I want to search for...
Permit #2020100007
Permit Details
Status: COED
| Parcel Id: 07-11-31-7035-01270-0030 |
| CONDITIONED SPACE: 2502 sqft |
| GARAGE: 785 sqft |
| OPENED PORCH (WITH ROOF) : 341 sqft |
| OPENED PORCH (WITH ROOF) : 145 sqft |
| Total Square Footage: 3773 sqft |
| Block: 01270 |
| Subdivision: 2172 - SECTION 35-BELLE TERRE |
| Job Phone: 386-931-5395 |
| Location Address: 5 BIDDING PL |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/20/2020 |
| NOC: RECORDED |
| Applicant name: RYAN JAMES PERRY |
| Owner: CONWAY, STEPHEN J. & PATRICIA S. |
|
Address 6336 STRASBOURG DRIVE CORPUS CHRISTI, TX 78414 |
| Lot: 0030 |
| Contracted Stated Job Value: ¤325,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
WATERSIDE HOMES RENOVATIONS AND DESIGNS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
10 BISCAYNE DRIVE PALM COAST, FL 32137 |
CBC1263021 (Exp: 08/31/2026) | 386-931-5395 |
Sub Contractors
PETER JOSEPH LYDEN
| Status | Location Address | State License Number | Phone |
| CANCEL |
17 UNIMAY CT BUNNELL, FL 32110 |
EC0002436 (Exp: 08/31/2022) | 386-931-2568 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
RYAN JAMES PERRY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
10 BISCAYNE DRIVE PALM COAST, FL 32137 |
CBC1263021 (Exp: 08/31/2026) | 386-931-5395 |
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
PO BOX 912 PALM COAST, FL 32164 |
CAC1820539 (Exp: 08/31/2026) | 386-264-0550 |
MARK A RUGGIERO
| Status | Location Address | State License Number | Phone |
| INACTIVE |
411 6TH STREET HOLLY HILL , FL 32117 |
01612 (Exp: 07/23/2023) | 386-252-5555 |
Inspection History
| Type | Request Date | Result | Inspector |
| GAS ROUGH | 09/17/2021 | APPROVED | RMARTIN |
| GAS FINAL | 09/17/2021 | APPROVED | RMARTIN |
| BLD - BUILDING FINAL | 09/17/2021 | FINAL APPROVED | RMARTIN |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION NEED TO BOND GAS LINE, NEED TO HAVE SEPERATE PERMIT FOR GENERATOR OR GENERATOR COMPLETED AND READY FOR INSPECTION, NEED TO HAVE REVISION ON SITE FOR MINI SPLIT, NEED TO HAVE SPRAY FOAM WALL OPENINGS CLOSED UP IN GARAGE CEILING 9/15/21 GENERATOR NOT DONE | |||
| BLD - BUILDING FINAL | 09/16/2021 | CANCELLED BY APPLICANT | RMARTIN |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION NEED TO BOND GAS LINE, NEED TO HAVE SEPERATE PERMIT FOR GENERATOR OR GENERATOR COMPLETED AND READY FOR INSPECTION, NEED TO HAVE REVISION ON SITE FOR MINI SPLIT, NEED TO HAVE SPRAY FOAM WALL OPENINGS CLOSED UP IN GARAGE CEILING 9/15/21 GENERATOR NOT DONE | |||
| BLD - BUILDING FINAL | 09/15/2021 | Disapproved - NO FEE | RMARTIN |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION NEED TO BOND GAS LINE, NEED TO HAVE SEPERATE PERMIT FOR GENERATOR OR GENERATOR COMPLETED AND READY FOR INSPECTION, NEED TO HAVE REVISION ON SITE FOR MINI SPLIT, NEED TO HAVE SPRAY FOAM WALL OPENINGS CLOSED UP IN GARAGE CEILING 9/15/21 GENERATOR NOT DONE | |||
| BLD - BUILDING FINAL | 09/14/2021 | CANCELLED BY APPLICANT | RMARTIN |
| Note: THIS IS A REINSPECTION NEED TO BOND GAS LINE, NEED TO HAVE SEPERATE PERMIT FOR GENERATOR OR GENERATOR COMPLETED AND READY FOR INSPECTION, NEED TO HAVE REVISION ON SITE FOR MINI SPLIT, NEED TO HAVE SPRAY FOAM WALL OPENINGS CLOSED UP IN GARAGE CEILING | |||
| BLD - BUILDING FINAL | 09/13/2021 | Disapproved - NO FEE | RMARTIN |
| Note: NEED TO BOND GAS LINE, NEED TO HAVE SEPERATE PERMIT FOR GENERATOR OR GENERATOR COMPLETED AND READY FOR INSPECTION, NEED TO HAVE REVISION ON SITE FOR MINI SPLIT, NEED TO HAVE SPRAY FOAM WALL OPENINGS CLOSED UP IN GARAGE CEILING | |||
| BLD - BUILDING FINAL | 09/10/2021 | CANCELLED BY APPLICANT | WEB |
| ELECTRIC - EARLY POWER | 09/03/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: 1. Need to have mini split added to electric plans and electric load calcs by final. 2. Emailed FPL at 11:08 am | |||
| U -UTILITY RESIDENTIAL FINAL | 07/27/2021 | FINAL APPROVED | DHANEY |
| Note: THIS IS A REINSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL | 07/22/2021 | CANCELLED BY APPLICANT | DHANEY |
| ROW - STORMWATER FINAL | 07/21/2021 | APPROVED - AS NOTED | KRUTH |
| Note: THIS IS A REINSPECTION need to pick up the garbage in the back of the property orange fence and plastic pipes . IN THE BACK YARD BY THE EMPTY LOT IS A BARE SPOT NEED TO BE SEEDED AND COVERT W/STRAW OR PINE NEEDLES corrections made 7/21/2021 | |||
| U-CROSS CONNECTION | 07/21/2021 | APPROVED | DHANEY |
| ROW - FINAL APRON (AFTER POUR) | 07/19/2021 | APPROVED | GBERTOLA |
| FINAL SURVEY (OFFICE USE ONLY) | 07/19/2021 | APPROVED | GBERTOLA |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 07/19/2021 | APPROVED | GBERTOLA |
| ROW - STORMWATER FINAL | 07/19/2021 | Disapproved - NO FEE | GBERTOLA |
| Note: need to pick up the garbage in the back of the property orange fence and plastic pipes . IN THE BACK YARD BY THE EMPTY LOT IS A BARE SPOT NEED TO BE SEEDED AND COVERT W/STRAW OR PINE NEEDLES | |||
| ROW- PRE-APRON (PRE-POUR) | 05/25/2021 | APPROVED - AS NOTED | KRUTH |
| Note: PIPE IS GOOD It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete | |||
| U - SEWER TIE IN | 04/29/2021 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 04/29/2021 | APPROVED | JGIBSON |
| PEP TANK INSTALLATION REQUEST | 03/29/2021 | APPROVED | CSTONE |
| INSULATION | 03/23/2021 | APPROVED | WMILLER |
| ALL ROUGH | 03/12/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Two Truss on the right side not under any column or have Hangers securing them. Need Clarification or Engineering Letter. 3/12/21 - Received Engineering Letter and installing Lag Bolts. | |||
| ALL ROUGH | 03/11/2021 | CANCELLED BY APPLICANT | FWILLIS |
| Note: THIS IS A REINSPECTION Two Truss on the right side not under any column or have Hangers securing them. Need Clarification or Engineering Letter. | |||
| LATH/BRICK/ WATER BARRIER | 03/10/2021 | APPROVED | WMILLER |
| ALL ROUGH | 03/09/2021 | Disapproved - NO FEE | FWILLIS |
| Note: Two Truss on the right side not under any column or have Hangers securing them. Need Clarification or Engineering Letter. | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/09/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Bearing Wall in Garage NOT PER PLAN. (3) 6X6 Posts and Connectors missing, Paralam and connectors missing. INSPECTION STOPPED 2/8/21 - PAGE A2 (FLOOR PLAN) SHOWS 4 2X6 POSTS WITH A HDU5 AT THE BOTTOM. 6X6 POST (ART STUDIO) SHOWS HDU5 AT THE BOTTOM. HTS 20 AT TOP SHOULD BE CONNECTED TO POST AS PER PLAN. 2/9/21 - Items Corrected. | |||
| ROOF VALLEY & METAL | 02/09/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/08/2021 | Disapproved - NO FEE | FWILLIS |
| Note: THIS IS A REINSPECTION Bearing Wall in Garage NOT PER PLAN. (3) 6X6 Posts and Connectors missing, Paralam and connectors missing. INSPECTION STOPPED 2/8/21 - PAGE A2 (FLOOR PLAN) SHOWS 4 2X6 POSTS WITH A HDU5 AT THE BOTTOM. 6X6 POST (ART STUDIO) SHOWS HDU5 AT THE BOTTOM. HTS 20 AT TOP SHOULD BE CONNECTED TO POST AS PER PLAN. | |||
| ELECTRIC-TUG | 02/08/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED TUG 9:50 | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/05/2021 | Disapproved - NO FEE | FWILLIS |
| Note: Bearing Wall in Garage NOT PER PLAN. (3) 6X6 Posts and Connectors missing, Paralam and connectors missing. INSPECTION STOPPED | |||
| TIE BEAM / LINTEL | 01/04/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Dowel Missing on left side marked in Orange. Window Sill Bed Joints exceed FBC R606.3.1 (3/8" to 1/2"). Marked in Orange at Window. 12/30/20 - ITEMS STILL OPEN, NO ADJUSTMENTS TO THE WINDOW SILL BED JOINTS, MARKED IN ORANGE, MADE. R606.3.1. 1/4/20 - ITEMS CORRECTED | |||
| TIE BEAM / LINTEL | 12/30/2020 | Disapproved - NO FEE | FWILLIS |
| Note: THIS IS A REINSPECTION Dowel Missing on left side marked in Orange. Window Sill Bed Joints exceed FBC R606.3.1 (3/8" to 1/2"). Marked in Orange at Window. 12/30/20 - ITEMS STILL OPEN, NO ADJUSTMENTS TO THE WINDOW SILL BED JOINTS, MARKED IN ORANGE, MADE. R606.3.1. | |||
| TIE BEAM / LINTEL | 12/29/2020 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: Dowel Missing on left side marked in Orange. Window Sill Bed Joints exceed FBC R606.3.1 (3/8" to 1/2"). Marked in Orange at Window. | |||
| FOUND SURVEY APPROVED (OFFICE) | 12/07/2020 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 11/23/2020 | APPROVED | FWILLIS |
| PLUMBING 1ST ROUGH UNDERGROUND | 11/20/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 10/29/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| PLUM | COMPLETE | 09/13/2021 | 09/13/2021 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 09/08/2021 | 09/08/2021 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BADMIN | HOLD | 07/16/2021 | 07/16/2021 |
| Note: Held By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM SHADE IN RAISED SEAL | |||
| BADMIN | COMPLETE | 07/16/2021 | 07/16/2021 |
| Note: Released By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/10/2021 | 03/16/2021 |
| Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 12/04/2020 | 12/07/2020 |
| Note: Released By: TBAKER Foundation Survey | |||
| ZON | COMPLETE | 12/04/2020 | 12/04/2020 |
| Note: Released By: TDOAK | |||
| SW1 | COMPLETE | 10/29/2020 | 11/02/2020 |
| Note: Released By: RGROSS | |||
| ENGIN1 | COMPLETE | 10/29/2020 | 10/30/2020 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 10/29/2020 | 10/29/2020 |
| Note: Released By: ELENS Zoning review not required. | |||
| SW1 | HOLD | 10/23/2020 | 10/27/2020 |
| Note: Held By: CTROHA Revise site plan to show where ROW beautification will be done | |||
| ZON | COMPLETE | 10/19/2020 | 10/20/2020 |
| Note: Released By: ELENS | |||
| ENGIN1 | COMPLETE | 10/13/2020 | 10/13/2020 |
| Note: Released By: TBAKER | |||
| ZON | HOLD | 10/13/2020 | 10/14/2020 |
| Note: Held By: ELENS One shade tree is required. (This was missed on first review.) | |||
| BLD | COMPLETE | 10/13/2020 | 10/15/2020 |
| Note: Released By: JPI | |||
| ENGIN1 | HOLD | 10/05/2020 | 10/06/2020 |
| Note: Held By: TBAKER Benchmark elevation disagrees with centerline of road elevation by .6' (possible typo in benchmark elevation on survey?) | |||
| BLD | HOLD | 10/01/2020 | 10/05/2020 |
| Note: Held By: JPI 1. Provide project specific roof ventilation calculations, per R806. 2. Footing plans call for Type 2A footing at garage separation wall and at entry door. Footing schedule illustrates a 2A footing as a two-story footing. at front entry. That per table is the garage footing. Clarify footing type. | |||
| CUSVC | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 10/01/2020 | 10/01/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 10/01/2020 | 10/07/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 10/01/2020 | 10/05/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 10/01/2020 | 10/05/2020 |
| Note: Released By: CTROHA | |||
| UTL | COMPLETE | 10/01/2020 | 10/08/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 10/01/2020 | 10/02/2020 |
| Note: Held By: ELENS Four foundation plantings are required on each side (in addition to A/C screening.) It appears that two more are required on each side. Two of the bedrooms on the floor plan are labeled Bedroom 2. | |||
| SWALE | COMPLETE | 10/01/2020 | 11/19/2020 |
| Note: Released By: TBAKER |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONTRACTOR CHANGE | ¤40.00 | 09/17/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/17/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/17/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/17/2021 |
| REINSPECTION FEE | ¤40.00 | 09/17/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤660.00 | 10/20/2020 |
| SITE PLAN 20 | ¤20.00 | 10/20/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/20/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/20/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/20/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 10/20/2020 |
| SEWER CREDIT | (¤850.00) | 10/20/2020 |
| SEWER INSPECTION | ¤25.00 | 10/20/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 10/20/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 10/20/2020 |
| METER - DEPOSIT | ¤60.00 | 10/20/2020 |
| WATER- TURN ON | ¤25.00 | 10/20/2020 |
| ADMIN FEE | ¤20.00 | 10/20/2020 |
| CONNECTION FEES | ¤1,002.88 | 10/20/2020 |
| BUILDING DISCOUNT 100% | (¤1,586.00) | 10/20/2020 |
| ELECTRIC FEE | ¤258.00 | 10/20/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 10/20/2020 |
| IMPACT FEE FIRE | ¤223.38 | 10/20/2020 |
| IMPACT FEE PARKS | ¤849.24 | 10/20/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 10/20/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 10/20/2020 |
| MECHANICAL FEE | ¤258.00 | 10/20/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/20/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 10/20/2020 |
| PLAN CHECK FEE | ¤132.00 | 10/20/2020 |
| PLUMBING FEE | ¤258.00 | 10/20/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤14,826.35 |