Permit #2020100152
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7004-00220-0250 |
| Block: 00220 |
| Subdivision: 2203 - SECTION 4-COUNTRY CLUB COVE |
| Job Phone: 386-931-0764 |
| Location Address: 28 CORMORANT CT |
| Type: SW - SEAWALL |
| Issue Date: 10/12/2020 |
| NOC: RECORDED |
| Applicant name: KEVIN A PECK |
| Owner: VOGEL, THOMAS & LEEANN |
|
Address 111 OVERHILL RD WADING RIVER, NY 11792 |
| Lot: 0250 |
| Contracted Stated Job Value: ¤20,000.00 |
| Job Description: New Seawall Gray in Color |
| Type: CN |
Contractor
KEVIN A PECK, INC
| Status | Location Address | Phone |
| INACTIVE |
5845 WALNUT AVE BUNNELL, FL 32110 |
386-931-0764 |
Inspection History
| Type | Request Date | Result | Inspector |
| SEAWALL FINAL | 12/30/2020 | FINAL APPROVED | WMILLER |
| LDSC-LANDSCAPE/IRRIGATION FINAL | 12/29/2020 | APPROVED | JHARDING |
| Note: THIS IS A REINSPECTION NO SOD , Need sod 5' from wall . | |||
| LDSC-LANDSCAPE/IRRIGATION FINAL | 12/23/2020 | Disapproved - NO FEE | DHANEY |
| Note: NO SOD , Need sod 5' from wall . | |||
| ROW - FINAL INSPECTION | 12/07/2020 | APPROVED - AS NOTED | RGROSS |
| Note: LOT HAS BEEN CLEARED BY A HOME BUILDER. SILT FENCE HAS BEEN INSTALLED. ROW WILL BE INSPECTED AND SODDED TOWARD THE END OF CONSTRUCTION BY THE HOME BUILDER. | |||
| SEAWALL DEADMAN CAP | 11/06/2020 | APPROVED | TSTAUFFACHER |
| TURBIDITY BARRIER | 10/21/2020 | APPROVED | WMILLER |
| Note: THIS IS A REINSPECTION Turbidity Barrier needs to cover complete work area and ends needs to be closed Permit needs to be onsite, 105.7 Documents need to be on site 107.3,1. | |||
| TURBIDITY BARRIER | 10/14/2020 | Disapproved - NO FEE | WMILLER |
| Note: Turbidity Barrier needs to cover complete work area and ends needs to be closed Permit needs to be onsite, 105.7 Documents need to be on site 107.3,1. |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 10/06/2020 | 10/06/2020 |
| Note: Released By: TDOAK | |||
| ENGIN1 | COMPLETE | 10/05/2020 | 10/06/2020 |
| Note: Released By: TBAKER | |||
| SW1 | COMPLETE | 10/05/2020 | 10/05/2020 |
| Note: Released By: CTROHA | |||
| ZON | HOLD | 10/05/2020 | 10/05/2020 |
| Note: Held By: TDOAK On the site plan, please mark the location of the proposed seawall on the side of the property that is adjacent to the canal, not the roadway. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| ADMIN FEE | ¤20.00 | 10/12/2020 |
| BUILDING DISCOUNT 100% | (¤140.00) | 10/12/2020 |
| PLAN CHECK FEE | ¤40.00 | 10/12/2020 |
| REMODEL/ADDITION/ACCES INSPECT | ¤80.00 | 10/12/2020 |
| SITE PLAN 20 | ¤20.00 | 10/12/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/12/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/12/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/12/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤104.00 |