Permit #2020121003
Permit Details
Status: COED
| Parcel Id: 07-11-31-7023-00270-0070 |
| CONDITIONED SPACE: 2517 sqft |
| GARAGE: 484 sqft |
| OPENED PORCH (WITH ROOF) : 380 sqft |
| OPENED PORCH (WITH ROOF) : 146 sqft |
| Total Square Footage: 3527 sqft |
| Block: 00270 |
| Subdivision: 2191 - SECTION 23-WYNNFIELD |
| Job Phone: 386-447-7007 |
| Location Address: 84 WHITE STAR DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 01/27/2021 |
| NOC: RECORDED |
| Applicant name: MAXIM TARANNIK |
| Owner: MIDELYNE MATHELIER SEJOUR & FRANDY SEJOUR |
|
Address 7A PLUMTREE PLACE PALM COAST , FL 32164 |
| Lot: 0070 |
| Contracted Stated Job Value: ¤308,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
GOLDEN MAGNOLIA, INC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
1 ROCKEFELLER DRIVE PALM COAST, FL 32164 |
RR282811984 (Exp: 08/31/2025) | 386-447-7007 |
Sub Contractors
GARY LLOYD SHEFFIELD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
48 EAGLE LAKES DRIVE FLAGLER BEACH, FL 32136 |
CAC048127 (Exp: 08/31/2026) | 386-597-3280 |
OLEG BELINSKIY
| Status | Location Address | State License Number | Phone |
| ACTIVE |
19 PINE CIRCLE DRIVE19 PALM COAST, FL 32167 |
CCC1325974 (Exp: 08/31/2026) | 386-263-7906 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
FERNANDO MEZA SR
| Status | Location Address | State License Number | Phone |
| ACTIVE |
457 CHELSEA PLACE AVE ORMOND BEACH, FL 32174 |
EC13003906 (Exp: 08/31/2026) | 386-241-5211 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 01/18/2022 | FINAL APPROVED | KSANDOE |
| Note: THIS IS A REINSPECTION not ready for final, only the items listed below were looked at. 1. missing locking caps on A/C 2. Disconect at A/C needs working space 30 inches wide x 36 inches 3. outles not installed 4. kitchen outlets need arch shields 5. sstove/range is on site but not installed Inspection stopped, (check all) | |||
| BLD - BUILDING FINAL | 01/05/2022 | Disapproved -FEE REQUIRED | LMILLER |
| Note: not ready for final, only the items listed below were looked at. 1. missing locking caps on A/C 2. Disconect at A/C needs working space 30 inches wide x 36 inches 3. outles not installed 4. kitchen outlets need arch shields 5. sstove/range is on site but not installed Inspection stopped, (check all) | |||
| U-CROSS CONNECTION | 12/13/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation-no cross connection | |||
| ROW - STORMWATER FINAL | 12/13/2021 | APPROVED | KRUTH |
| U -UTILITY RESIDENTIAL FINAL | 12/13/2021 | FINAL APPROVED | LFITZGERALD |
| ROW - FINAL APRON (AFTER POUR) | 12/10/2021 | APPROVED | KRUTH |
| ROW FIELD SURVEY /GRADING CERTIFICATION | 11/22/2021 | APPROVED | RGROSS |
| FINAL SURVEY (OFFICE USE ONLY) | 11/22/2021 | APPROVED | RGROSS |
| ROW- PRE-APRON (PRE-POUR) | 09/15/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING. | |||
| U - SEWER TIE IN | 09/14/2021 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 09/14/2021 | APPROVED | MGIBSON |
| ELECTRIC - EARLY POWER | 09/10/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 10:15 am | |||
| PEP TANK INSTALLATION REQUEST | 08/06/2021 | APPROVED | CSTONE |
| INSULATION | 07/29/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION Outlet boxes, plumbing penetration, at exterior walls need to have foam sprayed around and fill gaps at insulation board. | |||
| INSULATION | 07/26/2021 | Disapproved - NO FEE | JWALKER |
| Note: Outlet boxes, plumbing penetration, at exterior walls need to have foam sprayed around and fill gaps at insulation board. | |||
| LATH/BRICK/ WATER BARRIER | 07/12/2021 | APPROVED | MMESSER |
| Note: THIS IS A REINSPECTION The lath corners, around the windows are loose and missing fasteners. Lath needs to be fastened a 6" o.c. The area at front entry. Right hand side top of block that was submitted for a revision due to missing block work the revision was approved but will still need to be inspected at roof,bracing, sheating tie and down cell inspection. It cannot pass lath inspection. Remove lath and plywood for rough framing inspection of that area. | |||
| ALL ROUGH | 07/12/2021 | APPROVED - AS NOTED | MMESSER |
| Note: Fill concrete cut out at kitchen island. Seal dryer vent duct at box. | |||
| TIE DOWN | 07/08/2021 | APPROVED | MMESSER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 06/28/2021 | Disapproved -FEE REQUIRED | JWALKER |
| Note: THIS IS A REINSPECTION Trusses missing engineering. A-6, A-7, A-10, AH-9, B, BH5, D-12, DH7A, Missing block work @ truss location EJ2 area. Submit a revision or a detail of the 2X header used and the over framing done in replacement of the EJ2 trusses. Block wall is missing at truss location B1, BH5 right side of front entry. Complete block work and attach trusses per detail. Girder trusses CCGR location 7 engineering drawings. The following Girder tusses also. AH7 location 29 and 16 proper hold down anchor for uplift need to be installed A13 location 23 and 29 Proper hold down anchors for uplifit need to be installed. Anchor hold downs can be located blue print page 10. Roof sheating Rear gable ridge not nailed front left small bath area . Garage area front and back 2 sheets. The engineering packet in the box does not match the trusses lettering and numbering used on the job. Please provide the proper engineering packet, so that fixes can be properly located and checked. The lath and plywood need to be removed at the pony wall revision for proper inspection of framing and attachments. | |||
| LATH/BRICK/ WATER BARRIER | 06/24/2021 | Disapproved - NO FEE | JWALKER |
| Note: The lath corners, around the windows are loose and missing fasteners. Lath needs to be fastened a 6" o.c. The area at front entry. Right hand side top of block that was submitted for a revision due to missing block work the revision was approved but will still need to be inspected at roof,bracing, sheating tie and down cell inspection. It cannot pass lath inspection. Remove lath and plywood for rough framing inspection of that area. | |||
| ROOF VALLEY & METAL | 05/25/2021 | APPROVED | MMESSER |
| ROOF SHEATHING | 05/21/2021 | APPROVED | JWALKER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 05/17/2021 | Disapproved -FEE REQUIRED | JWALKER |
| Note: Trusses missing engineering. A-6, A-7, A-10, AH-9, B, BH5, D-12, DH7A, Missing block work @ truss location EJ2 area. Submit a revision or a detail of the 2X header used and the over framing done in replacement of the EJ2 trusses. Block wall is missing at truss location B1, BH5 right side of front entry. Complete block work and attach trusses per detail. Girder trusses CCGR location 7 engineering drawings. The following Girder tusses also. AH7 location 29 and 16 proper hold down anchor for uplift need to be installed A13 location 23 and 29 Proper hold down anchors for uplifit need to be installed. Anchor hold downs can be located blue print page 10. Roof sheating Rear gable ridge not nailed front left small bath area . Garage area front and back 2 sheets. | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 05/14/2021 | CANCELLED BY APPLICANT | WEB |
| TIE BEAM / LINTEL | 04/14/2021 | APPROVED | MMESSER |
| FOUND SURVEY APPROVED (OFFICE) | 04/06/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 03/16/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION ReBar (DOWELS) Missing on Right side, Left side and Rear. MISSING UFER GROUND .NEC..250.52(3) 3/15/21 - NO CITY STAMPED PLANS ON SITE. PLANS ON SITE (NOT STAMPED) HAVE BEEN SEPARATED. DOCUMENTS MUST BE APPROVED AND KEPT ON SITE 107.3,1. AND SHALL BE OPEN TO INSPECTION BY THE BUILDING OFFICIAL. | |||
| MONOLITHIC SLAB | 03/15/2021 | Disapproved - NO FEE | FWILLIS |
| Note: THIS IS A REINSPECTION ReBar (DOWELS) Missing on Right side, Left side and Rear. MISSING UFER GROUND .NEC..250.52(3) 3/15/21 - NO CITY STAMPED PLANS ON SITE. PLANS ON SITE (NOT STAMPED) HAVE BEEN SEPARATED. DOCUMENTS MUST BE APPROVED AND KEPT ON SITE 107.3,1. AND SHALL BE OPEN TO INSPECTION BY THE BUILDING OFFICIAL. | |||
| MONOLITHIC SLAB | 03/12/2021 | Disapproved -FEE REQUIRED | FWILLIS |
| Note: ReBar (DOWELS) Missing on Right side, Left side and Rear. MISSING UFER GROUND .NEC..250.52(3) | |||
| MONOLITHIC SLAB | 03/11/2021 | CANCELLED BY APPLICANT | WEB |
| PLUMBING 1ST ROUGH UNDERGROUND | 03/09/2021 | APPROVED | JGIBSON |
| WATER METER INSTALLATION REQUEST | 01/28/2021 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| BADMIN | HOLD | 12/10/2021 | 12/10/2021 |
| Note: Held By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM YOU NEED TO GO TO OUR WEBSITE AND UPLOAD OUR BLOWER DOOR TEST THAT IS 2020 7 EDITION THIS BLOWER DOOR TEST YOU SUBMITTED IS 2017 | |||
| BADMIN | COMPLETE | 12/10/2021 | 12/10/2021 |
| Note: Released By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 11/22/2021 | 11/22/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 11/22/2021 | 11/22/2021 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| BADMIN | COMPLETE | 10/18/2021 | 10/18/2021 |
| Note: Released By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM the blower door test has to say 2020 7 edition please go to our website and pick the correct one. | |||
| BLD | COMPLETE | 06/02/2021 | 06/10/2021 |
| Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 04/06/2021 | 04/06/2021 |
| Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 04/06/2021 | 04/06/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US | |||
| ZON | HOLD | 01/05/2021 | 01/05/2021 |
| Note: Held By: AMOBLEY Two additional shrubs required on left side facing the right of way. Must have a total of six shrubs on street side | |||
| ZON | COMPLETE | 01/05/2021 | 01/05/2021 |
| Note: Released By: AMOBLEY | |||
| BLD | COMPLETE | 12/22/2020 | 01/04/2021 |
| Note: Released By: JPI 1. The product approval list appears to be missing mullions. Please cure. | |||
| CUSVC | COMPLETE | 12/22/2020 | 12/23/2020 |
| Note: Released By: HHAND | |||
| ELEC | COMPLETE | 12/22/2020 | 12/28/2020 |
| Note: Released By: JMUNSON | |||
| ENGIN1 | COMPLETE | 12/22/2020 | 12/22/2020 |
| Note: Released By: TBAKER | |||
| LOCATE | COMPLETE | 12/22/2020 | 12/23/2020 |
| Note: Released By: CSTONE | |||
| MECH | COMPLETE | 12/22/2020 | 12/23/2020 |
| Note: Released By: CPISCITELLI | |||
| PLUM | COMPLETE | 12/22/2020 | 01/04/2021 |
| Note: Released By: JPI | |||
| SW1 | COMPLETE | 12/22/2020 | 12/30/2020 |
| Note: Released By: RGROSS | |||
| ZON | HOLD | 12/22/2020 | 12/23/2020 |
| Note: Held By: AMOBLEY Two additional shrubs required on left side facing the right of way AC Pad must be screened with 7 gallon shrubs | |||
| SWALE | COMPLETE | 12/22/2020 | 04/13/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| REINSPECTION RESIDENTIAL | ¤40.00 | 01/18/2022 |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 11/24/2021 |
| REINSPECTION FEE | ¤40.00 | 11/01/2021 |
| REINSPECTION FEE | ¤40.00 | 11/01/2021 |
| REINSPECTION FEE | ¤40.00 | 11/01/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 11/01/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 11/01/2021 |
| CONTRACTOR CHANGE | ¤40.00 | 11/01/2021 |
| BUILDING DISCOUNT 100% | (¤1,548.20) | 01/27/2021 |
| ELECTRIC FEE | ¤252.60 | 01/27/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 01/27/2021 |
| IMPACT FEE FIRE | ¤367.00 | 01/27/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 01/27/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 01/27/2021 |
| IMPACT FEE TRANSPORTATION | ¤1,674.00 | 01/27/2021 |
| MECHANICAL FEE | ¤252.60 | 01/27/2021 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 01/27/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 01/27/2021 |
| PLAN CHECK FEE | ¤128.40 | 01/27/2021 |
| PLUMBING FEE | ¤252.60 | 01/27/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤642.00 | 01/27/2021 |
| SITE PLAN 20 | ¤20.00 | 01/27/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 01/27/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 01/27/2021 |
| CONNECTION FEES | ¤1,017.83 | 01/27/2021 |
| METER - DEPOSIT | ¤60.00 | 01/27/2021 |
| WATER- TURN ON | ¤25.00 | 01/27/2021 |
| ADMIN FEE | ¤20.00 | 01/27/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 01/27/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤50.22) | 01/27/2021 |
| SEWER CREDIT | (¤1,342.00) | 01/27/2021 |
| SEWER INSPECTION | ¤25.00 | 01/27/2021 |
| SEWER CAPITAL FACILITY | ¤4,664.55 | 01/27/2021 |
| WATER CAPITAL FACILITY FEE | ¤3,424.45 | 01/27/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,046.75 |