I want to search for...

Permit #2020110521

Permit Details

Status: COED

Parcel Id: 07-11-31-7059-00340-0240
CONDITIONED SPACE: 1817 sqft
GARAGE: 433 sqft
OPENED PORCH (WITH ROOF) : 186 sqft
OPENED PORCH (WITH ROOF) : 38 sqft
Total Square Footage: 2474 sqft
Block: 00340
Subdivision: -
Job Phone: (386)437-1508
Location Address: 30 SEA FRONT TR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 12/14/2020
NOC: RECORDED
Applicant name: TAMMI SUE MARQUIS
Owner: HANSEN MICHAEL & KANDACE H&W

Address

29 CLOVERDALE COURT N

PALM COAST, FL 32137

Lot: 0240
Contracted Stated Job Value: ¤180,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

GULFSTREAM HOMES & CONSTRUCTION, LLC
Status Location Address State License Number Phone Fax
INACTIVE

PO BOX 1092

BUNNELL, FL 32110

CRC1326418 (Exp: 08/31/2026) (386)437-1508 386-437-9769

Sub Contractors

JAMES CRAIG FISHER
Status Location Address State License Number Phone
ACTIVE

PO BOX 451

BUNNELL, FL 32110

CAC1819807 (Exp: 08/31/2026) 386-222-9549
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
ARTHUR J PASCOE
Status Location Address State License Number Phone
ACTIVE

PO BOX 730007

ORMOND BEACH, FL 32174

EC13007168 (Exp: 08/31/2026) 386-547-6439
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 10/06/2021 FINAL APPROVED JHARDING
BLD - BUILDING FINAL 10/04/2021 FINAL APPROVED TSTAUFFACHER
ROW - FINAL APRON (AFTER POUR) 10/01/2021 APPROVED - AS NOTED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD
ROW FIELD SURVEY /GRADING CERTIFICATION 10/01/2021 APPROVED - AS NOTED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD
ROW - STORMWATER FINAL 10/01/2021 APPROVED - AS NOTED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD
FINAL SURVEY (OFFICE USE ONLY) 10/01/2021 APPROVED GBERTOLA
ROW- PRE-APRON (PRE-POUR) 08/04/2021 APPROVED - AS NOTED GBERTOLA
Note: THIS IS A REINSPECTION AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING.
ROW- PRE-APRON (PRE-POUR) 08/03/2021 CANCELLED BY APPLICANT RGROSS
ELECTRIC - EARLY POWER 07/14/2021 APPROVED - AS NOTED JMUNSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION House needs to be unlocked 7/13/21 Water heater wire needs to be safed off in box 7/14/21 Emailed FPL at 8:29 am
ELECTRIC - EARLY POWER 07/13/2021 Disapproved - NO FEE JMUNSON
Note: THIS IS A REINSPECTION House needs to be unlocked 7/13/21 Water heater wire needs to be safed off in box
ELECTRIC - EARLY POWER 07/12/2021 Disapproved -FEE REQUIRED JMUNSON
Note: House needs to be unlocked
GRAVITY SEWER TEST 06/23/2021 APPROVED - AS NOTED JGIBSON
Note: LAST TIME I WILL SCHEDULE GRAVITY SEWER INSPECTION, BOTH GRAVITY SEWER AND U-SEWER CONNECTION NEED TO BE SCHEDULED AT TIME OF COMPLETION. WHEN C/O COMES UP YOU WILL HAVE A PROBLEM WITH OUTSTANDING INSPECTIO!!!!!!
U-CROSS CONNECTION 06/23/2021 APPROVED - AS NOTED JHARDING
Note: No irrigation, no cross connections.
U - SEWER TIE IN 06/23/2021 APPROVED - AS NOTED JGIBSON
Note: SEE COMENTS FROM GRAVITY SEWER TEST
INSULATION 05/14/2021 APPROVED TSTAUFFACHER
PEP TANK INSTALLATION REQUEST 05/11/2021 APPROVED CSTONE
ALL ROUGH 05/07/2021 APPROVED - AS NOTED TSTAUFFACHER
Note: Add fire block at kitchen exhaust vent. Will check at insulation.
LATH/BRICK/ WATER BARRIER 04/30/2021 APPROVED JWALKER
ROOF VALLEY & METAL 04/19/2021 APPROVED TSTAUFFACHER
ROOF VALLEY & METAL 04/16/2021 CANCELLED BY APPLICANT WEB
ROOF SHEATHING / BRACES/TIES/DOWN CELL 04/08/2021 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION No truss engineering onsite Tie downs at bearing wall/girder attachment do not match plan description. Highlighted on large set of plans Roof decking and down cells okay
ROOF SHEATHING / BRACES/TIES/DOWN CELL 04/05/2021 Disapproved - NO FEE TSTAUFFACHER
Note: No truss engineering onsite Tie downs at bearing wall/girder attachment do not match plan description. Highlighted on large set of plans Roof decking and down cells okay
FOUND SURVEY APPROVED (OFFICE) 03/01/2021 APPROVED TBAKER
TIE BEAM / LINTEL 02/16/2021 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION received call at 9:22 AM
TIE BEAM / LINTEL 02/12/2021 CANCELLED BY APPLICANT TSTAUFFACHER
Note: received call at 9:22 AM
MONOLITHIC SLAB 02/04/2021 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION Front entry culumns do not meet plan specifications. Noted on page A1 of plans with highlighter.
MONOLITHIC SLAB 02/03/2021 Disapproved - NO FEE TSTAUFFACHER
Note: Front entry culumns do not meet plan specifications. Noted on page A1 of plans with highlighter.
PLUMBING 1ST ROUGH UNDERGROUND 01/19/2021 APPROVED JGIBSON
WATER METER INSTALLATION REQUEST 12/30/2020 APPROVED TCHURCHILL

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 02/25/2021 03/01/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US
ZON COMPLETE 02/25/2021 02/25/2021
Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM
ELEC COMPLETE 12/08/2020 12/08/2020
Note: Released By: JMUNSON
CUSVC COMPLETE 12/08/2020 12/09/2020
Note: Released By: HHAND
BLD COMPLETE 12/08/2020 12/11/2020
Note: Released By: JPI
BLD HOLD 11/12/2020 11/22/2020
Note: Held By: JPI 1. Sheet A1, Concrete to be 2500 psi and page A3 shows 3000 psi concrete. Reconcile, revise, and cloud drawings 2. Need CO detector between bedrooms 2 and 3 3. Mullions not on Product Approval list 4. Underlayment not on Product Approval list 5. Sliding glass door not on Product Approval list 6. No off ridge vent shown on Product Approval list
CUSVC HOLD 11/12/2020 11/13/2020
Note: Held By: HHAND Please correct the utility application to reflect the proper parcel number
ELEC HOLD 11/12/2020 11/13/2020
Note: Held By: JMUNSON Electrical load calculations do not match the square footage of the home.
ENGIN1 COMPLETE 11/12/2020 11/12/2020
Note: Released By: TBAKER
LOCATE COMPLETE 11/12/2020 11/16/2020
Note: Released By: CSTONE
MECH COMPLETE 11/12/2020 11/13/2020
Note: Released By: CPISCITELLI
PLUM COMPLETE 11/12/2020 11/22/2020
Note: Released By: JPI
SW1 COMPLETE 11/12/2020 11/17/2020
Note: Released By: KRUTH
ZON COMPLETE 11/12/2020 11/16/2020
Note: Released By: AMOBLEY
SWALE COMPLETE 11/12/2020 02/22/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 10/04/2021
SW ENG - FIELD SURVEY INSPECT ¤20.00 10/04/2021
STORM WATER PERMIT FEES ¤80.00 12/14/2020
3% TRANS IMPACT FEE CREDIT (¤50.22) 12/14/2020
SEWER CREDIT (¤849.40) 12/14/2020
SEWER INSPECTION ¤25.00 12/14/2020
SEWER CAPITAL FACILITY ¤4,664.55 12/14/2020
WATER CAPITAL FACILITY FEE ¤3,424.45 12/14/2020
NEW RESIDENTIAL INSPECTIONS ¤458.00 12/14/2020
SITE PLAN 20 ¤20.00 12/14/2020
SURCHARGE FS 533.721 ¤2.00 12/14/2020
SURCHARGE - FS 468.631 ¤2.00 12/14/2020
METER - DEPOSIT ¤60.00 12/14/2020
WATER- TURN ON ¤25.00 12/14/2020
ADMIN FEE ¤20.00 12/14/2020
CONNECTION FEES ¤1,017.83 12/14/2020
BUILDING DISCOUNT 100% (¤1,161.80) 12/14/2020
ELECTRIC FEE ¤197.40 12/14/2020
3% FIRE IMPACT FEE CREDIT (¤11.01) 12/14/2020
IMPACT FEE FIRE ¤367.00 12/14/2020
IMPACT FEE PARKS ¤1,199.12 12/14/2020
IMPACT FEE SCHOOL ¤3,600.00 12/14/2020
IMPACT FEE TRANSPORTATION ¤1,674.00 12/14/2020
MECHANICAL FEE ¤197.40 12/14/2020
WATER -IRRIGATION INSPECTION ¤25.00 12/14/2020
3% PARKS IMPACT FEE CREDIT (¤35.97) 12/14/2020
PLAN CHECK FEE ¤91.60 12/14/2020
PLUMBING FEE ¤197.40 12/14/2020
Fees Total Due: ¤0.00 Total Paid: ¤15,299.35