I want to search for...
Permit #2020100843
Permit Details
Status: COED
| Parcel Id: 07-11-31-7030-00140-0080 |
| CONDITIONED SPACE: 1502 sqft |
| GARAGE: 436 sqft |
| OPENED PORCH (WITH ROOF) : 234 sqft |
| OPENED PORCH (WITH ROOF) : 70 sqft |
| Total Square Footage: 2242 sqft |
| Block: 00140 |
| Subdivision: 2154 - SECTION 30-ROYAL PALMS |
| Job Phone: 386-447-4151 |
| Location Address: 4 RAINROCK PL |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 10/29/2020 |
| NOC: RECORDED |
| Applicant name: GENE WARREN SLONE |
| Owner: SMUK, SAMUEL |
|
Address 411 KELSEY PARK DR PALM BEACH GARDENS, FL 33410 |
| Lot: 0080 |
| Contracted Stated Job Value: ¤220,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
FLORIDA GREEN CONSTRUCTION INC.
| Status | Location Address | State License Number | Phone |
| INACTIVE |
870 E RETTA STREET DELEON SPRINGS, FL 32130 |
CBC1260957 (Exp: 08/31/2026) | 407-580-2657 |
Sub Contractors
ERIC FRANCO
| Status | Location Address | State License Number | Phone |
| CANCEL |
840 DELTONA BLVD SUITE F-2 SANFORD, FL 32771 |
CCC1327280 (Exp: 08/31/2022) | 386-575-4007 |
JOHN EDWARD GAMBONE
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
GREGG A MCANALLY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE PALM COAST, FL 32092 |
CAC1815760 (Exp: 08/31/2022) | 904-829-8898 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 11/15/2021 | FINAL APPROVED | JWALKER |
| U-CROSS CONNECTION | 10/13/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: has potable irrigation with PVB installed-no cross connection | |||
| U -UTILITY RESIDENTIAL FINAL | 10/13/2021 | FINAL APPROVED | LFITZGERALD |
| ELECTRIC - EARLY POWER | 10/01/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 9:20 | |||
| ROW - STORMWATER FINAL | 09/15/2021 | APPROVED | RGROSS |
| Note: 9/14/2021=REMOVE THE POTTY FROM THE SWALE OR FROM THE ROAD AND PLACE IT ON THE DRIVEWAY REPAIR THE SWALE WHERE THE POTTY WAS, WITH SOD, BLEND WITH THE SURROUNDING GRADE | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 09/14/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| ROW - FINAL APRON (AFTER POUR) | 09/14/2021 | APPROVED | GBERTOLA |
| Note: CULVERT ELEVATION IS GOOD | |||
| FINAL SURVEY (OFFICE USE ONLY) | 09/14/2021 | APPROVED | GBERTOLA |
| ROW- PRE-APRON (PRE-POUR) | 07/09/2021 | APPROVED | RGROSS |
| Note: READY TO POUR at the time of the inspection. Heavy rain in the forecast. Builder should double check elevation before pouring. | |||
| U - SEWER TIE IN | 06/15/2021 | APPROVED | JGIBSON |
| GRAVITY SEWER TEST | 06/15/2021 | APPROVED | JGIBSON |
| PEP TANK INSTALLATION REQUEST | 05/25/2021 | APPROVED | CSTONE |
| LATH/BRICK/ WATER BARRIER | 05/19/2021 | APPROVED | MMESSER |
| INSULATION | 05/04/2021 | APPROVED | MMESSER |
| ALL ROUGH | 04/28/2021 | APPROVED - AS NOTED | MMESSER |
| Note: Seal dryer vent duct at box. | |||
| ROOF VALLEY & METAL | 03/01/2021 | APPROVED | MMESSER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 02/17/2021 | APPROVED | MMESSER |
| TIE BEAM / LINTEL | 01/26/2021 | APPROVED | MMESSER |
| FOUND SURVEY APPROVED (OFFICE) | 01/20/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 01/14/2021 | APPROVED | MMESSER |
| PLUMBING 1ST ROUGH UNDERGROUND | 01/11/2021 | APPROVED | JGIBSON |
| ELECTRIC TEMP POLE | 11/25/2020 | APPROVED | TSTAUFFACHER |
| WATER METER INSTALLATION REQUEST | 11/12/2020 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 01/19/2021 | 01/20/2021 |
| Note: Released By: TBAKER | |||
| ZON | COMPLETE | 01/19/2021 | 01/19/2021 |
| Note: Released By: AMOBLEY | |||
| SWALE | COMPLETE | 10/20/2020 | 01/07/2021 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 10/19/2020 | 10/24/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 10/19/2020 | 10/20/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 10/19/2020 | 10/20/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 10/19/2020 | 10/20/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 10/19/2020 | 10/23/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 10/19/2020 | 10/20/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 10/19/2020 | 10/24/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 10/19/2020 | 10/23/2020 |
| Note: Released By: CTROHA | |||
| ZON | COMPLETE | 10/19/2020 | 10/21/2020 |
| Note: Released By: ELENS |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 01/06/2022 |
| STORM WATER PERMIT FEES | ¤80.00 | 10/29/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 10/29/2020 |
| SEWER CREDIT | (¤1,147.00) | 10/29/2020 |
| SEWER INSPECTION | ¤25.00 | 10/29/2020 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 10/29/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 10/29/2020 |
| METER - DEPOSIT | ¤60.00 | 10/29/2020 |
| METER - DEPOSIT | ¤60.00 | 10/29/2020 |
| WATER-METER | ¤434.59 | 10/29/2020 |
| WATER- TURN ON | ¤25.00 | 10/29/2020 |
| WATER- TURN ON | ¤25.00 | 10/29/2020 |
| ADMIN FEE | ¤20.00 | 10/29/2020 |
| CONNECTION FEES | ¤1,002.88 | 10/29/2020 |
| BUILDING DISCOUNT 100% | (¤1,124.00) | 10/29/2020 |
| ELECTRIC FEE | ¤192.00 | 10/29/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤6.70) | 10/29/2020 |
| IMPACT FEE FIRE | ¤223.38 | 10/29/2020 |
| IMPACT FEE PARKS | ¤849.24 | 10/29/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 10/29/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 10/29/2020 |
| MECHANICAL FEE | ¤192.00 | 10/29/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/29/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 10/29/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤25.48) | 10/29/2020 |
| PLAN CHECK FEE | ¤88.00 | 10/29/2020 |
| PLUMBING FEE | ¤192.00 | 10/29/2020 |
| NEW RESIDENTIAL INSPECTIONS | ¤440.00 | 10/29/2020 |
| SITE PLAN 20 | ¤20.00 | 10/29/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 10/29/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 10/29/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤14,893.94 |