Permit #2021010775

Permit Details

Status: COED

Subdivision: 2311 - THE TRAILS
Job Phone: (386)671-2727
Location Address: 100 SIENNA TRL
Type: SDD - SUBDIVISION SITE DEVELOPMENT
Issue Date: 05/13/2021
NOC: RECORDED
Applicant name: JOSEPH GEORGE WEBER
Owner: ADJ TRAILS OF PALM COAST

Address

444 SEABREEZE BLVD STE 805

DAYTONA BEACH, FL 32118

Job Description: SITE WORK: THE TRAILS STAGE 1
Type: CN

Contractor

JD WEBER CONSTRUCTION CO.
Status Location Address State License Number Phone Fax
DECEASED

150 BUSINESS CENTER DRIVE

ORMOND BEACH, FL 32174

CUC025621 (Exp: 08/31/2026) (386)671-2727 (386)671-2471

Inspection History

Type Request Date Result Inspector
PERFORMANCE BOND ACCEPTANCE 08/05/2022 APPROVED DRAMIREZ
Note: Landscape Performance Bond Submitted.
UC-FINAL SITE INSPECTION 08/04/2022 APPROVED - AS NOTED DHANEY
Note: THIS IS A REINSPECTION Phase 1 is complete - OK. . Phase 2 is under bond - needs final asphalt lift and sign/pavement markings .
U - UTILITY COMMERCIAL FINAL 08/04/2022 APPROVED - AS NOTED DHANEY
Note: Phase 1 complete - OK. . Phase 2 not complete - under Bond. Needs final asphalt lift and sign/pavement markings .
ROW - FINAL INSPECTION 08/04/2022 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION -ok per Don -phase 1 NEED TO HAVE THE SITE PLAN WITH THE PERMIT SO WE COMPARE SITE PLAN TO THE FIELD
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 08/03/2022 APPROVED - AS NOTED DHANEY
Note: Phase 1 complete - OK. Phase 2 not complete, needs final asphalt lift - sign /pavement marking. [ under bond ]
ROW - FINAL INSPECTION 08/03/2022 Disapproved - NO FEE PFLANAGAN
Note: NEED TO HAVE THE SITE PLAN WITH THE PERMIT SO WE COMPARE SITE PLAN TO THE FIELD
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 08/03/2022 APPROVED - AS NOTED DRAMIREZ
Note: Landscape Bond Submitted.
LDSC- LANDSCAPE FINAL 08/03/2022 APPROVED - AS NOTED DRAMIREZ
Note: A performance bond was submitted.
MAINT BOND ACCEPTANCE (OFFICE) 08/01/2022 APPROVED DHANEY
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 08/01/2022 APPROVED DHANEY
IRRIGATION AFFIDAVIT 08/01/2022 APPROVED DHANEY
LDSC-IRRIGATION FINAL 08/01/2022 APPROVED DHANEY
Note: Irrigation Affidavit submitted.
UC- PRELIMINARY AS-BUILTS 07/28/2022 APPROVED DHANEY
UC-FINAL SITE INSPECTION 07/06/2022 CANCELLED BY APPLICANT DHANEY
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 07/06/2022 APPROVED FWILLIS
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Sidewalk at front entry (main) not connected to City sidewalk along Belle Terre Section of sidewalk with large gap in center of site close to Belle Terre, by FPL Transformer 7/6/22 - ITEMS CORRECTED
UC- PRELIMINARY AS-BUILTS 07/06/2022 CANCELLED BY APPLICANT DHANEY
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 06/27/2022 CANCELLED BY APPLICANT JHARDING
Note: THIS IS A REINSPECTION Sidewalk at front entry (main) not connected to City sidewalk along Belle Terre Section of sidewalk with large gap in center of site close to Belle Terre, by FPL Transformer
UC-SUBSTANTIAL WALK-THRU 06/27/2022 APPROVED JHARDING
U-PUMP STATION START-UP 06/21/2022 APPROVED JHARDING
Note: THIS IS A REINSPECTION Not ready
UROW-RETENT/DETENT STABILI 06/21/2022 APPROVED JHARDING
UROW -FINAL GRADE PRIOR SOD 06/21/2022 APPROVED JHARDING
UROW - FINAL DRAINAGE 06/21/2022 APPROVED JHARDING
UROW- CURBING & GUTTER 06/13/2022 APPROVED DHANEY
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 06/13/2022 APPROVED DHANEY
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 06/13/2022 APPROVED DHANEY
UC-CONSTRUCTION ENTRANCE 06/13/2022 APPROVED DHANEY
UC-ASPHALT PRE PLACEMENT 06/13/2022 APPROVED DHANEY
UC-DRAINAGE STRUCT PLACMNT 06/13/2022 APPROVED DHANEY
UC-DRAINAGE PIPE PLACEMENT/LAMPING 06/13/2022 APPROVED DHANEY
CURBING AND GUTTER 06/13/2022 APPROVED DCUSHING
CONSTRUCTION ENTRANCE 06/13/2022 APPROVED DCUSHING
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 06/13/2022 Disapproved - NO FEE DCUSHING
Note: Sidewalk at front entry (main) not connected to City sidewalk along Belle Terre Section of sidewalk with large gap in center of site close to Belle Terre, by FPL Transformer
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 06/13/2022 APPROVED DHANEY
U-SEWER FORCE MAIN INSTALL/TESTING 06/13/2022 APPROVED DHANEY
U-WATER SERVICE INSTALLATION 06/13/2022 APPROVED DHANEY
U-GRAVITY SEWER INSTALL/TESTING 06/13/2022 APPROVED DHANEY
U-WATER MAIN DISINFECTION 06/13/2022 APPROVED DHANEY
U-WATER MAIN DISINFECTION SAMPLING 06/13/2022 APPROVED DHANEY
U-PUMP STATION PRE-INSTALLATION 06/13/2022 APPROVED DHANEY
U-PUMP STATION START-UP 06/13/2022 CANCELLED BY APPLICANT DHANEY
Note: Not ready
SILT FENCE 05/27/2022 APPROVED JHARDING
SILT FENCE 05/26/2022 CANCELLED BY INSPECTOR RGROSS
Note: Wrong Inspector was scheduled. Should have went to a Site Inspector. Rescheduled by inspector to J.Harding for the next day.
PLAN - PRE-CON 386-986-3750 05/10/2021 APPROVED JHARDING

Review History

Department Status Date In Date Out
PLENG COMPLETE 04/07/2021 04/07/2021
Note: Released By: DENNIS LEAP - - DLEAP@PALMCOASTGOV.COM
PLLA COMPLETE 04/07/2021 04/08/2021
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM
UD1 COMPLETE 04/07/2021 04/13/2021
Note: Released By: CHRIS JOHNSON - - CJOHNSON@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN COMMERCIAL ¤60.00 05/13/2021
BUILDING DISCOUNT 100% (¤60.00) 05/13/2021
SITE INSPECTION ¤680.00 05/13/2021
SITE PLAN 20 ¤20.00 05/13/2021
Fees Total Due: ¤0.00 Total Paid: ¤700.00