I want to search for...
Permit #2020110525
Permit Details
Status: COED
| Parcel Id: 07-11-31-7037-00100-0090 |
| CONDITIONED SPACE: 1853 sqft |
| GARAGE: 446 sqft |
| OPENED PORCH (WITH ROOF) : 142 sqft |
| OPENED PORCH (WITH ROOF) : 80 sqft |
| Total Square Footage: 2521 sqft |
| Block: 00100 |
| Subdivision: 2176 - SECTION 37-LAKEVIEW |
| Job Phone: 386-931-5395 |
| Location Address: 78 LUTHER DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 01/29/2021 |
| NOC: RECORDED |
| Applicant name: RYAN JAMES PERRY |
| Owner: WATERSIDE HOMES RENOVATIONS & DESIGNS INC |
|
Address 10 BISCAYNE DRIVE PALM COAST, FL 32137 |
| Lot: 0090 |
| Contracted Stated Job Value: ¤170,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
WATERSIDE HOMES RENOVATIONS AND DESIGNS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
10 BISCAYNE DRIVE PALM COAST, FL 32137 |
CBC1263021 (Exp: 08/31/2026) | 386-931-5395 |
Sub Contractors
PETER JOSEPH LYDEN
| Status | Location Address | State License Number | Phone |
| CANCEL |
17 UNIMAY CT BUNNELL, FL 32110 |
EC0002436 (Exp: 08/31/2022) | 386-931-2568 |
RYAN JAMES PERRY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
10 BISCAYNE DRIVE PALM COAST, FL 32137 |
CBC1263021 (Exp: 08/31/2026) | 386-931-5395 |
JOHN ROBERT BLEVINS JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
17 PORWYN LANE PALM COAST, FL 32164 |
CAC1816125 (Exp: 08/31/2026) | 386-585-8283 | 386-263-2096 |
DENNIS GENE GAINEY
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
P.O. BOX 1203 Bunnell, FL 32110 |
CFC046004 (Exp: 08/31/2026) | (386) 437-5637 | 386-437-3012 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 09/22/2021 | FINAL APPROVED | DHANEY |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION [Pep Panel completed,9/22- approved. ] | |||
| U-CROSS CONNECTION | 09/21/2021 | APPROVED | DHANEY |
| U -UTILITY RESIDENTIAL FINAL | 09/21/2021 | CANCELLED BY APPLICANT | DHANEY |
| Note: THIS IS A REINSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL | 09/20/2021 | CANCELLED BY APPLICANT | DHANEY |
| BLD - BUILDING FINAL | 09/20/2021 | FINAL APPROVED | DCUSHING |
| FINAL SURVEY (OFFICE USE ONLY) | 09/15/2021 | APPROVED | KRUTH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 09/15/2021 | APPROVED | KRUTH |
| ROW - STORMWATER FINAL | 09/15/2021 | APPROVED | KRUTH |
| ROW - FINAL APRON (AFTER POUR) | 09/15/2021 | APPROVED | KRUTH |
| ELECTRIC - EARLY POWER | 09/08/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 10:10 | |||
| ROW- PRE-APRON (PRE-POUR) | 07/13/2021 | APPROVED | RGROSS |
| Note: READY TO POUR | |||
| U - SEWER TIE IN | 06/29/2021 | APPROVED | FWILLIS |
| GRAVITY SEWER TEST | 06/29/2021 | APPROVED | FWILLIS |
| LATH/BRICK/ WATER BARRIER | 05/24/2021 | APPROVED | FWILLIS |
| INSULATION | 05/14/2021 | APPROVED | TSTAUFFACHER |
| Note: Windows and doors have been installed THIS IS A REINSPECTION • At time of insulation inspection, window and door rough openings shall be covered by wood structural panels applied over the water resistive barrier and sufficiently fastened and sealed to prevent any water entry into the building AND in between exterior cladding materials and the wall surface. • If the inspector determines the panel attachment is inadequate, the insulation inspection will be failed with a correction to properly fasten, secure and seal the wood panel(s) and a re-inspection fee charged. • Upon approval of the insulation inspection where windows or doors are missing, the inspector will create a window/door inspection. The window/door inspection will automatically be assigned an inspection priority code that will prevent scheduling of a building final inspection until the window / door inspection is approved. | |||
| PEP TANK INSTALLATION REQUEST | 05/06/2021 | APPROVED - AS NOTED | CSTONE |
| Note: dumpster will need to move | |||
| INSULATION | 05/05/2021 | Disapproved - NO FEE | FWILLIS |
| Note: • At time of insulation inspection, window and door rough openings shall be covered by wood structural panels applied over the water resistive barrier and sufficiently fastened and sealed to prevent any water entry into the building AND in between exterior cladding materials and the wall surface. • If the inspector determines the panel attachment is inadequate, the insulation inspection will be failed with a correction to properly fasten, secure and seal the wood panel(s) and a re-inspection fee charged. • Upon approval of the insulation inspection where windows or doors are missing, the inspector will create a window/door inspection. The window/door inspection will automatically be assigned an inspection priority code that will prevent scheduling of a building final inspection until the window / door inspection is approved. | |||
| ALL ROUGH | 04/30/2021 | APPROVED - AS NOTED | FWILLIS |
| Note: Windows and Doors Backordered. Will Check on Insulation. | |||
| ROOF VALLEY & METAL | 04/21/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 04/06/2021 | APPROVED | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 04/05/2021 | APPROVED | TBAKER |
| ELECTRIC-TUG | 03/19/2021 | APPROVED - AS NOTED | RMARTIN |
| Note: EMAILED FPL RELEASED POWER 10:20 | |||
| TIE BEAM / LINTEL | 03/12/2021 | APPROVED | FWILLIS |
| MONOLITHIC SLAB | 03/02/2021 | APPROVED | FWILLIS |
| PLUMBING 1ST ROUGH UNDERGROUND | 02/24/2021 | APPROVED - AS NOTED | JGIBSON |
| Note: NEED TO LIST CORRECT PLUMBING CONTRACTOR FROM HYDROTECH TO ADVANCE | |||
| WATER METER INSTALLATION REQUEST | 02/24/2021 | APPROVED | TCHURCHILL |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 04/05/2021 | 04/05/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US | |||
| ZON | COMPLETE | 04/05/2021 | 04/05/2021 |
| Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/08/2021 | 03/15/2021 |
| Note: Released By: FRED REODICA - (386)986-4734 - FReodica@ci.palm-coast.fl.us Revision - lintel substitution from cast-crete to power box by architect. | |||
| CUSVC | COMPLETE | 02/17/2021 | 02/17/2021 |
| Note: Released By: HHAND BUILDER MUST PAY THE DIFFERENCE BETWEEN THE OLD RATES & THE NEW RATES. | |||
| BADMIN | COMPLETE | 02/03/2021 | 02/03/2021 |
| Note: Released By: STHOMAS | |||
| BADMIN | HOLD | 02/02/2021 | 02/02/2021 |
| Note: Held By: STHOMAS NOC AT BOTTOM CAN NOT HAVE NAME OF COMPANY. MUST BE SIGNATURE/NAME OF PERSON. | |||
| SWALE | COMPLETE | 11/24/2020 | 02/18/2021 |
| Note: Released By: TBAKER | |||
| BLD | COMPLETE | 11/24/2020 | 12/01/2020 |
| Note: Released By: JPI | |||
| BLD | HOLD | 11/12/2020 | 11/22/2020 |
| Note: Held By: JPI 1. Since project is to use icynene insulation, there needs to be a detail of the hatch between occupied and unoccupied areas in the attic. 2. Sheet GN, soil bearing capacity assumed to be 2500 and 3000 psf. Please cure. 3. Mullions not on Product Approval list 4. Underlayment not on Product Approval list 5. Sliding glass door not on Product Approval list | |||
| CUSVC | COMPLETE | 11/12/2020 | 11/16/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 11/12/2020 | 11/13/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 11/12/2020 | 11/12/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 11/12/2020 | 11/16/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 11/12/2020 | 11/13/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 11/12/2020 | 11/22/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 11/12/2020 | 11/17/2020 |
| Note: Released By: KRUTH | |||
| ZON | COMPLETE | 11/12/2020 | 11/16/2020 |
| Note: Released By: AMOBLEY |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| CONNECTION FEES | ¤14.95 | 09/22/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 09/22/2021 |
| REVISION | ¤40.00 | 09/22/2021 |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 09/22/2021 |
| SEWER CAPITAL FACILITY | ¤68.48 | 09/22/2021 |
| WATER CAPITAL FACILITY FEE | ¤50.27 | 09/22/2021 |
| SEWER CAPITAL FACILITY | ¤4,596.07 | 01/29/2021 |
| WATER CAPITAL FACILITY FEE | ¤3,374.18 | 01/29/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 01/29/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 01/29/2021 |
| SEWER CREDIT | (¤850.00) | 01/29/2021 |
| SEWER INSPECTION | ¤25.00 | 01/29/2021 |
| SITE PLAN 20 | ¤20.00 | 01/29/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 01/29/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 01/29/2021 |
| METER - DEPOSIT | ¤60.00 | 01/29/2021 |
| WATER- TURN ON | ¤25.00 | 01/29/2021 |
| ADMIN FEE | ¤20.00 | 01/29/2021 |
| CONNECTION FEES | ¤1,002.88 | 01/29/2021 |
| BUILDING DISCOUNT 100% | (¤1,178.60) | 01/29/2021 |
| ELECTRIC FEE | ¤199.80 | 01/29/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 01/29/2021 |
| IMPACT FEE FIRE | ¤367.00 | 01/29/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 01/29/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 01/29/2021 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 01/29/2021 |
| MECHANICAL FEE | ¤199.80 | 01/29/2021 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 01/29/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 01/29/2021 |
| PLAN CHECK FEE | ¤93.20 | 01/29/2021 |
| PLUMBING FEE | ¤199.80 | 01/29/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤466.00 | 01/29/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,338.75 |