Permit #2020120960

Permit Details

Status: COED

Parcel Id: 07-11-31-7029-00210-0040
CONDITIONED SPACE: 1541 sqft
CONDITIONED SPACE: 252 sqft
GARAGE: 578 sqft
OPENED PORCH (WITH ROOF) : 105 sqft
OPENED PORCH (WITH ROOF) : 118 sqft
Total Square Footage: 2594 sqft
Block: 00210
Subdivision: 2209 - SECTION 29-ROYAL PALMS
Job Phone: 386-447-7007
Location Address: 65 RYAN DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 02/01/2021
NOC: RECORDED
Applicant name: MAXIM TARANNIK
Owner: NOVAKOWSKI RICHARD V & MARIA GRENADA H&W

Address

11631 SW 2ND STREET APT 206

PEMBROKE PINES, FL 33025

Lot: 0040
Contracted Stated Job Value: ¤179,000.00
Job Description: SINGLE HOME RESIDENCE (PERMIT # 2020040301)
Type: CN

Contractor

GOLDEN MAGNOLIA, INC
Status Location Address State License Number Phone
INACTIVE

1 ROCKEFELLER DRIVE

PALM COAST, FL 32164

RR282811984 (Exp: 08/31/2025) 386-447-7007

Sub Contractors

STEPHEN COURTEAUX
Status Location Address State License Number Phone Fax
ACTIVE

85 North Yonge Street

Ormond Beach, FL 32174

EC13001748 (Exp: 08/31/2026) (386) 672-4900 386-676-7472
OLEG BELINSKIY
Status Location Address State License Number Phone
ACTIVE

19 PINE CIRCLE DRIVE19

PALM COAST, FL 32167

CCC1325974 (Exp: 08/31/2026) 386-263-7906
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
GARY LLOYD SHEFFIELD
Status Location Address State License Number Phone
ACTIVE

48 EAGLE LAKES DRIVE

FLAGLER BEACH, FL 32136

CAC048127 (Exp: 08/31/2026) 386-597-3280
PHILIP ALAN KENOVICH
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 1470

HOLLY HILL, FL 32117

LG270 (Exp: 08/31/2026) (386)672-2507

Inspection History

Type Request Date Result Inspector
GAS ROUGH 12/13/2021 APPROVED MGIBSON
Note: THIS IS A REINSPECTION New inspection due to canceled inspection THIS IS A REINSPECTION GAS LINE NEEDS TO BE BONDED ANOTHER GAS ROUGH INSPECTION WILL NEED TO BE CALLED IN WHEN AB GROUND TANKS OR UG TANK IS ON SITE AND LINES NEED TO BE APPROVED FROM TANKS TO HOUSE CONNECT NO BOND WIRE AND NO GUAGE PRESENT AT TIME OF INSPECTION
BLD - BUILDING FINAL 12/10/2021 FINAL APPROVED JWALKER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Home has what appear to be personal belongs moved in. Blocking access to outlets Missing sink in lauindry. Back bathroom missing sink cabinets. The flex tight conduit at outdoor condensor is not attached properly. Please have all items and trash, and tools removed for access to outlets, showers, toilets. ETC. Stopped inspection 12/3/21 Checked A/C condensor before trying to enter. The Locking caps are not locked. The home was locked unable to enter. 12/7/21 1 The return plenum next to the air handler. 3" minimum space is required 2 The drian in the front shower is not grouted 3 Missing discharge pipe at water heater 4 Garage door and rear slider entrances need to have working switched light fixtures 5 Attic stairs are not cut to open correctly 6 There is an exposed UFB wire coming up out of the floor at the kitchen island. 7 Tighten all loose outlets. Check all 8 The energy calculations do not match the installed units.
BLD - BUILDING FINAL 12/09/2021 CANCELLED BY APPLICANT JWALKER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Home has what appear to be personal belongs moved in. Blocking access to outlets Missing sink in lauindry. Back bathroom missing sink cabinets. The flex tight conduit at outdoor condensor is not attached properly. Please have all items and trash, and tools removed for access to outlets, showers, toilets. ETC. Stopped inspection 12/3/21 Checked A/C condensor before trying to enter. The Locking caps are not locked. The home was locked unable to enter. 12/7/21 1 The return plenum next to the air handler. 3" minimum space is required 2 The drian in the front shower is not grouted 3 Missing discharge pipe at water heater 4 Garage door and rear slider entrances need to have working switched light fixtures 5 Attic stairs are not cut to open correctly 6 There is an exposed UFB wire coming up out of the floor at the kitchen island. 7 Tighten all loose outlets. Check all 8 The energy calculations do not match the installed units.
BLD - BUILDING FINAL 12/07/2021 Disapproved -FEE REQUIRED JWALKER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Home has what appear to be personal belongs moved in. Blocking access to outlets Missing sink in lauindry. Back bathroom missing sink cabinets. The flex tight conduit at outdoor condensor is not attached properly. Please have all items and trash, and tools removed for access to outlets, showers, toilets. ETC. Stopped inspection 12/3/21 Checked A/C condensor before trying to enter. The Locking caps are not locked. The home was locked unable to enter. 12/7/21 1 The return plenum next to the air handler. 3" minimum space is required 2 The drian in the front shower is not grouted 3 Missing discharge pipe at water heater 4 Garage door and rear slider entrances need to have working switched light fixtures 5 Attic stairs are not cut to open correctly 6 There is an exposed UFB wire coming up out of the floor at the kitchen island. 7 Tighten all loose outlets. Check all 8 The energy calculations do not match the installed units.
BLD - BUILDING FINAL 12/03/2021 Disapproved -FEE REQUIRED JWALKER
Note: THIS IS A REINSPECTION Home has what appear to be personal belongs moved in. Blocking access to outlets Missing sink in lauindry. Back bathroom missing sink cabinets. The flex tight conduit at outdoor condensor is not attached properly. Please have all items and trash, and tools removed for access to outlets, showers, toilets. ETC. Stopped inspection 12/3/21 Checked A/C condensor before trying to enter. The Locking caps are not locked. The home was locked unable to enter.
BLD - BUILDING FINAL 11/24/2021 Disapproved -FEE REQUIRED JWALKER
Note: Home has what appear to be personal belongs moved in. Blocking access to outlets Missing sink in lauindry. Back bathroom missing sink cabinets. The flex tight conduit at outdoor condensor is not attached properly. Please have all items and trash, and tools removed for access to outlets, showers, toilets. ETC. Stopped inspection
U-CROSS CONNECTION 11/24/2021 APPROVED - AS NOTED JHARDING
Note: No cross connections.
U -UTILITY RESIDENTIAL FINAL 11/24/2021 FINAL APPROVED JHARDING
ROW FIELD SURVEY /GRADING CERTIFICATION 11/23/2021 APPROVED RGROSS
ROW - STORMWATER FINAL 11/23/2021 APPROVED RGROSS
ROW - FINAL APRON (AFTER POUR) 11/23/2021 APPROVED RGROSS
Note: See note on pre pour.
GAS ROUGH 11/23/2021 CANCELLED BY APPLICANT WEB
Note: THIS IS A REINSPECTION GAS LINE NEEDS TO BE BONDED ANOTHER GAS ROUGH INSPECTION WILL NEED TO BE CALLED IN WHEN AB GROUND TANKS OR UG TANK IS ON SITE AND LINES NEED TO BE APPROVED FROM TANKS TO HOUSE CONNECTION
GAS ROUGH 11/23/2021 Disapproved -FEE REQUIRED MGIBSON
Note: New inspection due to canceled inspection THIS IS A REINSPECTION GAS LINE NEEDS TO BE BONDED ANOTHER GAS ROUGH INSPECTION WILL NEED TO BE CALLED IN WHEN AB GROUND TANKS OR UG TANK IS ON SITE AND LINES NEED TO BE APPROVED FROM TANKS TO HOUSE CONNECT NO BOND WIRE AND NO GUAGE PRESENT AT TIME OF INSPECTION
FINAL SURVEY (OFFICE USE ONLY) 11/23/2021 APPROVED RGROSS
Note: See note on Pre pour.
ROW- PRE-APRON (PRE-POUR) 09/20/2021 APPROVED - AS NOTED RGROSS
Note: Culvert is set 1/2 tenth higher than tolerance but approved as-noted by Robert because it is the high point.
ELECTRIC - EARLY POWER 06/29/2021 APPROVED - AS NOTED JMUNSON
Note: THIS IS A REINSPECTION Bathroom light needs to be safed off in box. 6/29/21 Emailed FPL at 8:14 am
ELECTRIC - EARLY POWER 06/28/2021 Disapproved - NO FEE JMUNSON
Note: Bathroom light needs to be safed off in box.
GRAVITY SEWER TEST 06/25/2021 APPROVED JGIBSON
U - SEWER TIE IN 06/25/2021 APPROVED JGIBSON
ROW- PRE-APRON (PRE-POUR) 06/11/2021 CANCELLED BY APPLICANT WEB
PEP TANK INSTALLATION REQUEST 05/27/2021 APPROVED CSTONE
INSULATION 04/20/2021 APPROVED MMESSER
Note: THIS IS A REINSPECTION need fire blocking at drop ceilings and chase walls FIREBLOCKING REQUIRED R302.11 (1-6)
INSULATION 04/09/2021 Disapproved - NO FEE WMILLER
Note: need fire blocking at drop ceilings and chase walls FIREBLOCKING REQUIRED R302.11 (1-6)
LATH/BRICK/ WATER BARRIER 04/08/2021 APPROVED MMESSER
GAS ROUGH 04/05/2021 PARTIALLY APPROVED JGIBSON
Note: GAS LINE NEEDS TO BE BONDED ANOTHER GAS ROUGH INSPECTION WILL NEED TO BE CALLED IN WHEN AB GROUND TANKS OR UG TANK IS ON SITE AND LINES NEED TO BE APPROVED FROM TANKS TO HOUSE CONNECTION
ALL ROUGH 03/24/2021 APPROVED MMESSER
ROOF VALLEY & METAL 03/23/2021 APPROVED JBODEN
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/03/2021 APPROVED - AS NOTED MMESSER
Note: Finish securing threaded rods (3) to bottom plate at bearing wall.

Review History

Department Status Date In Date Out
MECH COMPLETE 12/09/2021 12/09/2021
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
PLUM COMPLETE 11/30/2021 11/30/2021
Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM Revision: gas will not be installed a this time per owner.
SWALE COMPLETE 06/16/2021 06/16/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 01/12/2021 01/12/2021
Note: Released By: AMOBLEY
ENGIN1 COMPLETE 01/12/2021 01/13/2021
Note: Released By: TBAKER
SW1 COMPLETE 01/12/2021 01/13/2021
Note: Released By: CTROHA Stormwater review not requested on Permit Correction/Revision Form
ZON HOLD 01/04/2021 01/05/2021
Note: Held By: AMOBLEY Revised site plan missing the driveway and front walkway. Must show them with the width and material for review
MECH COMPLETE 01/04/2021 01/04/2021
Note: Released By: CPISCITELLI
BLD COMPLETE 12/21/2020 01/03/2021
Note: Released By: JPI
CUSVC COMPLETE 12/21/2020 12/23/2020
Note: Released By: HHAND Fees were paid in May 2020 and meter was installed. No additional water/sewer fees owed.
ELEC COMPLETE 12/21/2020 12/22/2020
Note: Released By: JMUNSON
ENGIN1 COMPLETE 12/21/2020 12/22/2020
Note: Released By: TBAKER
LOCATE COMPLETE 12/21/2020 12/21/2020
Note: Released By: CSTONE
MECH HOLD 12/21/2020 12/22/2020
Note: Held By: CPISCITELLI 1.Provide Heatload and Duct Layout signed by the builder 2. Energy calcs need to be signed by the builder
PLUM COMPLETE 12/21/2020 01/03/2021
Note: Released By: JPI
SW1 COMPLETE 12/21/2020 12/23/2020
Note: Released By: CTROHA
ZON HOLD 12/21/2020 12/22/2020
Note: Held By: AMOBLEY Survey must have total lot square footage

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION RESIDENTIAL ¤40.00 12/08/2021
REINSPECTION RESIDENTIAL ¤40.00 12/08/2021
REINSPECTION RESIDENTIAL ¤40.00 12/08/2021
REINSPECTION RESIDENTIAL ¤40.00 12/08/2021
SW ENG - FIELD SURVEY INSPECT ¤20.00 12/08/2021
CONTRACTOR CHANGE ¤40.00 10/27/2021
BUILDING DISCOUNT 100% (¤1,174.40) 02/01/2021
ELECTRIC FEE ¤199.20 02/01/2021
MECHANICAL FEE ¤199.20 02/01/2021
PLAN CHECK FEE ¤92.80 02/01/2021
PLUMBING FEE ¤199.20 02/01/2021
NEW RESIDENTIAL INSPECTIONS ¤464.00 02/01/2021
SITE PLAN 20 ¤20.00 02/01/2021
SURCHARGE FS 533.721 ¤2.00 02/01/2021
SURCHARGE - FS 468.631 ¤2.00 02/01/2021
STORM WATER PERMIT FEES ¤80.00 02/01/2021
ADMIN FEE ¤20.00 02/01/2021
Fees Total Due: ¤0.00 Total Paid: ¤324.00