I want to search for...
Permit #2020090116
Permit Details
Status: COED
| Parcel Id: 07-11-31-7029-00640-0010 |
| CONDITIONED SPACE: 2517 sqft |
| GARAGE: 484 sqft |
| OPENED PORCH (WITH ROOF) : 380 sqft |
| OPENED PORCH (WITH ROOF) : 146 sqft |
| Total Square Footage: 3527 sqft |
| Block: 00640 |
| Subdivision: 2209 - SECTION 29-ROYAL PALMS |
| Job Phone: 386-447-7007 |
| Location Address: 88 RYAN DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/29/2020 |
| NOC: RECORDED |
| Applicant name: MAXIM TARANNIK |
| Owner: TRANG IDA |
|
Address 3981 EAST MEADOW DRIVE DULUTH, GA 30096 |
| Lot: 0010 |
| Contracted Stated Job Value: ¤330,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
GOLDEN MAGNOLIA, INC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1 ROCKEFELLER DRIVE PALM COAST, FL 32164 |
RR282811984 (Exp: 08/31/2025) | 386-447-7007 |
Sub Contractors
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
FERNANDO MEZA SR
| Status | Location Address | State License Number | Phone |
| CANCEL |
457 CHELSEA PLACE AV ORMOND BEACH, FL 32174 |
EC13003906 (Exp: 08/31/2022) | 570-575-8139 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 09/09/2021 | Disapproved - NO FEE | JWALKER |
| Note: THIS IS A REINSPECTION Termite cert is not affixed to the electrical panel. Remove bush from the front of the access panel at the condensor to allow for required 30 inch work space NEC 210.26. Remove pile of broken concrete and 2x4s at side door. Please have the energy calculations and approved drawings on site for final inspection The 12-2 wire in the garage attic needs to be removed from the top of the plywood and protected due to the space being used as storage area. NEC 220.23 (A) Plastic dust covers need to be removed form smoke detectors Hot water heater has not been wired The A/C unit calls for 45 max amp breaker a 50 amp is installed The Air Handler calls for a 60 amp breaker a 50 is also installed for the unit. 9/9/21 The hot water suppy to the kitcheb sink is not working. Please have energy calculations and approved drawings on site for the final inspection | |||
| BLD - BUILDING FINAL | 09/09/2021 | FINAL APPROVED | JWALKER |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Termite cert is not affixed to the electrical panel. Remove bush from the front of the access panel at the condensor to allow for required 30 inch work space NEC 210.26. Remove pile of broken concrete and 2x4s at side door. Please have the energy calculations and approved drawings on site for final inspection The 12-2 wire in the garage attic needs to be removed from the top of the plywood and protected due to the space being used as storage area. NEC 220.23 (A) Plastic dust covers need to be removed form smoke detectors Hot water heater has not been wired The A/C unit calls for 45 max amp breaker a 50 amp is installed The Air Handler calls for a 60 amp breaker a 50 is also installed for the unit. 9/9/21 The hot water suppy to the kitcheb sink is not working. Please have energy calculations and approved drawings on site for the final inspection | |||
| BLD - BUILDING FINAL | 09/07/2021 | Disapproved -FEE REQUIRED | JWALKER |
| Note: Termite cert is not affixed to the electrical panel. Remove bush from the front of the access panel at the condensor to allow for required 30 inch work space NEC 210.26. Remove pile of broken concrete and 2x4s at side door. Please have the energy calculations and approved drawings on site for final inspection The 12-2 wire in the garage attic needs to be removed from the top of the plywood and protected due to the space being used as storage area. NEC 220.23 (A) Plastic dust covers need to be removed form smoke detectors Hot water heater has not been wired The A/C unit calls for 45 max amp breaker a 50 amp is installed The Air Handler calls for a 60 amp breaker a 50 is also installed for the unit. | |||
| ROW - FINAL APRON (AFTER POUR) | 09/07/2021 | APPROVED | KRUTH |
| ROW - STORMWATER FINAL | 09/07/2021 | APPROVED | KRUTH |
| U -UTILITY RESIDENTIAL FINAL | 08/31/2021 | FINAL APPROVED | LFITZGERALD |
| Note: THIS IS A REINSPECTION sewer riser pipe not lowered for pep tank or with flush mount cap to be flush with grade(one by side of house with same situation) | |||
| U -UTILITY RESIDENTIAL FINAL | 08/23/2021 | Disapproved -FEE REQUIRED | LFITZGERALD |
| Note: sewer riser pipe not lowered for pep tank or with flush mount cap to be flush with grade(one by side of house with same situation) | |||
| U-CROSS CONNECTION | 08/23/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation-no cross connection | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 08/20/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| FINAL SURVEY (OFFICE USE ONLY) | 08/20/2021 | APPROVED | GBERTOLA |
| ROW- PRE-APRON (PRE-POUR) | 06/11/2021 | APPROVED - AS NOTED | RGROSS |
| Note: Faceboard was hit by a car. Be sure to reestablish the face board so that it is level and above the road edge. After that ...Ready to pour. | |||
| U - SEWER TIE IN | 05/27/2021 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 05/27/2021 | APPROVED | JGIBSON |
| ELECTRIC - EARLY POWER | 05/17/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: THIS IS A REINSPECTION Neutral wire needs to be phased in meter can. NEC 2014 200.6 5?17/21 Emailed FPL at 9:07 am | |||
| ELECTRIC - EARLY POWER | 05/14/2021 | Disapproved - NO FEE | JMUNSON |
| Note: Neutral wire needs to be phased in meter can. NEC 2014 200.6 | |||
| PEP TANK INSTALLATION REQUEST | 04/30/2021 | APPROVED | CSTONE |
| PEP TANK INSTALLATION REQUEST | 04/29/2021 | CANCELLED BY APPLICANT | WEB |
| LATH/BRICK/ WATER BARRIER | 04/05/2021 | APPROVED | JBODEN |
| INSULATION | 04/05/2021 | APPROVED - AS NOTED | JBODEN |
| Note: seal penetration at pantry switch | |||
| ALL ROUGH | 03/25/2021 | APPROVED - AS NOTED | MMESSER |
| Note: Need A/C platform finished before insulation inspection. | |||
| ROOF VALLEY & METAL | 02/25/2021 | APPROVED | MMESSER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/23/2021 | APPROVED - AS NOTED | MMESSER |
| Note: Strap trusses A06, A07, A08 above garage entry door. | |||
| TIE BEAM / LINTEL | 02/05/2021 | APPROVED | MMESSER |
| FOUND SURVEY APPROVED (OFFICE) | 01/19/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 01/08/2021 | APPROVED | MMESSER |
| PLUMBING 1ST ROUGH UNDERGROUND | 12/28/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 12/16/2020 | APPROVED - AS NOTED | CSTONE |
| Note: Already installed 12/7/20 |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | HOLD | 09/02/2021 | 09/02/2021 |
| Note: Held By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM NOC NEEDS TO BE RECORDED AND CERTIFIED | |||
| BADMIN | COMPLETE | 09/02/2021 | 09/02/2021 |
| Note: Released By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM | |||
| BADMIN | HOLD | 06/23/2021 | 06/23/2021 |
| Note: Held By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM RENAME TO BLOWER DOOR.PDF | |||
| BADMIN | COMPLETE | 06/23/2021 | 06/23/2021 |
| Note: Released By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 01/19/2021 | 01/19/2021 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 01/19/2021 | 01/19/2021 |
| Note: Released By: TDOAK | |||
| ZON | COMPLETE | 01/18/2021 | 01/19/2021 |
| Note: Released By: AMOBLEY | |||
| ENGIN1 | COMPLETE | 01/18/2021 | 01/19/2021 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 09/15/2020 | 09/15/2020 |
| Note: Released By: ELENS | |||
| MECH | COMPLETE | 09/15/2020 | 09/15/2020 |
| Note: Released By: CPISCITELLI | |||
| ELEC | COMPLETE | 09/15/2020 | 09/15/2020 |
| Note: Released By: JMUNSON | |||
| SW1 | COMPLETE | 09/04/2020 | 09/04/2020 |
| Note: Released By: GBERTOLA | |||
| SWALE | COMPLETE | 09/03/2020 | 10/07/2020 |
| Note: Released By: TBAKER | |||
| UTL | COMPLETE | 09/02/2020 | 09/08/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 09/02/2020 | 09/03/2020 |
| Note: Held By: ELENS Foundation plantings required for this corner lot: 6 on left side-facing right of way, 8 across the front, 4 on the interior side (in addition to the A/C screening). Please relabel the "office" on the floor plan. (Cannot indicate a commercial use.) Can be labeled as "den" or "study". | |||
| BLD | COMPLETE | 09/02/2020 | 09/09/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 09/02/2020 | 09/04/2020 |
| Note: Released By: HHAND | |||
| ELEC | HOLD | 09/02/2020 | 09/03/2020 |
| Note: Held By: JMUNSON Submit riser diagram | |||
| ENGIN1 | COMPLETE | 09/02/2020 | 09/03/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 09/02/2020 | 09/04/2020 |
| Note: Released By: TCHURCHILL | |||
| MECH | HOLD | 09/02/2020 | 09/03/2020 |
| Note: Held By: CPISCITELLI Orientation of Energy calcs does not match the site plan. Revise to match the site plan. | |||
| PLUM | COMPLETE | 09/02/2020 | 09/09/2020 |
| Note: Released By: JPI |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 09/10/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/10/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/10/2021 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 09/10/2021 |
| REINSPECTION FEE | ¤40.00 | 09/10/2021 |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 09/10/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/29/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 09/29/2020 |
| SEWER CREDIT | (¤2,465.75) | 09/29/2020 |
| SEWER INSPECTION | ¤25.00 | 09/29/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 09/29/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 09/29/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤660.00 | 09/29/2020 |
| SITE PLAN 20 | ¤20.00 | 09/29/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 09/29/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 09/29/2020 |
| CONNECTION FEES | ¤1,002.88 | 09/29/2020 |
| METER - DEPOSIT | ¤60.00 | 09/29/2020 |
| WATER- TURN ON | ¤25.00 | 09/29/2020 |
| ADMIN FEE | ¤20.00 | 09/29/2020 |
| BUILDING DISCOUNT 100% | (¤1,586.00) | 09/29/2020 |
| ELECTRIC FEE | ¤258.00 | 09/29/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 09/29/2020 |
| IMPACT FEE FIRE | ¤223.38 | 09/29/2020 |
| IMPACT FEE PARKS | ¤849.24 | 09/29/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 09/29/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 09/29/2020 |
| MECHANICAL FEE | ¤258.00 | 09/29/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 09/29/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 09/29/2020 |
| PLAN CHECK FEE | ¤132.00 | 09/29/2020 |
| PLUMBING FEE | ¤258.00 | 09/29/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤13,230.60 |