Permit #2020121306

Permit Details

Status: FINAL

Parcel Id: 09-12-31-0000-02030-0020
Total Square Footage: 3200 sqft
Block: 02030
Subdivision: -
Job Phone: 407-916-7235
Location Address: 60 MEMORIAL MEDICAL PKWY
Type: CIA - COMMERCIAL INTERIOR EXTERIOR ALTERATION
Issue Date: 10/14/2021
NOC: Unknown
Applicant name: BRUCE ROBERT ADAMS
Owner: MEMORIAL HOSPITAL-FLAGLER INC

Address

60 MEMORIAL MEDICAL PKWY

PALM COAST, FL 32164

Lot: 0020
Contracted Stated Job Value: ¤2,066,563.00
Job Description: Renovations - Sterile Processing Department
Type: CN

Contractor

THE ROBINS & MORTON GROUP
Status Location Address Mailing Address State License Number Phone
ACTIVE

423 S KELLER RD

ORLANDO, FL 32810

#200

ORLANDO, FL 32810

CGC1523017 (Exp: 08/31/2026) 407-916-7235

Inspection History

Type Request Date Result Inspector
U - UTILITY COMMERCIAL FINAL 03/14/2023 FINAL APPROVED LFITZGERALD
Note: this inspection is on most if not all CIA just as a cover all protection in case water meter's/hydrants or any other water/sewer assembly was utilized.
BUILDING FINAL 11/03/2022 FINAL APPROVED LMILLER
Note: 11/2/2022 - PREVIOUS INSPECTION NOTES 9/16/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION THIS IS A REINSPECTION Partial for first pahse only in Copy room, O.R. storage, and First pase of Decon room 7-7-22 partial for Sequence 2 phase 2 9-16-22 partial for phase 2 (approved) 11-2-22 cancelled per Keith, Need to close out progress inspections and sprinkler permit prior' 11-3-22 Final Approved
FIRE FINAL 11/03/2022 CANCELLED BY APPLICANT WEB
FIRE FINAL 11/03/2022 APPROVED LMILLER
PLUMBING FINAL 11/03/2022 APPROVED - AS NOTED RMARTIN
Note: PER MARK GIBSON ALREADY APPROVED
HVAC FINAL 11/03/2022 FINAL APPROVED CPISCITELLI
ELECTRIC 2ND ROUGH 11/03/2022 APPROVED RMARTIN
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION marked on teds plan 6/30/22 marked on teds plans
BUILDING FINAL 11/02/2022 CANCELLED BY APPLICANT LMILLER
Note: 9/16/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION THIS IS A REINSPECTION Partial for first pahse only in Copy room, O.R. storage, and First pase of Decon room 7-7-22 partial for Sequence 2 phase 2 9-16-22 partial for phase 2 (approved) 11-2-22 cancelled per Keith, Need to close out progress inspections and sprinkler permit prior
BUILDING FINAL 09/16/2022 PARTIALLY APPROVED LMILLER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Partial for first pahse only in Copy room, O.R. storage, and First pase of Decon room 7-7-22 partial for Sequence 2 phase 2 9-16-22 partial for phase 2 (approved)
ELECTRIC FINAL 09/16/2022 APPROVED RMARTIN
Note: THIS IS A REINSPECTION 7/6/22 Soil hold final/partial for SPD renovation
ABOVE CEILING 08/18/2022 APPROVED RMARTIN
ELECTRIC OTHER 08/17/2022 APPROVED RMARTIN
Note: New inspection due to canceled inspection Inspector Notes from Inspection 3220 THIS NEEDS TO BE AN ABOVE CEILING
ELECTRIC OTHER 08/16/2022 CANCELLED BY APPLICANT WEB
Note: Inspector Notes from Inspection 3220 THIS NEEDS TO BE AN ABOVE CEILING
HVAC OTHER 08/15/2022 APPROVED CPISCITELLI
Note: THIS IS A REINSPECTION Inspected decon room and soil area
HVAC OTHER 08/12/2022 Disapproved - NO FEE CPISCITELLI
Note: Need to seal returns in room and support all flex
ELECTRIC OTHER 08/12/2022 APPROVED - AS NOTED RMARTIN
Note: THIS NEEDS TO BE AN ABOVE CEILING
PLUMBING OTHER 08/12/2022 APPROVED - AS NOTED MGIBSON
Note: THIS WAS INSPECTED AT SECOND ROUGH ABOVE CELING
FIREWALL FINAL 08/12/2022 APPROVED DCUSHING
PLUMBING FINAL 07/21/2022 PARTIALLY APPROVED MGIBSON
Note: Inspector Notes from Inspection 3080 7/13/22 This inspection was for one wall located in the contamination room . Inspected 1/2"scw, 1/2" hw ,1/2" DI, and 1/2" CA A new Compressed air line located on same wall oppsite side was inspected. At contractors risk the wall may be covered . Submitt a revision to the building department for new compressed air line. Left notes on the PL 103 drawing Level 1 pressure phase 2. DETAIL 3 This was the last partial inspection for test guages on all water dsi, line, compressed air line,hot,cold, . informed c/m that tags would need to be installed and legend for related tags for shut-off valves need to be in place for last plumbing final inspection
ELECTRIC 2ND ROUGH 07/20/2022 CANCELLED BY APPLICANT RMARTIN
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION marked on teds plan 6/30/22 marked on teds plans
FRAMING 07/14/2022 PARTIALLY APPROVED DCUSHING
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION pending approved documents (one section of firewall only) 2-28-22 notes above resolved Partial framing (phase 1 complete) 6-16-22 need approved revision on site for inspection 6-17-22 partial for revision only 7.14.22 - partial - decon, cartwash areas
PLUMBING 2ND ROUGH 07/13/2022 APPROVED - AS NOTED JWALKER
Note: 7/13/22 This inspection was for one wall located in the contamination room . Inspected 1/2"scw, 1/2" hw ,1/2" DI, and 1/2" CA A new Compressed air line located on same wall oppsite side was inspected. At contractors risk the wall may be covered . Submitt a revision to the building department for new compressed air line. Left notes on the PL 103 drawing Level 1 pressure phase 2. DETAIL 3
BUILDING FINAL 07/07/2022 PARTIALLY APPROVED LMILLER
Note: THIS IS A REINSPECTION Partial for first pahse only in Copy room, O.R. storage, and First pase of Decon room 7-7-22 partial for Sequence 2 phase 2
ABOVE CEILING 07/06/2022 APPROVED JMUNSON
Note: THIS IS A REINSPECTION THIS WAS DONE ON 4/5/22
ELECTRIC FINAL 07/06/2022 PARTIALLY APPROVED JMUNSON
Note: 7/6/22 Soil hold final/partial for SPD renovation
PLUMBING FINAL 07/06/2022 PARTIALLY APPROVED MGIBSON
Note: THIS WAS FOR HYDRANT BOX WITH DRAIN
HVAC OTHER 07/06/2022 APPROVED CPISCITELLI
Note: soil hold area finaled
ELECTRIC 2ND ROUGH 06/30/2022 PARTIALLY APPROVED RMARTIN
Note: THIS IS A REINSPECTION marked on teds plan 6/30/22 marked on teds plans
PLUMBING 2ND ROUGH 06/30/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Inspector Notes from Inspection 3070 THIS IS A REINSPECTION THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY THIS COMPLETES ALL PHASES OF UNDERGROUND FIRST ROUGH PLUMBING THIS WAS A PARTIAL INSPECTION FOR JUST ONE BOX WITH WASTE AND VENT AND WATER LINE THIS WAS A PARTIAL INSPECTION FOR WASTE AND VENT FOR ONE SINK ONLY THIS WAS A VENT CONNECTION IN CEILING AREA ONLY FOR WALL INSPECTION IONIZED WATER LINES AND PRESSURE GUAGES FOR LINES IN SAME WALL AREA AS BEFORE ARE APPROVED ONLY
PLUMBING 2ND ROUGH 06/29/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Inspector Notes from Inspection 3070 THIS IS A REINSPECTION THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY THIS COMPLETES ALL PHASES OF UNDERGROUND FIRST ROUGH PLUMBING THIS WAS A PARTIAL INSPECTION FOR JUST ONE BOX WITH WASTE AND VENT AND WATER LINE THIS WAS A PARTIAL INSPECTION FOR WASTE AND VENT FOR ONE SINK ONLY THIS WAS A VENT CONNECTION IN CEILING AREA ONLY FOR WALL INSPECTION
PLUMBING 2ND ROUGH 06/23/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION Inspector Notes from Inspection 3070 THIS IS A REINSPECTION THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY THIS COMPLETES ALL PHASES OF UNDERGROUND FIRST ROUGH PLUMBING THIS WAS A PARTIAL INSPECTION FOR JUST ONE BOX WITH WASTE AND VENT AND WATER LINE THIS WAS A PARTIAL INSPECTION FOR WASTE AND VENT FOR ONE SINK ONLY
FRAMING 06/21/2022 PARTIALLY APPROVED LMILLER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION pending approved documents (one section of firewall only) 2-28-22 notes above resolved Partial framing (phase 1 complete) 6-16-22 need approved revision on site for inspection 6-17-22 partial for revision only
PLUMBING 2ND ROUGH 06/17/2022 PARTIALLY APPROVED MGIBSON
Note: Inspector Notes from Inspection 3070 THIS IS A REINSPECTION THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY THIS COMPLETES ALL PHASES OF UNDERGROUND FIRST ROUGH PLUMBING THIS WAS A PARTIAL INSPECTION FOR JUST ONE BOX WITH WASTE AND VENT AND WATER LINE
ELECTRIC 2ND ROUGH 06/17/2022 PARTIALLY APPROVED RMARTIN
Note: marked on teds plan
HVAC ROUGH 06/17/2022 PARTIALLY APPROVED CPISCITELLI
Note: THIS IS A REINSPECTION 6/17 inspected fire damper and supply duct phase 2 sequence 1 3/23 tested smoke detectors in unit 3/8 inspected phase 1 supply trunk to be able to wrap 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
FRAMING 06/16/2022 Disapproved -FEE REQUIRED LMILLER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION pending approved documents (one section of firewall only) 2-28-22 notes above resolved Partial framing (phase 1 complete) 6-16-22 need approved revision on site for inspection
MONOLITHIC SLAB 06/07/2022 APPROVED LMILLER
MONOLITHIC SLAB 06/06/2022 CANCELLED BY APPLICANT WEB
PLUMBING 1ST ROUGH 05/19/2022 APPROVED - AS NOTED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY THIS COMPLETES ALL PHASES OF UNDERGROUND FIRST ROUGH PLUMBING
PLUMBING 1ST ROUGH 05/17/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION rerouting of 4'' sanitary line and rough in 3 compartment sink line THIS WAS A CONTINUE OF SAME LINE WHERE A FLOOR SINK WAS ADDEDED ALONG WITH OTHER LINE FOR SANITARY
PLUMBING 1ST ROUGH 05/13/2022 PARTIALLY APPROVED MGIBSON
Note: rerouting of 4'' sanitary line and rough in 3 compartment sink line
PLUMBING OTHER 04/11/2022 APPROVED - AS NOTED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION WATSTE AND WATER FOR '' EVS '' ROOM ONLY THIS WAS FOR WASTE & VENT WATER IN EVS ROOM IN CEILING AREA ONLY THIS WAS A PARTIAL AREA FOR WATER LINES HOT AND COLD, TWO DROPS FROM CELINNG AREA AND PURIFIED WATER LINES, ABOVE CELING AREA STILL NEEDS TO BE INSULALATED AND FIRE WALL NEEDS TO BE SEALED THIS WAS A PARTIAL INSPECTION FOR DS WATER PRESSURE TEST IN CELING AN PRESSURE TEST FOR WATER LINES IN CEILING 4/11/25 Inspected two hand wash / eye wash sinks and approved them.
ABOVE CEILING 04/06/2022 PARTIALLY APPROVED RMARTIN
Note: THIS WAS DONE ON 4/5/22
ABOVE CEILING 04/04/2022 APPROVED RMARTIN
Note: THIS IS A REINSPECTION NEED TO LEAVE TILE OUT IN AREAS WHERE DUCTS NOT SEALED, ELECTRIC, PLUMBING ARE GOOD IN THE TWO BACK ROOMS
ABOVE CEILING 04/01/2022 PARTIALLY APPROVED RMARTIN
Note: NEED TO LEAVE TILE OUT IN AREAS WHERE DUCTS NOT SEALED, ELECTRIC, PLUMBING ARE GOOD IN THE TWO BACK ROOMS
PLUMBING PRESSURE TEST 03/23/2022 APPROVED PBUCKLEY
Note: THIS IS A REINSPECTION THIS WAS A PRESSURE TEST ON WATER LINES AND DSI LINES ALL ARE APPROVED Steam lines (4) inspected icluding 100 psi air test for sterlizers.
HVAC ROUGH 03/23/2022 PARTIALLY APPROVED CPISCITELLI
Note: 3/23 tested smoke detectors in unit 3/8 inspected phase 1 supply trunk to be able to wrap 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 03/22/2022 CANCELLED BY APPLICANT WEB
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION 3/8 inspected phase 1 supply trunk to be able to wrap 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 03/18/2022 APPROVED - AS NOTED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION partial final for OR storage, copy room, and decontainment room Duct wrap deontamination room 1-1400 and vicinity duct is shown on M101.1
PLUMBING 2ND ROUGH 03/18/2022 APPROVED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A PARTIAL FINAL OF PHASE ONE, STERILE SINK IS TEMPORARY, AND WILL BE RELOCATED TO DIFFERENT LOCATION AT A LATER PHASE
PLUMBING PRESSURE TEST 03/15/2022 PARTIALLY APPROVED MGIBSON
Note: THIS WAS A PRESSURE TEST ON WATER LINES AND DSI LINES ALL ARE APPROVED
HVAC ROUGH 03/15/2022 APPROVED - AS NOTED PBUCKLEY
Note: Test on VAV supply / return lines
HVAC FINAL 03/15/2022 CANCELLED BY APPLICANT PBUCKLEY
Note: THIS IS A REINSPECTION partial final for OR storage, copy room, and decontainment room
HVAC ROUGH 03/14/2022 PARTIALLY APPROVED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION 3/8 inspected phase 1 supply trunk to be able to wrap 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 03/08/2022 PARTIALLY APPROVED CPISCITELLI
Note: THIS IS A REINSPECTION 3/8 inspected phase 1 supply trunk to be able to wrap 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
PLUMBING 2ND ROUGH 03/02/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION GEORGE CALLED AND CANCEALED INSPECTION WRONG INSPECTION, THIS WAS A FIRST ROUGH PLUBING INSPECTION THIS IS A PARTIAL INSPECTION FOR WALLS ONLY WASTE AND VENT, WATER LINES OTHER PLUMBING TO BE SCHEDULED AT A LATER DATE
ELECTRIC 2ND ROUGH 02/28/2022 APPROVED - AS NOTED RMARTIN
Note: WALLS ONLY, LOOKED AT FIRE ALARM CONDUIT ALSO
FRAMING 02/28/2022 PARTIALLY APPROVED LMILLER
Note: THIS IS A REINSPECTION pending approved documents (one section of firewall only) 2-28-22 notes above resolved Partial framing (phase 1 complete)
MONOLITHIC SLAB 02/22/2022 APPROVED LMILLER
PLUMBING 1ST ROUGH 02/17/2022 APPROVED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS APPROVED, THIS WILL BE THE FIRST OF ABOUT 5 FIRST ROUGH INSPECTIONS TO BE DONE IN DIFFERENT PHASES this was a partial inspection for 3'' soil stack that is being remove and rerouted into existing wall, also looked at sanitary line tht is being relocated to another area for floor space along with 6'' roofdrain, will inspect at a later time waste line and roof drain are approved, howeverexisting conduit is in the way for plumbing to be copleted to new location og floorsinks and floor drains in other areas RFIS HAVE BEEN SUBMITTED
PLUMBING 1ST ROUGH 02/11/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS APPROVED, THIS WILL BE THE FIRST OF ABOUT 5 FIRST ROUGH INSPECTIONS TO BE DONE IN DIFFERENT PHASES this was a partial inspection for 3'' soil stack that is being remove and rerouted into existing wall, also looked at sanitary line tht is being relocated to another area for floor space along with 6'' roofdrain, will inspect at a later time waste line and roof drain are approved, howeverexisting conduit is in the way for plumbing to be copleted to new location og floorsinks and floor drains in other areas RFIS HAVE BEEN SUBMITTED
PLUMBING 1ST ROUGH 02/10/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS APPROVED, THIS WILL BE THE FIRST OF ABOUT 5 FIRST ROUGH INSPECTIONS TO BE DONE IN DIFFERENT PHASES this was a partial inspection for 3'' soil stack that is being remove and rerouted into existing wall, also looked at sanitary line tht is being relocated to another area for floor space along with 6'' roofdrain, will inspect at a later time
HVAC ROUGH 02/08/2022 PARTIALLY APPROVED CPISCITELLI
Note: 2/8 Inspected phase 1 trunk to be able to wrap 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 02/01/2022 PARTIALLY APPROVED CPISCITELLI
Note: THIS IS A REINSPECTION 2/1 inspected wrap in mechanical room 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 01/27/2022 PARTIALLY APPROVED CPISCITELLI
Note: 1/27 Inspected duct tie in to unit 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
HVAC ROUGH 01/25/2022 PARTIALLY APPROVED CPISCITELLI
Note: 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans. 1/25/22 Inspect duct seal on trunks in mechanical room phase 1
PLUMBING FINAL 01/18/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A PARTIAL FINAL OF PHASE ONE, STERILE SINK IS TEMPORARY, AND WILL BE RELOCATED TO DIFFERENT LOCATION AT A LATER PHASE
BUILDING FINAL 01/18/2022 PARTIALLY APPROVED LMILLER
Note: Partial for first pahse only in Copy room, O.R. storage, and First pase of Decon room
HVAC FINAL 01/14/2022 PARTIALLY APPROVED CPISCITELLI
Note: partial final for OR storage, copy room, and decontainment room
ELECTRIC FINAL 01/13/2022 APPROVED JMUNSON
PLUMBING OTHER 01/03/2022 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION WATSTE AND WATER FOR '' EVS '' ROOM ONLY THIS WAS FOR WASTE & VENT WATER IN EVS ROOM IN CEILING AREA ONLY THIS WAS A PARTIAL AREA FOR WATER LINES HOT AND COLD, TWO DROPS FROM CELINNG AREA AND PURIFIED WATER LINES, ABOVE CELING AREA STILL NEEDS TO BE INSULALATED AND FIRE WALL NEEDS TO BE SEALED THIS WAS A PARTIAL INSPECTION FOR DS WATER PRESSURE TEST IN CELING AN PRESSURE TEST FOR WATER LINES IN CEILING
HVAC ROUGH 12/28/2021 PARTIALLY APPROVED PBUCKLEY
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans.
HVAC ROUGH 12/22/2021 CANCELLED BY APPLICANT TSTAUFFACHER
Note: THIS IS A REINSPECTION 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans.
HVAC ROUGH 12/14/2021 PARTIALLY APPROVED CPISCITELLI
Note: 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans 12/14 inspected metal taps and metal runs duct seal on supply to be able to wrap. Highlighted on plans.
PLUMBING OTHER 12/13/2021 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION WATSTE AND WATER FOR '' EVS '' ROOM ONLY THIS WAS FOR WASTE & VENT WATER IN EVS ROOM IN CEILING AREA ONLY THIS WAS A PARTIAL AREA FOR WATER LINES HOT AND COLD, TWO DROPS FROM CELINNG AREA AND PURIFIED WATER LINES, ABOVE CELING AREA STILL NEEDS TO BE INSULALATED AND FIRE WALL NEEDS TO BE SEALED
ABOVE CEILING 12/13/2021 APPROVED - AS NOTED RMARTIN
Note: PLUMBING MOSTLY
PLUMBING 2ND ROUGH 12/09/2021 CANCELLED BY APPLICANT MGIBSON
Note: THIS IS A REINSPECTION GEORGE CALLED AND CANCEALED INSPECTION WRONG INSPECTION, THIS WAS A FIRST ROUGH PLUBING INSPECTION
HVAC ROUGH 12/08/2021 PARTIALLY APPROVED CPISCITELLI
Note: THIS IS A REINSPECTION 12/2 Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans 12/8 Inspected metal trunk seal to be able to wrap. Inspected wrap on other trunk in same area. Highlighted and noted on plans
PLUMBING OTHER 12/08/2021 PARTIALLY APPROVED MGIBSON
Note: THIS IS A REINSPECTION WATSTE AND WATER FOR '' EVS '' ROOM ONLY THIS WAS FOR WASTE & VENT WATER IN EVS ROOM IN CEILING AREA ONLY
ELECTRIC 2ND ROUGH 12/08/2021 APPROVED RMARTIN
ABOVE CEILING 12/08/2021 APPROVED - AS NOTED RMARTIN
Note: MEPS MET ON SITE
MONOLITHIC SLAB 12/08/2021 APPROVED LMILLER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION area marked on plumbing plans 11029-21... detail needs to be approved and on site for inspection. un-approved details on site call for expansion bolts around perimeter, tapcons were used, need approved revision on site matching conditions at site. 12-08-21... notes above resolved
HVAC ROUGH 12/02/2021 PARTIALLY APPROVED CPISCITELLI
Note: Inspect 2 damper openings only (Not Dampers) and metal trunk seal in same area to be able to wrap. Highlighted and noted plans
PLUMBING OTHER 12/01/2021 PARTIALLY APPROVED MGIBSON
Note: WATSTE AND WATER FOR '' EVS '' ROOM ONLY
MONOLITHIC SLAB 11/29/2021 Disapproved -FEE REQUIRED LMILLER
Note: THIS IS A REINSPECTION area marked on plumbing plans 11029-21... detail needs to be approved and on site for inspection. un-approved details on site call for expansion bolts around perimeter, tapcons were used, need approved revision on site matching conditions at site.
MONOLITHIC SLAB 11/19/2021 PARTIALLY APPROVED LMILLER
Note: area marked on plumbing plans
ELECTRIC 2ND ROUGH 11/18/2021 PARTIALLY APPROVED JMUNSON
Note: THIS IS A REINSPECTION NEED APPROVED SET OF PLANS ON SITE FOR INSPECTION, MARKED ON PRINT WALL ONLY 11/18/21 Marked on print walls only
FIREWALL NAILING 11/18/2021 APPROVED LMILLER
Note: looked at drywall of one wall that was inspected for framing prior
FRAMING 11/16/2021 PARTIALLY APPROVED LMILLER
Note: pending approved documents (one section of firewall only)
ELECTRIC 2ND ROUGH 11/16/2021 PARTIALLY APPROVED RMARTIN
Note: NEED APPROVED SET OF PLANS ON SITE FOR INSPECTION, MARKED ON PRINT WALL ONLY
PLUMBING 1ST ROUGH 11/15/2021 PARTIALLY APPROVED MGIBSON
Note: THIS IS APPROVED, THIS WILL BE THE FIRST OF ABOUT 5 FIRST ROUGH INSPECTIONS TO BE DONE IN DIFFERENT PHASES
PLUMBING 2ND ROUGH 11/15/2021 Disapproved - NO FEE MGIBSON
Note: WRONG INSPECTION, THIS WAS A FIRST ROUGH PLUBING INSPECTION

Review History

Department Status Date In Date Out
MECH COMPLETE 09/21/2022 09/21/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
PLUM COMPLETE 09/21/2022 09/26/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
BLD COMPLETE 09/12/2022 09/19/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
ELEC COMPLETE 09/12/2022 09/19/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ELEC COMPLETE 08/25/2022 08/29/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 07/19/2022 07/22/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
ELEC COMPLETE 07/19/2022 07/19/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
PLUM COMPLETE 07/19/2022 07/22/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
BLD COMPLETE 07/07/2022 07/07/2022
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
BLD COMPLETE 06/22/2022 07/06/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
BADMIN INFORMATION 06/20/2022 06/20/2022
Note: Marked INFORMATION By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM Please rename the files with the plan sheet name - you can add additional information 'after' the plan sheet name, but the file name should be the plan sheet name.
ELEC COMPLETE 05/25/2022 05/26/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
BLD COMPLETE 04/13/2022 04/19/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
ELEC COMPLETE 04/13/2022 04/18/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
MECH COMPLETE 04/13/2022 04/14/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
BLD COMPLETE 03/29/2022 03/31/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
ELEC COMPLETE 03/29/2022 03/30/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
FI1 COMPLETE 03/29/2022 04/04/2022
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
MECH COMPLETE 03/29/2022 03/29/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
PLUM COMPLETE 03/29/2022 04/01/2022
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
MECH COMPLETE 12/01/2021 12/02/2021
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
BLD COMPLETE 12/01/2021 12/07/2021
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
ELEC COMPLETE 12/01/2021 12/01/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
FD1 COMPLETE 12/01/2021 12/01/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
PLUM COMPLETE 12/01/2021 12/07/2021
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
BLD CANCEL 11/24/2021 11/29/2021
Note: cancelled to allow for additional information to be uploaded.
ELEC CANCEL 11/24/2021 11/29/2021
Note: cancelled to allow for additional information to be uploaded.
FI1 CANCEL 11/24/2021 11/29/2021
Note: cancelled to allow for additional information to be uploaded.
MECH HOLD 11/24/2021 11/24/2021
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Plans missing from listed revised plans on submission form
BADMIN COMPLETE 04/20/2021 04/20/2021
Note: Released By: BARBIE BEMBRY - - BUILDINGDIVISION@PALMCOASTGOV.COM
PLUM COMPLETE 03/30/2021 04/12/2021
Note: Released By: JPI
BLD COMPLETE 02/16/2021 02/19/2021
Note: Released By: JPI
PLUM HOLD 02/16/2021 02/19/2021
Note: Held By: JPI 1. Riser Diagram-Gravity, page P801, and 1st Level Plumbing-Gravity-Final Layout, page PS101.3, do not match. A few issues are as follows. Equipment in room 1-1400 Decontamination, per floor plan, are draining to 4” line from Cart wash drain line. Riser illustrates drains will connect to existing 4” line branched from existing 6” main drain line. In riser diagram the existing 4” line in the decontamination room ends in clean out. Not shown on floor plan. Plumbing to and near the Ultrasonic Cleaner, 11-960, does not match. Floor plan illustrates the 4” line running above ceiling branching off the 3” line with equipment not being serviced. Please review all final plumbing plans and match to riser diagrams. 2. Riser Diagram-Pressure is only for 1st Floor. Provide riser for second floor equipment as well.
BADMIN HOLD 02/16/2021 03/23/2021
Note: Held By: BARBIE BEMBRY - - BUILDINGDIVISION@PALMCOASTGOV.COM need to provide subcontractors prior to permit issuance.
BADMIN HOLD 01/21/2021 02/02/2021
Note: Held By: BBEMBRY will need to provide subcontractors prior to permit issuance.
BLD HOLD 01/21/2021 01/28/2021
Note: Held By: JPI 1. Index sheet states Page G502 is to contain U428 and U465 description. Only U465 given. Page G501 A type wall schedule only utilizes U465 wall. Is U465 the only wall used?
PLUM HOLD 01/21/2021 01/28/2021
Note: Held By: JPI 1. Riser diagrams page P801 not in set. Please provide. Still not provided. 2. Plumbing lines are running to and from second floor mechanical room from RO/DI equipment. Is floor ceiling assembly a rated assembly? No plans illustrating floor penetrations and protection. Still not provided.
ELEC COMPLETE 01/21/2021 01/22/2021
Note: Released By: JMUNSON
MECH COMPLETE 01/21/2021 01/22/2021
Note: Released By: CPISCITELLI
BADMIN HOLD 01/11/2021 01/11/2021
Note: Held By: BBEMBRY Need to provide all subcontractors.
BLD HOLD 12/30/2020 01/12/2021
Note: Held By: JPI 1. Provide door schedule. Page AE601 is a duplicate of AF601 the finish schedule page. Need to verify door ratings. 2. Index sheet states Page G502 is to contain U428 and U465 description. Only U465 given. Page G501 A type wall schedule only utilizes U465 wall. Is this correct? 3. Provide manufacturers cut sheets on all equipment.
DSD COMPLETE 12/30/2020 12/30/2020
Note: Released By: JGONZALEZ
ELEC COMPLETE 12/30/2020 01/12/2021
Note: Released By: JMUNSON
FI1 COMPLETE 12/30/2020 01/15/2021
Note: Released By: JBODEN FIRE PROTECTION SYSTEM REQUIRES A SEPARATE PERMIT
MECH COMPLETE 12/30/2020 01/12/2021
Note: Released By: CPISCITELLI
PLUM HOLD 12/30/2020 01/12/2021
Note: Held By: JPI 1. Riser diagrams page P801 is not in the plan set. Please provide. 2. Plumbing lines are running to and from second floor mechanical room from RO/DI equipment. Is floor ceiling assembly a rated assembly? No plans illustrating floor penetrations and protection.
UD1 COMPLETE 12/30/2020 01/04/2021
Note: Released By: CJOHNSON

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - MISC 32.50 ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤65.00 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤0.00 03/13/2023
PLAN REVIEW - REVISION ¤65.00 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
PLAN REVIEW - REVISION ¤32.50 03/13/2023
REINSPECTION - COMMERCIAL ¤60.00 03/13/2023
REINSPECTION - COMMERCIAL ¤60.00 03/13/2023
BUILDING DISCOUNT 100% (¤20,802.32) 10/14/2021
ELECTRIC FEE ¤1,299.94 10/14/2021
MECHANICAL FEE ¤1,299.94 10/14/2021
PLAN CHECK FEE ¤2,376.56 10/14/2021
PLUMBING FEE ¤1,299.94 10/14/2021
SITE PLAN 20 ¤20.00 10/14/2021
SURCHARGE FS 533.721 ¤2.00 10/14/2021
SURCHARGE - FS 468.631 ¤2.00 10/14/2021
ADMIN COMMERCIAL ¤60.00 10/14/2021
ADMINISTRATIVE - COMMERCIAL ¤60.00 10/14/2021
INSPECTION - COMMERCIAL ADD ¤14,465.94 10/14/2021
INSPECTION- ELECTRICAL ¤1,299.94 10/14/2021
INSPECTION - MECHANICAL ¤1,299.94 10/14/2021
INSPECTION - PLUMBING ¤1,299.94 10/14/2021
PLAN REVIEW - COMMERCIAL ¤2,376.56 10/14/2021
Fees Total Due: ¤0.00 Total Paid: ¤6,935.38