Permit #2020111056
Permit Details
Status: COED
| Parcel Id: 07-11-31-7035-01020-0110 |
| CONDITIONED SPACE: 2062 sqft |
| GARAGE: 502 sqft |
| OPENED PORCH (WITH ROOF) : 146 sqft |
| OPENED PORCH (WITH ROOF) : 43 sqft |
| Total Square Footage: 2753 sqft |
| Block: 01020 |
| Subdivision: 2172 - SECTION 35-BELLE TERRE |
| Job Phone: 386-447-4151 |
| Location Address: 123 BICKFORD DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 12/15/2020 |
| NOC: RECORDED |
| Applicant name: GENE WARREN SLONE |
| Owner: MASEFIELD DEVELOPMENT LLC |
|
Address 50 LEANNI WAY STE C-1 PALM COAST, FL 32137 |
| Lot: 0110 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY HOME |
| Type: CN |
Contractor
FLORIDA GREEN CONSTRUCTION INC.
| Status | Location Address | State License Number | Phone |
| INACTIVE |
870 E RETTA STREET DELEON SPRINGS, FL 32130 |
CBC1260957 (Exp: 08/31/2026) | 407-580-2657 |
Sub Contractors
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
ERIC FRANCO
| Status | Location Address | State License Number | Phone |
| CANCEL |
840 DELTONA BLVD SUITE F-2 SANFORD, FL 32771 |
CCC1327280 (Exp: 08/31/2022) | 386-575-4007 |
JOHN EDWARD GAMBONE
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
15 HARGROVE LN PALM COAST, FL 32137 |
1G PALM COAST, FL 32137 |
EC13006037 (Exp: 08/31/2026) | 386-586-9144 |
GREGG A MCANALLY
| Status | Location Address | State License Number | Phone |
| INACTIVE |
3370 AGRICULTURAL CENTER DRIVE PALM COAST, FL 32092 |
CAC1815760 (Exp: 08/31/2022) | 904-829-8898 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 08/31/2022 | FINAL APPROVED | MKRASKI |
| BLD - BUILDING FINAL | 08/19/2022 | Disapproved - NO FEE | MKRASKI |
| Note: 1. ODU needs 4 hurricane straps 2. Condisation line needs to be 12'' off home 3. AHU closet high voltage whip needs to be sealed better 4. Outlet on back side of home outside needs to be weather resistant Stopped inspection | |||
| U-CROSS CONNECTION | 06/08/2022 | APPROVED | DHANEY |
| U -UTILITY RESIDENTIAL FINAL | 06/08/2022 | FINAL APPROVED | DHANEY |
| ROW - FINAL APRON (AFTER POUR) | 03/01/2022 | APPROVED | KRUTH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 03/01/2022 | APPROVED | KRUTH |
| ROW - STORMWATER FINAL | 03/01/2022 | APPROVED | KRUTH |
| FINAL SURVEY (OFFICE USE ONLY) | 03/01/2022 | APPROVED | KRUTH |
| ELECTRIC - EARLY POWER | 02/22/2022 | Disapproved - NO FEE | JMUNSON |
| Note: 1. Neutral wire needs to mbe phased in meter can 2. Need island outlet done by final | |||
| ELECTRIC - EARLY POWER | 02/22/2022 | APPROVED - AS NOTED | JMUNSON |
| Note: THIS IS A REINSPECTION 1. Neutral wire needs to mbe phased in meter can 2. Need island outlet done by final Emailed FPL at 2:52 pm | |||
| ROW- PRE-APRON (PRE-POUR) | 01/07/2022 | APPROVED - AS NOTED | KRUTH |
| Note: pipe is good at the time of the inspection It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete | |||
| U - SEWER TIE IN | 12/16/2021 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 12/16/2021 | APPROVED | MGIBSON |
| PEP TANK INSTALLATION REQUEST | 12/01/2021 | APPROVED | TCHURCHILL |
| INSULATION | 09/08/2021 | APPROVED | FWILLIS |
| LATH/BRICK/ WATER BARRIER | 08/30/2021 | APPROVED | FWILLIS |
| ALL ROUGH | 08/23/2021 | APPROVED | FWILLIS |
| ROOF VALLEY & METAL | 05/27/2021 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 05/20/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION 1. Max O/C spacing on roof sheathing exceeded per FBC R 803.2.3.1 Sheathing fastenings. 2. H2.5 were placed were plans call for sp1 on several locations (h2.5 meet the uplift requirements of sp1) 3. CONTINUOUS LOAD PATH… R301,2.1 OVERFRAMING NOT TIED TO STRUCTURAL MEMBERS BENEATH 4. straps at back porch missing fasteners and or not placed properly 5. need to expose all connections at front entry (covered with OSB) 6. note on plans calls for lsta30 on post or jack to header 7. trusses at front entry over cmu connectors are missing fasteners 5/20/21 - ITEMS CORRECTED. | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 05/19/2021 | Disapproved -FEE REQUIRED | WMILLER |
| Note: 1. Max O/C spacing on roof sheathing exceeded per FBC R 803.2.3.1 Sheathing fastenings. 2. H2.5 were placed were plans call for sp1 on several locations (h2.5 meet the uplift requirements of sp1) 3. CONTINUOUS LOAD PATH… R301,2.1 OVERFRAMING NOT TIED TO STRUCTURAL MEMBERS BENEATH 4. straps at back porch missing fasteners and or not placed properly 5. need to expose all connections at front entry (covered with OSB) 6. note on plans calls for lsta30 on post or jack to header 7. trusses at front entry over cmu connectors are missing fasteners | |||
| TIE BEAM / LINTEL | 05/04/2021 | APPROVED | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 04/30/2021 | APPROVED | TDOAK |
| MONOLITHIC SLAB | 04/13/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Need proof of Compaction Test Need a Readable set of approved plans not separated. No Foundation Detail in plans on site. | |||
| MONOLITHIC SLAB | 04/06/2021 | Disapproved - NO FEE | FWILLIS |
| Note: Need proof of Compaction Test Need a Readable set of approved plans not separated. No Foundation Detail in plans on site. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 03/31/2021 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 02/22/2021 | APPROVED | TCHURCHILL |
| ELECTRIC TEMP POLE | 02/11/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 10:12 am |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 04/29/2021 | 04/30/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 04/29/2021 | 04/30/2021 |
| Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 12/10/2020 | 12/10/2020 |
| Note: Released By: CPISCITELLI | |||
| ZON | COMPLETE | 12/08/2020 | 12/08/2020 |
| Note: Released By: ELENS | |||
| MECH | HOLD | 12/08/2020 | 12/08/2020 |
| Note: Held By: CPISCITELLI Energy calcs and EPL card need to be signed by the builder | |||
| SWALE | COMPLETE | 11/30/2020 | 03/09/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US | |||
| BLD | COMPLETE | 11/25/2020 | 12/02/2020 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 11/25/2020 | 11/30/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 11/25/2020 | 12/01/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 11/25/2020 | 11/30/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 11/25/2020 | 12/02/2020 |
| Note: Released By: CSTONE | |||
| MECH | HOLD | 11/25/2020 | 11/30/2020 |
| Note: Held By: CPISCITELLI Square footage on Energy calcs and heatlaod does not match the plans. Revise to match | |||
| PLUM | COMPLETE | 11/25/2020 | 12/02/2020 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 11/25/2020 | 12/01/2020 |
| Note: Released By: RGROSS | |||
| ZON | HOLD | 11/25/2020 | 11/30/2020 |
| Note: Held By: ELENS Four shrubs are required on each side: Four, in addition to the A/screening on the left, and four on the right. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION FEE | ¤40.00 | 09/01/2022 |
| NEW RESIDENTIAL INSPECTIONS | ¤514.00 | 12/15/2020 |
| SITE PLAN 20 | ¤20.00 | 12/15/2020 |
| SURCHARGE FS 533.721 | ¤2.00 | 12/15/2020 |
| SURCHARGE - FS 468.631 | ¤2.00 | 12/15/2020 |
| STORM WATER PERMIT FEES | ¤80.00 | 12/15/2020 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 12/15/2020 |
| SEWER CREDIT | (¤850.00) | 12/15/2020 |
| SEWER INSPECTION | ¤25.00 | 12/15/2020 |
| SEWER CAPITAL FACILITY | ¤4,664.55 | 12/15/2020 |
| WATER CAPITAL FACILITY FEE | ¤3,424.45 | 12/15/2020 |
| METER - DEPOSIT | ¤60.00 | 12/15/2020 |
| METER - DEPOSIT | ¤60.00 | 12/15/2020 |
| WATER-METER | ¤441.07 | 12/15/2020 |
| WATER- TURN ON | ¤25.00 | 12/15/2020 |
| WATER- TURN ON | ¤25.00 | 12/15/2020 |
| ADMIN FEE | ¤20.00 | 12/15/2020 |
| CONNECTION FEES | ¤1,017.83 | 12/15/2020 |
| BUILDING DISCOUNT 100% | (¤1,279.40) | 12/15/2020 |
| ELECTRIC FEE | ¤214.20 | 12/15/2020 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 12/15/2020 |
| IMPACT FEE FIRE | ¤367.00 | 12/15/2020 |
| IMPACT FEE PARKS | ¤1,199.12 | 12/15/2020 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 12/15/2020 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 12/15/2020 |
| MECHANICAL FEE | ¤214.20 | 12/15/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 12/15/2020 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 12/15/2020 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 12/15/2020 |
| PLAN CHECK FEE | ¤102.80 | 12/15/2020 |
| PLUMBING FEE | ¤214.20 | 12/15/2020 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,829.82 |