I want to search for...
Permit #2020090710
Permit Details
Status: COED
| Parcel Id: 21-10-30-5410-00000-1640 |
| CONDITIONED SPACE: 3004 sqft |
| GARAGE: 401 sqft |
| OPENED PORCH (WITH ROOF) : 60 sqft |
| Total Square Footage: 3465 sqft |
| Subdivision: 2135 - SAWMILL CREEK SUBDIVISION |
| Job Phone: 904-268-7730 |
| Location Address: 112 OAKLEAF WAY |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/29/2020 |
| NOC: RECORDED |
| Applicant name: SCOTT CHRISTIAN HOWARD |
| Owner: MARONDA HOMES LLC |
|
Address 5220 SHAD ROAD SUTE 202 JACKSONVILLE, FL 32257 |
| Lot: 164 |
| Contracted Stated Job Value: ¤140,000.00 |
| Job Description: SINGLE FAMILY DWELLING |
| Type: CN |
Contractor
MARONDA HOMES
| Status | Location Address | State License Number | Phone |
| INACTIVE |
4005 MARONDA WAY , |
CRC056762 (Exp: 08/31/2026) | 904-268-7730 |
Sub Contractors
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
MICHAEL LEE RAFFENSBERGER
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
7725 SANDSCOVE CT WINTER PARK, FL 32792 |
CAC1819723 (Exp: 08/31/2024) | 407-629-6920 | 407-629-9307 |
JEFFREY TROY SABAKA
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
2191 DEERWOOD ACRES DR ST AUGUSTINE, FL 32084 |
CFC1427439 (Exp: 08/31/2026) | 904-838-2218 | 904-819-0965 |
ANDREW SCOTT DIGAETANO JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
44 FORT CAROLINE PALM COAST, FL 32137 |
CCC1331606 (Exp: 08/31/2026) | 386-302-9063 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 04/21/2021 | FINAL APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| BLD - BUILDING FINAL | 04/20/2021 | CANCELLED BY APPLICANT | FWILLIS |
| U -UTILITY RESIDENTIAL FINAL | 04/20/2021 | FINAL APPROVED | DHANEY |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/30/2021 | APPROVED | KRUTH |
| ROW - STORMWATER FINAL | 03/30/2021 | APPROVED | KRUTH |
| ROW - FINAL APRON (AFTER POUR) | 03/30/2021 | APPROVED | KRUTH |
| FINAL SURVEY (OFFICE USE ONLY) | 03/30/2021 | APPROVED | KRUTH |
| U-CROSS CONNECTION | 03/18/2021 | APPROVED - AS NOTED | JHARDING |
| Note: Approved, no cross connections. | |||
| ROW- PRE-APRON (PRE-POUR) | 03/04/2021 | APPROVED - AS NOTED | KRUTH |
| Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete | |||
| ELECTRIC - EARLY POWER | 03/04/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 10:45 | |||
| U - SEWER TIE IN | 02/19/2021 | APPROVED | JGIBSON |
| INSULATION | 01/25/2021 | APPROVED | FWILLIS |
| ALL ROUGH | 01/22/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION 5ft HEAD OF WATER, 6TH EDITION FBC CHAPTER 25 SECTION P2503.5.1 (1) and or FBC CHAPTER 25 SECTION P2503.5.1 BUILDING SEWER TESTING Must use water for testing plastic pipes. Testing with not less than 5-foot (3048mm) of head water and be able to maintain such pressure for 15 minutes. | |||
| LATH/BRICK/ WATER BARRIER | 01/22/2021 | APPROVED | FWILLIS |
| ALL ROUGH | 01/20/2021 | Disapproved - NO FEE | FWILLIS |
| Note: 5ft HEAD OF WATER, 6TH EDITION FBC CHAPTER 25 SECTION P2503.5.1 (1) and or FBC CHAPTER 25 SECTION P2503.5.1 BUILDING SEWER TESTING Must use water for testing plastic pipes. Testing with not less than 5-foot (3048mm) of head water and be able to maintain such pressure for 15 minutes. | |||
| ROOF VALLEY & METAL | 01/19/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 01/08/2021 | APPROVED | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 11/19/2020 | APPROVED | TBAKER |
| TIE BEAM / LINTEL | 11/12/2020 | APPROVED | JCOLASANTI |
| MONOLITHIC SLAB | 11/04/2020 | APPROVED | TSTAUFFACHER |
| Note: THIS IS A REINSPECTION center steel gargage left corner...entry footers need to be 12" deep all the way around | |||
| MONOLITHIC SLAB | 11/03/2020 | Disapproved - NO FEE | JCOLASANTI |
| Note: center steel gargage left corner...entry footers need to be 12" deep all the way around | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 10/28/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 10/28/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 10/02/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ZON | CANCEL | 02/23/2021 | 02/23/2021 |
| Note: Good afternoon, I didn't mean to upload the revision on permit # 2020090710. Please cancel that. I apologize. Sending positive vibes your way, Jeremy Friedman Permitting Coordinator O: 904-268-7730 | M: 904-305-8901 | friedmanj@maronda.com 5220 Shad Road #202 | Jacksonville, FL 32257 | |||
| SW1 | CANCEL | 02/22/2021 | 02/23/2021 |
| ENGIN1 | CANCEL | 02/22/2021 | 02/23/2021 |
| ZON | HOLD | 02/22/2021 | 02/22/2021 |
| Note: Held By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM There is already an approved foundation survey with the house at the originally approved setback. | |||
| SW1 | HOLD | 12/04/2020 | 12/04/2020 |
| Note: Held By: GBERTOLA LOOKING ON THE SITE PLAN ON THE RIGHT SIDE NEED MORE ELEVATION FRONT THE BACK TO FRONT EVEN BY THE SIDE WALK | |||
| ZON | COMPLETE | 12/03/2020 | 12/03/2020 |
| Note: Released By: TDOAK | |||
| ENGIN1 | COMPLETE | 12/03/2020 | 12/04/2020 |
| Note: Released By: TBAKER | |||
| ENGIN1 | COMPLETE | 11/18/2020 | 11/19/2020 |
| Note: Released By: TBAKER Foundation Survey | |||
| ZON | COMPLETE | 11/18/2020 | 11/18/2020 |
| Note: Released By: AMOBLEY | |||
| MECH | COMPLETE | 09/25/2020 | 09/25/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 09/22/2020 | 09/23/2020 |
| Note: Released By: ELENS Bathroom 4 will be relabeled to bathroom # 3. Jeremy Friedman is sending in a revised floor plan. | |||
| UTL | COMPLETE | 09/22/2020 | 09/25/2020 |
| Note: Released By: LFITZGERALD | |||
| ENGIN1 | COMPLETE | 09/22/2020 | 09/23/2020 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 09/22/2020 | 09/22/2020 |
| Note: Released By: CTROHA | |||
| CUSVC | COMPLETE | 09/22/2020 | 09/22/2020 |
| Note: Released By: HHAND | |||
| MECH | HOLD | 09/22/2020 | 09/22/2020 |
| Note: Held By: CPISCITELLI 1. Orientation of Energy calcs does not match the site plan. Revise to match the site plan.(Second Request) | |||
| URB | COMPLETE | 09/21/2020 | 09/21/2020 |
| Note: Released By: JBEAUDET | |||
| SW1 | HOLD | 09/17/2020 | 09/17/2020 |
| Note: Held By: GBERTOLA PLEASE CHECK THE RESIDENTIAL SITE PLAN CHECK LIST Lot drainage features and patterns must be clearly depicted and include flow arrows. WE NEED THE FLOW ARROWS | |||
| UTL | COMPLETE | 09/16/2020 | 09/21/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 09/16/2020 | 09/21/2020 |
| Note: Held By: ELENS Should bathroom #4 downstairs be labeled bathroom #3? | |||
| BLD | COMPLETE | 09/16/2020 | 09/19/2020 |
| Note: Released By: JPI | |||
| CUSVC | HOLD | 09/16/2020 | 09/17/2020 |
| Note: Held By: HHAND Please update the utility application to have "reclaim" checked off. | |||
| ELEC | COMPLETE | 09/16/2020 | 09/17/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 09/16/2020 | 09/17/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 09/16/2020 | 09/18/2020 |
| Note: Released By: CSTONE | |||
| MECH | HOLD | 09/16/2020 | 09/17/2020 |
| Note: Held By: CPISCITELLI 1. Orientation of Energy calcs does not match the site plan. Revise to match the site plan. 2. Square footage on energy calcs and heat load do not match the house. Revise to match. 3. R403.7.1.2.1 FBC Energy Conservation 2017 6TH Edition- Chosen equipment exceeds the maximum of 1.15 times the load calculated. | |||
| PLUM | COMPLETE | 09/16/2020 | 09/19/2020 |
| Note: Released By: JPI |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| METER - DEPOSIT | ¤60.00 | 09/29/2020 |
| WATER-METER | ¤434.59 | 09/29/2020 |
| WATER-METER | ¤361.04 | 09/29/2020 |
| ADMIN FEE | ¤20.00 | 09/29/2020 |
| CONNECTION FEES | ¤25.00 | 09/29/2020 |
| BUILDING DISCOUNT 100% | (¤1,674.20) | 09/29/2020 |
| ELECTRIC FEE | ¤270.60 | 09/29/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 09/29/2020 |
| IMPACT FEE FIRE | ¤223.38 | 09/29/2020 |
| IMPACT FEE PARKS | ¤849.24 | 09/29/2020 |
| IMPACT FEE TRANSPORTATION | ¤3,059.00 | 09/29/2020 |
| MECHANICAL FEE | ¤270.60 | 09/29/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 09/29/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 09/29/2020 |
| PLAN CHECK FEE | ¤140.40 | 09/29/2020 |
| PLUMBING FEE | ¤270.60 | 09/29/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤702.00 | 09/29/2020 |
| SITE PLAN 20 | ¤20.00 | 09/29/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 09/29/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 09/29/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 09/29/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤91.77) | 09/29/2020 |
| SEWER INSPECTION | ¤25.00 | 09/29/2020 |
| SEWER CAPITAL FACILITY | ¤2,389.36 | 09/29/2020 |
| WATER CAPITAL FACILITY FEE | ¤2,234.43 | 09/29/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,666.09 |