I want to search for...
Permit #2021031442
Permit Details
Status: FINAL
| Parcel Id: 07-11-31-7017-00010-1440 |
| Block: 00010 |
| Subdivision: 2129 - SECTION 17-BELLE TERRE |
| Job Phone: 786-512-4421 |
| Location Address: 38 BOULDER ROCK DR |
| Type: DR - DRIVEWAY |
| Issue Date: 03/31/2021 |
| NOC: RECORDED |
| Applicant name: ABEL MENENDEZ |
| Owner: TEMIR, ROZALIA |
|
Address 38 BOULDER ROCK DRIVE PALM COAST, FL 32137 |
| Lot: 1440 |
| Contracted Stated Job Value: ¤10,000.00 |
| Job Description: CONCRETE DRIVEWAY & CIRCULAR |
| Type: CN |
Contractor
ROYAL TILE & PAVERS INC
| Status | Location Address | Phone |
| ACTIVE |
69 FLEETWOOD DR PALM COAST, FL 32137 |
786-512-4421 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - FINAL APRON (AFTER POUR) | 05/27/2021 | APPROVED | RGROSS |
| U -UTILITY RESIDENTIAL FINAL | 05/27/2021 | FINAL APPROVED | DHANEY |
| ROW - FINAL INSPECTION | 05/25/2021 | APPROVED | KRUTH |
| ROW- PRE-APRON (PRE-POUR) | 04/20/2021 | APPROVED | KRUTH |
| Note: THIS IS A REINSPECTION pipe on the left side was 2 tenths high out of tolerance and water under both pipes corrections made good to pour | |||
| ROW- PRE-APRON (PRE-POUR) | 04/19/2021 | Disapproved -FEE REQUIRED | KRUTH |
| Note: pipe on the left side was 2 tenths high out of tolerance and water under both pipes |
Review History
| Department | Status | Date In | Date Out |
| ZON | HOLD | 03/29/2021 | 03/29/2021 |
| Note: Held By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM Please note that walkways cannot exceed 6' in width. You are proposing a 8'7" area leading to the front door, which is not allowed as it would technically become a driveway to the front door - which isn't allowed by code. Also, you are adding a walkway all around the front of the house - this home is required to have a minimum of 8 foundation plantings in the front of the home and 4 along each side - to be planted 2-8' from the foundation. | |||
| ZON | COMPLETE | 03/29/2021 | 03/29/2021 |
| Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/23/2021 | 03/25/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US | |||
| UTL | COMPLETE | 03/23/2021 | 03/26/2021 |
| Note: Released By: LARRY FITZGERALD - - LFITZGERALD@CI.PALM-COAST.FL.US | |||
| ZON | HOLD | 03/23/2021 | 03/23/2021 |
| Note: Held By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM Site plan submitted must be clear. There are many lines/dimensions and it's unclear the scope of work. Please clearly demonstrate the proposed work for this permit. Include all dimensions and that the circular driveway at its widest section does not exceed the 18' maximim width for circular driveways. Also please provide the setback from the front property line to the bottom of the arc of the circular portion. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| STORMWATER REINSPECTION FEE | ¤40.00 | 05/26/2021 |
| ADMIN FEE | ¤20.00 | 03/31/2021 |
| BUILDING DISCOUNT 100% | (¤20.00) | 03/31/2021 |
| SITE PLAN 20 | ¤20.00 | 03/31/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 03/31/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 03/31/2021 |
| STORM WATER PERMIT FEES | ¤40.00 | 03/31/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤104.00 |