Permit #2020100039
Permit Details
Status: COED
| Parcel Id: 07-11-31-7037-01200-0060 |
| CONDITIONED SPACE: 2052 sqft |
| GARAGE: 407 sqft |
| OPENED PORCH (WITH ROOF) : 16 sqft |
| Total Square Footage: 2475 sqft |
| Block: 01200 |
| Subdivision: 2176 - SECTION 37-LAKEVIEW |
| Job Phone: 904-268-7730 |
| Location Address: 11 LOUISIANA DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/12/2020 |
| NOC: RECORDED |
| Applicant name: SCOTT CHRISTIAN HOWARD |
| Owner: MARONDA HOMES LLC |
|
Address 5220 SHAD ROAD #202 JACKSONVILLE, FL 32257 |
| Lot: 0060 |
| Contracted Stated Job Value: ¤120,000.00 |
| Job Description: SINGLE FAMILY DWELLING |
| Type: CN |
Contractor
MARONDA HOMES
| Status | Location Address | State License Number | Phone |
| INACTIVE |
4005 MARONDA WAY , |
CRC056762 (Exp: 08/31/2026) | 904-268-7730 |
Sub Contractors
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
RONALD KEVIN HAUPT
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4005 MARONDA WAY SANFORD, FL 32771 |
CAC058534 (Exp: 08/31/2026) | 407-321-0064 |
CLINTON J HULSLANDER SR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
4005 MARONDA WAY SANFORD, FL 32771 |
CFC1430632 (Exp: 08/31/2026) | 407-321-0064 | 407-688-8534 |
ANDREW SCOTT DIGAETANO JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
44 FORT CAROLINE PALM COAST, FL 32137 |
CCC1331606 (Exp: 08/31/2026) | 386-302-9063 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - STORMWATER FINAL | 06/04/2021 | APPROVED - AS NOTED | KRUTH |
| Note: THIS IS A REINSPECTION porta john is still on site couldnt do the stormwater inspection it has to be removed or on the drivewayand there is a board blocking the swale that needs to be removed READ NOTES | |||
| U -UTILITY RESIDENTIAL FINAL | 05/27/2021 | FINAL APPROVED | DHANEY |
| ROW - STORMWATER FINAL | 05/27/2021 | Disapproved -FEE REQUIRED | KRUTH |
| Note: porta john is still on site couldnt do the stormwater inspection it has to be removed or on the drivewayand there is a board blocking the swale that needs to be removed READ NOTES | |||
| BLD - BUILDING FINAL | 05/27/2021 | FINAL APPROVED | FWILLIS |
| FINAL SURVEY (OFFICE USE ONLY) | 05/26/2021 | APPROVED | KRUTH |
| ROW - FINAL APRON (AFTER POUR) | 05/26/2021 | APPROVED | KRUTH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 05/26/2021 | APPROVED | KRUTH |
| ELECTRIC - EARLY POWER | 05/10/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: THIS IS A REINSPECTION NEED TO SAFE OFF PEP TANK WIRE, ALSO ALL DOORS LOCKED NEED ACCESS TO HOME FOR INSPECTION 5/10/21 EMAILED FPL RELEASED POWER 11:20 | |||
| ELECTRIC - EARLY POWER | 05/07/2021 | Disapproved -FEE REQUIRED | RMARTIN |
| Note: NEED TO SAFE OFF PEP TANK WIRE, ALSO ALL DOORS LOCKED NEED ACCESS TO HOME FOR INSPECTION | |||
| ROW- PRE-APRON (PRE-POUR) | 04/21/2021 | APPROVED - AS NOTED | KRUTH |
| Note: THIS IS A REINSPECTION pipe is under water and a lot of dirt filled in the pipe needs to be pumped dry before an inspection At the time of inspection everything was good ready to pour | |||
| ROW- PRE-APRON (PRE-POUR) | 04/19/2021 | Disapproved -FEE REQUIRED | KRUTH |
| Note: pipe is under water and a lot of dirt filled in the pipe needs to be pumped dry before an inspection | |||
| U - SEWER TIE IN | 04/14/2021 | APPROVED | JGIBSON |
| LATH/BRICK/ WATER BARRIER | 04/06/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| LATH/BRICK/ WATER BARRIER | 04/05/2021 | CANCELLED BY APPLICANT | FWILLIS |
| INSULATION | 03/23/2021 | APPROVED | WMILLER |
| U-CROSS CONNECTION | 03/18/2021 | APPROVED - AS NOTED | DHANEY |
| Note: Approved No IRR. No Cross CN | |||
| PEP TANK INSTALLATION REQUEST | 03/17/2021 | APPROVED | CSTONE |
| ALL ROUGH | 03/15/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ALL ROUGH | 03/12/2021 | CANCELLED BY APPLICANT | FWILLIS |
| ROOF VALLEY & METAL | 03/11/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/02/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/01/2021 | CANCELLED BY APPLICANT | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 01/13/2021 | APPROVED | TBAKER |
| TIE BEAM / LINTEL | 01/12/2021 | APPROVED | FWILLIS |
| MONOLITHIC SLAB | 01/05/2021 | APPROVED | FWILLIS |
| PLUMBING 1ST ROUGH UNDERGROUND | 12/29/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 12/29/2020 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 11/12/2020 | APPROVED - AS NOTED | CSTONE |
| Note: already installed |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 01/12/2021 | 01/13/2021 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 01/12/2021 | 01/12/2021 |
| Note: Released By: TDOAK | |||
| BLD | COMPLETE | 12/18/2020 | 12/29/2020 |
| Note: Released By: FREODICA Revision - changed flooring type to ceramic & flipped washer/dyer. | |||
| ZON | COMPLETE | 10/08/2020 | 10/09/2020 |
| Note: Released By: ELENS | |||
| SWALE | COMPLETE | 10/02/2020 | 11/19/2020 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 10/01/2020 | 10/05/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 10/01/2020 | 10/07/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 10/01/2020 | 10/02/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 10/01/2020 | 10/05/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 10/01/2020 | 10/05/2020 |
| Note: Released By: CTROHA | |||
| UTL | COMPLETE | 10/01/2020 | 10/08/2020 |
| Note: Released By: LFITZGERALD | |||
| ZON | HOLD | 10/01/2020 | 10/05/2020 |
| Note: Held By: ELENS Please specify the type of Magnolia being proposed on the landscape plan. (Since this will be the required shade tree.) |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| STORMWATER REINSPECTION FEE | ¤40.00 | 06/09/2021 |
| REVISION | ¤40.00 | 05/19/2021 |
| REINSPECTION FEE | ¤40.00 | 05/19/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 05/19/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤490.00 | 10/12/2020 |
| SITE PLAN 20 | ¤20.00 | 10/12/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/12/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/12/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/12/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 10/12/2020 |
| SEWER CREDIT | (¤1,700.00) | 10/12/2020 |
| SEWER INSPECTION | ¤25.00 | 10/12/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 10/12/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 10/12/2020 |
| METER - DEPOSIT | ¤60.00 | 10/12/2020 |
| WATER- TURN ON | ¤25.00 | 10/12/2020 |
| ADMIN FEE | ¤20.00 | 10/12/2020 |
| CONNECTION FEES | ¤1,002.88 | 10/12/2020 |
| BUILDING DISCOUNT 100% | (¤1,229.00) | 10/12/2020 |
| ELECTRIC FEE | ¤207.00 | 10/12/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 10/12/2020 |
| IMPACT FEE FIRE | ¤223.38 | 10/12/2020 |
| IMPACT FEE PARKS | ¤849.24 | 10/12/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 10/12/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 10/12/2020 |
| MECHANICAL FEE | ¤207.00 | 10/12/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/12/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 10/12/2020 |
| PLAN CHECK FEE | ¤98.00 | 10/12/2020 |
| PLUMBING FEE | ¤207.00 | 10/12/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤13,936.35 |