Permit #2021020444

Permit Details

Status: COED

Parcel Id: 07-11-31-7006-00040-0120
CONDITIONED SPACE: 2084 sqft
GARAGE: 675 sqft
OPENED PORCH (WITH ROOF) : 39 sqft
OPENED PORCH (WITH ROOF) : 578 sqft
Total Square Footage: 3376 sqft
Block: 00040
Subdivision: 2213 - SECTION 6-FLORIDA PARK
Job Phone: 386-447-4400
Location Address: 24 FLINTSTONE CT
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 03/04/2021
NOC: RECORDED
Applicant name: DAVID PAUL CROCKETT
Owner: PARKS, SCOTT & MARI

Address

36 FAIRHILL LN

PALM COAST, FL 32137

Lot: 0120
Contracted Stated Job Value: ¤355,300.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

SALTWATER HOMES INC
Status Location Address Mailing Address State License Number Phone Fax
DECEASED

138 PALM COAST PARKWAY

PALM COAST, FL 32137

SUITE 328

PALM COAST, FL 32137

RG0041345 (Exp: 08/31/2025) 386-447-4400 866-244-9639

Sub Contractors

WILLIAM FRANK DUDLEY JR.
Status Location Address State License Number Phone
ACTIVE

P.O. BOX 978

Bunnell, FL 32110

EC0003177 (Exp: 08/31/2026) (386)437-3068
SANTOS L HERNANDEZ
Status Location Address State License Number Phone Fax
ACTIVE

946 SHADDICK DRIVE

ORANGE CITY, FL 32763

CCC1328011 (Exp: 08/31/2026) 386-218-4942 386-218-4937
THOMAS A REGULA
Status Location Address State License Number Phone Fax
INACTIVE

11320 PHILLIPS PKWY DRIVE E

JACKSONVILLE, FL 32256

CMC1250075 (Exp: 08/31/2026) 904-278-0339 904-278-0366
DENNIS GENE GAINEY
Status Location Address State License Number Phone Fax
INACTIVE

P.O. BOX 1203

Bunnell, FL 32110

CFC046004 (Exp: 08/31/2026) (386) 437-5637 386-437-3012

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 06/16/2022 FINAL APPROVED AGAETANO
Note: THIS IS A REINSPECTION 1. Master bath GFCI has no power. 2. Microwave not installed. 3. Seal duct at AHU at ceiling. 4. AC equipment installed does not match the Energy Calcs. 5. Ceiling lights in guest bedrooms and master bedroom not working.
U-CROSS CONNECTION 06/13/2022 APPROVED DHANEY
BLD - BUILDING FINAL 06/13/2022 Disapproved - NO FEE AGAETANO
Note: 1. Master bath GFCI has no power. 2. Microwave not installed. 3. Seal duct at AHU at ceiling. 4. AC equipment installed does not match the Energy Calcs. 5. Ceiling lights in guest bedrooms and master bedroom not working.
U -UTILITY RESIDENTIAL FINAL 06/09/2022 FINAL APPROVED DHANEY
ROW - DRAINAGE 06/08/2022 APPROVED - AS NOTED EMADISON
Note: ** EVERYTHING LOOKS GOOD AT THE TIME OF THE INSPECTION Inspect for swlae blockage W/O #25389 12/15/21 - Swale is completely blocked. Next Inspection. 12/17/21. Contacted builder to let him know we would be back Friday. Said He would contact Darrell Cone for corrections.
ROW - STORMWATER FINAL 06/08/2022 APPROVED - AS NOTED EMADISON
Note: ** AT THE TIME OF THE INSPECTION EVERYTHING LOOKS GOOD
ROW - FINAL APRON (AFTER POUR) 06/08/2022 APPROVED EMADISON
ROW FIELD SURVEY /GRADING CERTIFICATION 06/08/2022 APPROVED EMADISON
FINAL SURVEY (OFFICE USE ONLY) 06/08/2022 APPROVED EMADISON
ROW- PAVER RESTRAINTS 04/20/2022 APPROVED RGROSS
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION call in for the paver restraints after the restraints are poured and the matierial is compacted
ROW- PAVER RESTRAINTS 04/18/2022 CANCELLED BY APPLICANT RGROSS
Note: THIS IS A REINSPECTION call in for the paver restraints after the restraints are poured and the matierial is compacted
ELECTRIC - EARLY POWER 03/28/2022 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 1:15
ROW- PRE-APRON (PRE-POUR) 03/15/2022 APPROVED - AS NOTED KRUTH
Note: pipe is good at the time of the inspection It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
ROW- PAVER RESTRAINTS 03/15/2022 PARTIALLY APPROVED KRUTH
Note: call in for the paver restraints after the restraints are poured and the matierial is compacted
LATH/BRICK/ WATER BARRIER 01/14/2022 APPROVED AGAETANO
INSULATION 01/04/2022 APPROVED AGAETANO
ALL ROUGH 12/20/2021 APPROVED AGAETANO
ROW - DRAINAGE 12/17/2021 APPROVED - AS NOTED KRUTH
Note: THIS IS A REINSPECTION Inspect for swlae blockage W/O #25389 12/15/21 - Swale is completely blocked. Next Inspection. 12/17/21 corrections made
ROW - DRAINAGE 12/15/2021 Disapproved -FEE REQUIRED RGROSS
Note: Inspect for swlae blockage W/O #25389 12/15/21 - Swale is completely blocked. Next Inspection. 12/17/21. Contacted builder to let him know we would be back Friday. Said He would contact Darrell Cone for corrections.
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/12/2021 CANCELLED BY APPLICANT WEB
ROOF SHEATHING / BRACES/TIES/DOWN CELL 11/12/2021 APPROVED FWILLIS
ROOF VALLEY & METAL 11/12/2021 APPROVED FWILLIS
ELECTRIC-TUG 09/16/2021 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 12:00
TIE BEAM / LINTEL 09/10/2021 APPROVED DCUSHING
ELEV CERT-FOUNDATION APPROVAL 08/18/2021 APPROVED JMYERS
FOUND SURVEY APPROVED (OFFICE) 08/18/2021 APPROVED TBAKER
MONOLITHIC SLAB 07/16/2021 APPROVED WMILLER
Note: THIS IS A REINSPECTION
MONOLITHIC SLAB 07/15/2021 CANCELLED BY APPLICANT MMESSER
PLUMBING 1ST ROUGH UNDERGROUND 07/09/2021 APPROVED JGIBSON
GRAVITY SEWER TEST 07/09/2021 APPROVED JGIBSON
U - SEWER TIE IN 07/09/2021 APPROVED JGIBSON
WATER METER INSTALLATION REQUEST 05/20/2021 APPROVED CSTONE

Review History

Department Status Date In Date Out
BADMIN INFORMATION 06/23/2022 06/23/2022
Note: Marked INFORMATION By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM WE NEED THE CERIFICATE OF COMPIANCE FOR TERMITE PROTECTION THIS A TREATMENT DOCUMENT NOT CERTIFICATE
PLFM COMPLETE 06/07/2022 06/08/2022
Note: Released By: JORDAN MYERS, C.F.M - (386)986-2320 - JMYERS@PALMCOASTGOV.COM The Final elevation certificate has been approved.
BADMIN INFORMATION 05/16/2022 05/16/2022
Note: Marked INFORMATION By: MARGA DEFREITAS - - MDEFREITAS@PALMCOASTGOV.COM BLOWER DOOR TEST HAS TO BE 2020 CODE 7 EDTION THIS ONE IS 2017 6TH EDITION.
ZON COMPLETE 03/11/2022 03/11/2022
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
ENGIN1 COMPLETE 08/18/2021 08/18/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
PLFM COMPLETE 08/18/2021 08/18/2021
Note: Released By: JORDAN MYERS, C.F.M - (904)562-0045 - JMYERS@PALMCOASTGOV.COM The Foundation elevation certificate has been approved. Please provide Final prior to receiving CO.
ZON COMPLETE 08/18/2021 08/18/2021
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ELEC COMPLETE 03/01/2021 03/01/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ZON COMPLETE 03/01/2021 03/01/2021
Note: Released By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM
MECH COMPLETE 02/17/2021 02/17/2021
Note: Released By: CPISCITELLI
ELEC HOLD 02/17/2021 02/17/2021
Note: Held By: JMUNSON Electric load calcs do match the square footage of the house.
ZON HOLD 02/17/2021 02/18/2021
Note: Held By: AMOBLEY No new landscape plan submitted with correction... Additional foundation plantings required along rear because house backs to a canal Additional foundation planting required along side to total four wrapping corners
PLFM COMPLETE 02/17/2021 02/17/2021
Note: Released By: JMYERS The Construction elevation certificate has been accepted. Please provide Foundation and Final prior to receiving CO.
BLD COMPLETE 02/17/2021 02/19/2021
Note: Released By: JPI
PLFM HOLD 02/10/2021 02/10/2021
Note: Held By: JMYERS According to the Site Plan provided, the structure will be inside of the Special Flood Hazard Area. Please provide elevation certificates at construction, foundation, and final.
BLD HOLD 02/08/2021 02/11/2021
Note: Held By: JPI 1. Siding, FL 24161 and roof tiles, FL 601, have not been approved for 2020 code cycle. Please select other products. 2. Step down from dwelling to garage is not illustrated on foundation plan or sheet 5 (structural). Please identify. 3. Rear porch section/wall detail not provided on page 5. 4. Provide a mixed construction detail of wood framing to block with attachments clearly identified. 5. Provide design loads, per R301. 6. Provide typical interior wall detail. 7. Product approval missing the following item: mullions.
CUSVC COMPLETE 02/08/2021 02/16/2021
Note: Released By: HHAND
ELEC HOLD 02/08/2021 02/09/2021
Note: Held By: JMUNSON 1. Electric load calcs do not match the square footage of the house. 2. Need smoke alarm outside of bedroom 2 and 3. FRC 2020 314.3 & 315.1
ENGIN1 COMPLETE 02/08/2021 02/08/2021
Note: Released By: TBAKER
LOCATE COMPLETE 02/08/2021 02/10/2021
Note: Released By: CSTONE
MECH HOLD 02/08/2021 02/09/2021
Note: Held By: CPISCITELLI Energy Calcs need to be signed by the builder
PLUM COMPLETE 02/08/2021 02/11/2021
Note: Released By: JPI
SW1 COMPLETE 02/08/2021 02/16/2021
Note: Released By: KRUTH
ZON HOLD 02/08/2021 02/10/2021
Note: Held By: AMOBLEY Additional foundation plantings required along rear because house backs to a canal Additional foundation planting required along side to total four wrapping corners Site plan/survey does not specify the apron being concrete or pavers Right of way agreement signed by all owners and notarized will be required if paver driveway will be going into the right of way.
SWALE COMPLETE 02/08/2021 05/04/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
SW ENG - INSPECTION 20 ¤20.00 06/16/2022
SW ENG - INSPECTION 20 ¤20.00 06/16/2022
SW ENG - INSPECTION 20 ¤20.00 06/16/2022
STORM WATER PERMIT FEES ¤80.00 03/04/2021
3% TRANS IMPACT FEE CREDIT (¤51.54) 03/04/2021
SEWER INSPECTION ¤25.00 03/04/2021
SEWER CAPITAL FACILITY ¤4,664.55 03/04/2021
WATER CAPITAL FACILITY FEE ¤3,424.45 03/04/2021
METER - DEPOSIT ¤60.00 03/04/2021
WATER- TURN ON ¤25.00 03/04/2021
ADMIN FEE ¤20.00 03/04/2021
CONNECTION FEES ¤1,017.83 03/04/2021
BUILDING DISCOUNT 100% (¤1,695.20) 03/04/2021
ELECTRIC FEE ¤273.60 03/04/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 03/04/2021
IMPACT FEE FIRE ¤367.00 03/04/2021
IMPACT FEE PARKS ¤1,199.12 03/04/2021
IMPACT FEE SCHOOL ¤3,600.00 03/04/2021
IMPACT FEE TRANSPORTATION ¤1,718.00 03/04/2021
MECHANICAL FEE ¤273.60 03/04/2021
WATER -IRRIGATION INSPECTION ¤25.00 03/04/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 03/04/2021
PLAN CHECK FEE ¤142.40 03/04/2021
PLUMBING FEE ¤273.60 03/04/2021
NEW RESIDENTIAL INSPECTIONS ¤712.00 03/04/2021
SITE PLAN 20 ¤20.00 03/04/2021
SURCHARGE FS 533.721 ¤2.00 03/04/2021
SURCHARGE - FS 468.631 ¤2.00 03/04/2021
Fees Total Due: ¤0.00 Total Paid: ¤16,191.43