I want to search for...
Permit #2020101251
Permit Details
Status: INSPECT
| Parcel Id: 27-10-30-0000-01010-0090 |
| Block: 01010 |
| Subdivision: - |
| Job Phone: (386)931-7331 |
| Location Address: 100 ARIELLA PL |
| Type: CSD - COMMERCIAL SITE DEVELOPMENT |
| Issue Date: 04/06/2022 |
| NOC: Unknown |
| Applicant name: SCOTT DALE SOWERS |
| Owner: MATANZAS WEST ACQUISITION LLC |
|
Address 645 MAYPORT ROAD ATLANTIC BEACH, FL 32233 |
| Lot: 0090 |
| Job Description: SITE WORK - MATANZAS WEST 285 UNIT APARTMENTS |
| Type: CN |
Contractor
S E CLINE CONSTRUCTION, INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 354425 PALM COAST, FL 32137 |
CGC061947 (Exp: 08/31/2028) | (386)446-6426 | (386)446-6481 |
Inspection History
| Type | Request Date | Result | Inspector |
| UC - PROJECT STATUS | 02/07/2024 | APPROVED | JHARDING |
| Note: inspecion called to keep project active. | |||
| ROW- PROJECT STATUS | 03/09/2023 | APPROVED - AS NOTED | DHANEY |
| Note: Pre-Con has been completed . Construction has not started yet . | |||
| ROW - EROSION CONTROL / INLET PROTE/SILT FENCE | |||
| UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) | |||
| UROW-RETENT/DETENT STABILI | |||
| UROW -FINAL GRADE PRIOR SOD | |||
| UROW- CURBING & GUTTER | |||
| UROW - FINAL DRAINAGE | |||
| ROW - FINAL INSPECTION | |||
| UC-TRAF - MAINT OF TRAFFIC | |||
| UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) | |||
| UC-CONSTRUCTION ENTRANCE | |||
| UC-MOT MAINTENANCE OF TRAFFIC | |||
| UC-ASPHALT PRE PLACEMENT | |||
| UC-DRAINAGE STRUCT PLACMNT | |||
| UC-DRAINAGE PIPE PLACEMENT/LAMPING | |||
| U-WATER METER INSTALLATION/VERIFICATION | |||
| PROJECT CLOSE OUT MEETING (386-986-3750) | |||
| UC-SUBSTANTIAL WALK-THRU | |||
| UC- PRELIMINARY AS-BUILTS | |||
| UC-FINAL SITE INSPECTION | |||
| U - UTILITY COMMERCIAL FINAL | |||
| FORM BOARD | |||
| BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS | |||
| BLD- ADA PARKING | |||
| BLD - ADA COMPLIANT | |||
| BLD- ADA SIGNAGECONTROL | |||
| BLD- ADA VEHICULAR WAY | |||
| BLD - ADA SIGNAGE- INFOR/DIRECT | |||
| BLD - UNDERGROUND SITE LIGHTING CONDUITS | |||
| BLD - SITE LIGHTING-PLACEMENT/FOUNDATION | |||
| BLD - SITE LIGHTING-POLE SET/FIXTURE | |||
| BLD - SITE LIGHTING-CONDUCTORS/CONNECTORS | |||
| MAINT BOND ACCEPTANCE (OFFICE) | |||
| BLD - SEWER TIE IN | |||
| CLOSE OUT DOCUMENTS | |||
| PLAN - PRE-CON 386-986-3750 | |||
| PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY | |||
| LANDSCAPE PRE-CONSTRUCTION MEETING | |||
| LDSC-PRE-CLEARING | |||
| LDSC-TREE BARRICADE | |||
| LDSC-PRE-PLANTING TREE QUALITY | |||
| LDSC-IRRIGATION FINAL | |||
| LDSC-SITE LIGHT STAKE LOCATE | |||
| LDSC- SUBSTANTIAL COMPLETE (OFFICE USE) | |||
| LDSC- LANDSCAPE / IRRIGATION AS-BUILT | |||
| LDSC- LANDSCAPE FINAL | |||
| U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR | |||
| U-SEWER FORCE MAIN INSTALL/TESTING | |||
| U-WATER SERVICE INSTALLATION | |||
| U-GRAVITY SEWER INSTALL/TESTING | |||
| U-REUSE MAIN INSTALL/TESTING | |||
| U-WATER MAIN DISINFECTION | |||
| U-WATER MAIN DISINFECTION SAMPLING | |||
| U-PUMP STATION PRE-INSTALLATION | |||
| U-PUMP STATION START-UP |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 10/28/2020 | 10/28/2020 |
| Note: Released By: PBUCKLEY | |||
| ELEC | COMPLETE | 10/28/2020 | 10/28/2020 |
| Note: Released By: JMUNSON | |||
| PLENG | COMPLETE | 10/28/2020 | 10/28/2020 |
| Note: Released By: DLEAP | |||
| PLLA | COMPLETE | 10/28/2020 | 10/28/2020 |
| Note: Released By: DRAMIREZ | |||
| UD1 | COMPLETE | 10/28/2020 | 10/30/2020 |
| Note: Released By: CJOHNSON |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| BUILDING DISCOUNT 100% | (¤125.00) | 04/06/2022 |
| INSPECTION 40 | ¤1,600.00 | 04/06/2022 |
| PERMIT FEE | ¤125.00 | 04/06/2022 |
| SITE PLAN 20 | ¤20.00 | 04/06/2022 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤1,620.00 |