Permit #2020100541
Permit Details
Status: COED
| Parcel Id: 21-10-30-5410-00000-1740 |
| CONDITIONED SPACE: 2151 sqft |
| GARAGE: 436 sqft |
| OPENED PORCH (WITH ROOF) : 27 sqft |
| OPENED PORCH (WITH ROOF) : 157 sqft |
| Total Square Footage: 2771 sqft |
| Subdivision: 2135 - SAWMILL CREEK SUBDIVISION |
| Job Phone: 904-268-7730 |
| Location Address: 132 OAKLEAF WAY |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/23/2020 |
| NOC: RECORDED |
| Applicant name: SCOTT CHRISTIAN HOWARD |
| Owner: MARONDA HOMES, LLC |
|
Address 5220 SHAD ROAD JACKSONVILLE, FL 32257 |
|
Address STE 202 JACKSONVILLE, FL 32257 |
| Lot: 174 |
| Contracted Stated Job Value: ¤120,000.00 |
| Job Description: SINGLE FAMILY DWELLING |
| Type: CN |
Contractor
MARONDA HOMES
| Status | Location Address | State License Number | Phone |
| INACTIVE |
4005 MARONDA WAY , |
CRC056762 (Exp: 08/31/2026) | 904-268-7730 |
Sub Contractors
JOSEPH H STRADA JR
| Status | Location Address | State License Number | Phone |
| CANCEL |
3400 ST JOHNS PKWY SANFORD, FL 32771 |
EC13003715 (Exp: 08/31/2022) | 877-906-1113 |
MICHAEL LEE RAFFENSBERGER
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
7725 SANDSCOVE CT WINTER PARK, FL 32792 |
CAC1819723 (Exp: 08/31/2024) | 407-629-6920 | 407-629-9307 |
ANDREW SCOTT DIGAETANO JR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
44 FORT CAROLINE PALM COAST, FL 32137 |
CCC1331606 (Exp: 08/31/2026) | 386-302-9063 |
JEFFREY R OESCHGER
| Status | Location Address | State License Number |
| INACTIVE |
4237 HOLDEN ROAD LAKELAND, FL 33811 |
CFC1429768 (Exp: 08/31/2024) |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 04/30/2021 | FINAL APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Toilets not installed, multiple trades and people in dwelling. | |||
| BLD - BUILDING FINAL | 04/29/2021 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: Toilets not installed, multiple trades and people in dwelling. | |||
| U -UTILITY RESIDENTIAL FINAL | 04/29/2021 | FINAL APPROVED | DHANEY |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 04/08/2021 | APPROVED - AS NOTED | KRUTH |
| Note: THIS IS A REINSPECTION Water ponding in the rear center and the rear left side of the building. 4/8/21 Corrections made in ellevations of sod | |||
| ROW - STORMWATER FINAL | 04/08/2021 | APPROVED | KRUTH |
| ROW - FINAL APRON (AFTER POUR) | 04/08/2021 | APPROVED | KRUTH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/25/2021 | Disapproved - NO FEE | RGROSS |
| Note: Water ponding in the rear center and the rear left side of the building. Also there should have been a common swale along the left side property line. | |||
| FINAL SURVEY (OFFICE USE ONLY) | 03/25/2021 | APPROVED | RGROSS |
| U-CROSS CONNECTION | 03/17/2021 | APPROVED | DHANEY |
| ELECTRIC - EARLY POWER | 03/15/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEAAED POWER 10:10 | |||
| ROW - FINAL APRON (AFTER POUR) | 02/26/2021 | Disapproved -FEE REQUIRED | KRUTH |
| Note: no final survey submitted final survey after pour stormwater final | |||
| ROW- PRE-APRON (PRE-POUR) | 02/24/2021 | APPROVED - AS NOTED | KRUTH |
| Note: It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist READY TO POUR upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete. | |||
| INSULATION | 02/10/2021 | APPROVED | FWILLIS |
| LATH/BRICK/ WATER BARRIER | 02/09/2021 | APPROVED | FWILLIS |
| ALL ROUGH | 02/08/2021 | APPROVED | FWILLIS |
| ROOF VALLEY & METAL | 01/28/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 01/21/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 01/20/2021 | CANCELLED BY APPLICANT | FWILLIS |
| TIE BEAM / LINTEL | 12/22/2020 | CANCELLED BY APPLICANT | WEB |
| TIE BEAM / LINTEL | 12/22/2020 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Dowel not Drilled & Epoxied in rear, marked in orange on wall. Window Sill Bed Joint Exceeds FBC R606.3.1 (3/8" to 1/2) 12/22/20 - Items corrected. | |||
| TIE BEAM / LINTEL | 12/21/2020 | Disapproved - NO FEE | FWILLIS |
| Note: Dowel not Drilled & Epoxied in rear, marked in orange on wall. Window Sill Bed Joint Exceeds FBC R606.3.1 (3/8" to 1/2) | |||
| TIE BEAM / LINTEL | 12/21/2020 | CANCELLED BY APPLICANT | WEB |
| FOUND SURVEY APPROVED (OFFICE) | 12/21/2020 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 12/08/2020 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION MISSING UFER GROUND .NEC..250.52(3) | |||
| MONOLITHIC SLAB | 12/07/2020 | Disapproved - NO FEE | FWILLIS |
| Note: MISSING UFER GROUND .NEC..250.52(3) | |||
| GRAVITY SEWER TEST | 12/01/2020 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION NOT RAN YET | |||
| U - SEWER TIE IN | 12/01/2020 | APPROVED | JGIBSON |
| Note: THIS IS A REINSPECTION NOT RAN YET | |||
| U - SEWER TIE IN | 11/24/2020 | Disapproved - NO FEE | JGIBSON |
| Note: NOT RAN YET | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 11/24/2020 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 11/24/2020 | Disapproved - NO FEE | JGIBSON |
| Note: NOT RAN YET | |||
| WATER METER INSTALLATION REQUEST | 11/09/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 12/18/2020 | 12/21/2020 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 12/18/2020 | 12/18/2020 |
| Note: Released By: AMOBLEY | |||
| PLUM | COMPLETE | 12/03/2020 | 12/08/2020 |
| Note: Released By: FREODICA Correction to revision - changed plumbing riser. | |||
| BADMIN | HOLD | 12/03/2020 | 12/03/2020 |
| Note: Held By: STHOMAS MUST ANSWER 'PLUM' HOLD BEFORE SUBMITTING REVISIONS FOR SIDEWALK | |||
| BADMIN | COMPLETE | 12/03/2020 | 12/03/2020 |
| Note: Released By: JMONTARULI | |||
| PLUM | HOLD | 11/04/2020 | 11/12/2020 |
| Note: Held By: FREODICA Revision : changed sanitary riser diagram and plumber. Provide complete drain pipe sizes on sanitary riser diagram including dated signature of plumbing contractor per FBCR 6th Ed. Sec. P3005.4/FBC Sec. 107.2.1. FReodica -386-986-4734. | |||
| URB | COMPLETE | 10/14/2020 | 10/20/2020 |
| Note: Released By: JBEAUDET | |||
| BLD | COMPLETE | 10/13/2020 | 10/15/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 10/13/2020 | 10/14/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 10/13/2020 | 10/14/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 10/13/2020 | 10/13/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 10/13/2020 | 10/19/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 10/13/2020 | 10/14/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 10/13/2020 | 10/15/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 10/13/2020 | 10/21/2020 |
| Note: Released By: CTROHA | |||
| ZON | COMPLETE | 10/13/2020 | 10/14/2020 |
| Note: Released By: AMOBLEY |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 04/30/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 04/28/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 04/28/2021 |
| REVISION | ¤40.00 | 04/28/2021 |
| SITE PLAN 20 | ¤20.00 | 10/23/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/23/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/23/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/23/2020 |
| METER - DEPOSIT | ¤60.00 | 10/23/2020 |
| WATER-METER | ¤434.59 | 10/23/2020 |
| WATER-METER | ¤361.04 | 10/23/2020 |
| ADMIN FEE | ¤20.00 | 10/23/2020 |
| CONNECTION FEES | ¤25.00 | 10/23/2020 |
| BUILDING DISCOUNT 100% | (¤1,308.80) | 10/23/2020 |
| ELECTRIC FEE | ¤218.40 | 10/23/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 10/23/2020 |
| IMPACT FEE FIRE | ¤223.38 | 10/23/2020 |
| IMPACT FEE PARKS | ¤849.24 | 10/23/2020 |
| IMPACT FEE TRANSPORTATION | ¤3,059.00 | 10/23/2020 |
| MECHANICAL FEE | ¤218.40 | 10/23/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/23/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 10/23/2020 |
| PLAN CHECK FEE | ¤105.60 | 10/23/2020 |
| PLUMBING FEE | ¤218.40 | 10/23/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤91.77) | 10/23/2020 |
| SEWER INSPECTION | ¤25.00 | 10/23/2020 |
| SEWER CAPITAL FACILITY | ¤2,389.36 | 10/23/2020 |
| WATER CAPITAL FACILITY FEE | ¤2,234.43 | 10/23/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤528.00 | 10/23/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤9,826.09 |