I want to search for...
Permit #2020090249
Permit Details
Status: COED
| Parcel Id: 07-11-31-7017-00040-0470 |
| CONDITIONED SPACE: 3130 sqft |
| GARAGE: 560 sqft |
| OPENED PORCH (WITH ROOF) : 36 sqft |
| OPENED PORCH (WITH ROOF) : 400 sqft |
| Total Square Footage: 4126 sqft |
| Block: 00040 |
| Subdivision: 2129 - SECTION 17-BELLE TERRE |
| Job Phone: 904-268-7730 |
| Location Address: 15 BOLLING LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/24/2020 |
| NOC: RECORDED |
| Applicant name: SCOTT CHRISTIAN HOWARD |
| Owner: MARONDA HOMES, LLC OF FLORIDA |
|
Address 5220 SHAD ROAD JACKSONVILLE, FL 32257 |
|
Address STE 202 JACKSONVILLE, FL 32257 |
| Lot: 0470 |
| Contracted Stated Job Value: ¤135,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
MARONDA HOMES
| Status | Location Address | State License Number | Phone |
| INACTIVE |
4005 MARONDA WAY , |
CRC056762 (Exp: 08/31/2026) | 904-268-7730 |
Sub Contractors
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
JEFFREY TROY SABAKA
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
2191 DEERWOOD ACRES DR ST AUGUSTINE, FL 32084 |
CFC1427439 (Exp: 08/31/2026) | 904-838-2218 | 904-819-0965 |
ANDREW SCOTT DIGAETANO JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
44 FORT CAROLINE PALM COAST, FL 32137 |
CCC1331606 (Exp: 08/31/2026) | 386-302-9063 |
MICHAEL LEE RAFFENSBERGER
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
7725 SANDSCOVE CT WINTER PARK, FL 32792 |
CAC1819723 (Exp: 08/31/2024) | 407-629-6920 | 407-629-9307 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - DRAINAGE | 04/21/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION ON THE LEFT CORNER BACK SIDE IS A FLAT SPOT ON THE FINAL SURVEY SHOULD NUMBERS FROM 25.70 TO 25.25 HOME OWNER IS COMPLIANING WATER ON HIS PROPERTY NEED TO FIX THAT CORNER AND MOVE THE WATER TO THE FRONT 04/16/2021= I HAVE A MEETING WITH THE BUILDER, SUPERVISOR WILL WORK IN THE BACK AREA TO CORRECT THE FLAT AREA BE BACK ON 04/19/2021 04/21/2021= CORRECTION WERE MADE | |||
| ROW - DRAINAGE | 04/16/2021 | Disapproved - NO FEE | GBERTOLA |
| Note: THIS IS A REINSPECTION ON THE LEFT CORNER BACK SIDE IS A FLAT SPOT ON THE FINAL SURVEY SHOULD NUMBERS FROM 25.70 TO 25.25 HOME OWNER IS COMPLIANING WATER ON HIS PROPERTY NEED TO FIX THAT CORNER AND MOVE THE WATER TO THE FRONT 04/16/2021= I HAVE A MEETING WITH THE BUILDER, SUPERVISOR WILL WORK IN THE BACK AREA TO CORRECT THE FLAT AREA BE BACK ON 04/19/2021 | |||
| U -UTILITY RESIDENTIAL FINAL | 04/16/2021 | FINAL APPROVED | DHANEY |
| BLD - BUILDING FINAL | 04/16/2021 | FINAL APPROVED | FWILLIS |
| U-CROSS CONNECTION | 04/16/2021 | APPROVED | DHANEY |
| ROW - DRAINAGE | 04/09/2021 | Disapproved - NO FEE | GBERTOLA |
| Note: ON THE LEFT CORNER BACK SIDE IS A FLAT SPOT ON THE FINAL SURVEY SHOULD NUMBERS FROM 25.70 TO 25.25 HOME OWNER IS COMPLIANING WATER ON HIS PROPERTY NEED TO FIX THAT CORNER AND MOVE THE WATER TO THE FRONT | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/31/2021 | APPROVED | KRUTH |
| ROW - STORMWATER FINAL | 03/31/2021 | APPROVED | KRUTH |
| ROW - FINAL APRON (AFTER POUR) | 03/31/2021 | APPROVED | KRUTH |
| FINAL SURVEY (OFFICE USE ONLY) | 03/31/2021 | APPROVED | KRUTH |
| ELECTRIC - EARLY POWER | 03/09/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 10:55 am | |||
| U - SEWER TIE IN | 03/01/2021 | APPROVED | JGIBSON |
| ROW- PRE-APRON (PRE-POUR) | 02/26/2021 | APPROVED | KRUTH |
| Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. pipe is good | |||
| INSULATION | 01/27/2021 | APPROVED | FWILLIS |
| ALL ROUGH | 01/25/2021 | APPROVED | FWILLIS |
| LATH/BRICK/ WATER BARRIER | 01/13/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 01/12/2021 | APPROVED | FWILLIS |
| ROOF VALLEY & METAL | 01/12/2021 | APPROVED | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 01/11/2021 | APPROVED | AMOBLEY |
| TIE BEAM / LINTEL | 12/03/2020 | APPROVED | TSTAUFFACHER |
| MONOLITHIC SLAB | 11/20/2020 | APPROVED | JBODEN |
| PLUMBING 1ST ROUGH UNDERGROUND | 11/17/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 11/17/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 10/02/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 01/11/2021 | 01/11/2021 |
| Note: Released By: AMOBLEY | |||
| ENGIN1 | COMPLETE | 01/08/2021 | 01/11/2021 |
| Note: Released By: TBAKER | |||
| ENGIN1 | COMPLETE | 12/10/2020 | 12/11/2020 |
| Note: Released By: TBAKER | |||
| ZON | HOLD | 12/10/2020 | 12/10/2020 |
| Note: Held By: TDOAK The 3'x3' concrete pad is encroaching in the 5' utility easement on the foundation survey. | |||
| SW1 | COMPLETE | 09/18/2020 | 09/18/2020 |
| Note: Released By: CTROHA | |||
| MECH | COMPLETE | 09/18/2020 | 09/18/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 09/18/2020 | 09/22/2020 |
| Note: Released By: AMOBLEY | |||
| UTL | COMPLETE | 09/18/2020 | 09/23/2020 |
| Note: Released By: LFITZGERALD | |||
| ENGIN1 | COMPLETE | 09/18/2020 | 09/21/2020 |
| Note: Released By: TBAKER | |||
| SW1 | HOLD | 09/08/2020 | 09/08/2020 |
| Note: Held By: GBERTOLA REVIEW THE CHECK LIST FLOW ARROWS NOT PRESENT . | |||
| SWALE | COMPLETE | 09/08/2020 | 10/14/2020 |
| Note: Released By: TBAKER | |||
| UTL | COMPLETE | 09/04/2020 | 09/10/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | COMPLETE | 09/04/2020 | 09/08/2020 |
| Note: Released By: AMOBLEY | |||
| BLD | COMPLETE | 09/04/2020 | 09/10/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 09/04/2020 | 09/08/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 09/04/2020 | 09/08/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 09/04/2020 | 09/08/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 09/04/2020 | 09/09/2020 |
| Note: Released By: TCHURCHILL | |||
| MECH | HOLD | 09/04/2020 | 09/08/2020 |
| Note: Held By: CPISCITELLI Orientation of heatload does not match the site plan. Revise to match the site plan | |||
| PLUM | COMPLETE | 09/04/2020 | 09/10/2020 |
| Note: Released By: JPI |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| 09/24/2020 | ||
| METER - DEPOSIT | ¤60.00 | 09/24/2020 |
| WATER- TURN ON | ¤25.00 | 09/24/2020 |
| ADMIN FEE | ¤20.00 | 09/24/2020 |
| CONNECTION FEES | ¤1,002.88 | 09/24/2020 |
| CONTRACTOR CHANGE | ¤40.00 | 09/24/2020 |
| BUILDING DISCOUNT 100% | (¤1,829.60) | 09/24/2020 |
| ELECTRIC FEE | ¤292.80 | 09/24/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 09/24/2020 |
| IMPACT FEE FIRE | ¤223.38 | 09/24/2020 |
| IMPACT FEE PARKS | ¤849.24 | 09/24/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 09/24/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 09/24/2020 |
| MECHANICAL FEE | ¤292.80 | 09/24/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 09/24/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 09/24/2020 |
| PLAN CHECK FEE | ¤155.20 | 09/24/2020 |
| PLUMBING FEE | ¤292.80 | 09/24/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤776.00 | 09/24/2020 |
| SITE PLAN 20 | ¤20.00 | 09/24/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 09/24/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 09/24/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/24/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 09/24/2020 |
| SEWER INSPECTION | ¤25.00 | 09/24/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 09/24/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 09/24/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,516.35 |