Permit #2021020065

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7030-00180-0040
Total Square Footage: 420 sqft
Block: 00180
Subdivision: 2154 - SECTION 30-ROYAL PALMS
Job Phone: 386-447-0035
Location Address: 79 RAINTREE PL
Type: BA - BUILDING ADDITION
Issue Date: 02/23/2021
NOC: RECORDED
Applicant name: GARY W MCCAIN
Owner: AMARO ABILIO & ROSA H&W

Address

79 RAINTREE PLACE

PALM COAST, FL 32164

Lot: 0040
Contracted Stated Job Value: ¤50,000.00
Job Description: Room Addition & Screen Enclosure
Type: CN

Contractor

MCCAIN CONSTRUCTION LLC
Status Location Address State License Number Phone
ACTIVE

15 WEIDNER PLACE

PALM COAST, FL 32164

CBC1261573 (Exp: 08/31/2026) 386-447-0035

Sub Contractors

MISHA ROMANOVSKIY
Status Location Address State License Number Phone Fax
INACTIVE

77 PEBBLE BEACH DRIVE

PALM COAST, FL 32164

ER13015548 (Exp: 08/31/2024) 386-793-5553 386-961-4388
THOMAS A REGULA
Status Location Address State License Number Phone Fax
INACTIVE

11320 PHILLIPS PKWY DRIVE E

JACKSONVILLE, FL 32256

CMC1250075 (Exp: 08/31/2026) 904-278-0339 904-278-0366
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001

Inspection History

Type Request Date Result Inspector
U -UTILITY RESIDENTIAL FINAL 12/08/2021 FINAL APPROVED LFITZGERALD
BLD - BUILDING FINAL 07/21/2021 FINAL APPROVED TSTAUFFACHER
ROW - FINAL INSPECTION 07/20/2021 APPROVED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD
INSULATION 06/11/2021 APPROVED JWALKER
LATH/BRICK/ WATER BARRIER 06/04/2021 APPROVED MMESSER
ALL ROUGH 06/02/2021 APPROVED MMESSER
ROOF VALLEY & METAL 03/16/2021 APPROVED MMESSER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 03/12/2021 APPROVED MMESSER
FOUND SURVEY APPROVED (OFFICE) 03/09/2021 APPROVED TBAKER
FOOTER 03/03/2021 APPROVED MMESSER

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 03/08/2021 03/09/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US
ZON COMPLETE 03/08/2021 03/08/2021
Note: Released By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM
BADMIN HOLD 03/01/2021 03/01/2021
Note: Held By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM NAME NOTARIZED AT BOTTOM INCORRECT.
BADMIN COMPLETE 03/01/2021 03/01/2021
Note: Released By: SCOTT THOMAS - - STHOMAS@PALMCOASTGOV.COM
SW1 COMPLETE 02/22/2021 02/22/2021
Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM
MECH COMPLETE 02/16/2021 02/16/2021
Note: Released By: CPISCITELLI
ZON COMPLETE 02/16/2021 02/18/2021
Note: Released By: ELENS
BLD COMPLETE 02/16/2021 02/23/2021
Note: Released By: FRED REODICA - (386)986-4734 - FReodica@ci.palm-coast.fl.us
ELEC COMPLETE 02/16/2021 02/17/2021
Note: Released By: JMUNSON
BLD HOLD 02/01/2021 02/08/2021
Note: Held By: FREODICA 1. Provide floor plan for the following infomation for clarity per FBC 7th Ed.. Sec. 107.2.1. a. Identify the screen enclosure where composite roofing wiil be installed and where the building addition will be done as it appears (2) engineers of record are doing the job. b. Identify the use of proposed space - building addition. c.. Indicate the location of windows and door to be installed. 2. Provide product approval per F.S. 553.842. a. Soffits, FL 16453 for roof underlayment cannot be found on Approval Listing. FReodica -386-986-4734
ELEC HOLD 02/01/2021 02/02/2021
Note: Held By: JMUNSON Submit electrical drawing and scope of work
MECH HOLD 02/01/2021 02/02/2021
Note: Held By: CPISCITELLI Energy Calcs need to be signed by the builder below preparer.
PLUM CANCEL 02/01/2021 02/08/2021
SW1 HOLD 02/01/2021 02/02/2021
Note: Held By: KRUTH the shed is going to be in the utility easement refer to the informational packet attatched
ZON HOLD 02/01/2021 02/04/2021
Note: Held By: ELENS Please clearly indicate on the site plan and the elevation the proposed screen room and building addition with dimensions and setbacks. Please demonstrate that the exterior material and color of the addition will match the existing house
MECH HOLD 02/01/2021 02/02/2021
Note: Held By: CPISCITELLI The previous review was not correct. This is the correct review. 1.Energy Calcs need to be on the 2020 7th edition code cycle 2. Energy Calcs need to be signed by the builder

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN FEE ¤20.00 02/23/2021
BUILDING DISCOUNT 100% (¤440.00) 02/23/2021
ELECTRIC FEE ¤90.00 02/23/2021
MECHANICAL FEE ¤90.00 02/23/2021
PLAN CHECK FEE ¤40.00 02/23/2021
REMODEL/ADDITION/ACCES INSPECT ¤200.00 02/23/2021
SITE PLAN 20 ¤20.00 02/23/2021
SURCHARGE FS 533.721 ¤2.00 02/23/2021
SURCHARGE - FS 468.631 ¤2.00 02/23/2021
STORM WATER PERMIT FEES ¤80.00 02/23/2021
Fees Total Due: ¤0.00 Total Paid: ¤104.00