2020
WATER- TURN ON ¤25.00 09/14/2020
ADMIN FEE ¤145.00 09/14/2020
CONNECTION FEES ¤1,002.88 09/14/2020
BUILDING DISCOUNT 100% (¤20.00) 09/14/2020
3% FIRE IMPACT FEE CREDIT (¤6.70) 09/14/2020
IMPACT FEE FIRE ¤223.38 09/14/2020
IMPACT FEE PARKS ¤849.24 09/14/2020
IMPACT FEE SCHOOL ¤3,600.00 09/14/2020
IMPACT FEE TRANSPORTATION ¤1,674.00 09/14/2020
WATER -IRRIGATION INSPECTION ¤25.00 09/14/2020
3% PARKS IMPACT FEE CREDIT (¤25.48) 09/14/2020
SITE PLAN 20 ¤20.00 09/14/2020
SURCHARGE FS 533.721 ¤2.00 09/14/2020
SURCHARGE - FS 468.631 ¤2.24 09/14/2020
STORM WATER PERMIT FEES ¤80.00 09/14/2020
3% TRANS IMPACT FEE CREDIT (¤50.22) 09/14/2020
SEWER CREDIT (¤850.00) 09/14/2020
SEWER INSPECTION ¤25.00 09/14/2020
SEWER CAPITAL FACILITY ¤4,596.07 09/14/2020
WATER CAPITAL FACILITY FEE ¤3,374.18 09/14/2020
Fees Total Due: ¤0.00 Total Paid: ¤14,751.59