Permit #2021040236

Permit Details

Status: FINAL

Parcel Id: 07-11-31-7033-00390-0230
Total Square Footage: 300 sqft
Block: 00390
Subdivision: 2184 - SECTION 33-ROYAL PALMS
Job Phone: (386)451-0113
Location Address: 19 RENWORTH LN
Type: BA - BUILDING ADDITION
Issue Date: 06/02/2021
NOC: Unknown
Applicant name: ANDREA L JONES
Owner: BENTLEY, THOMAS

Address

19 RENWORTH LANE

PALM COAST, FL 32164

Lot: 0230
Contracted Stated Job Value: ¤2,400.00
Job Description: 12x25 composite roof on existing slab
Type: CN

Contractor

ALUMINUM CREATIONS, CORP.
Status Location Address State License Number Phone Fax
INACTIVE

155 DAWSON BROWN RD.

DE LEON SPRINGS, FL 32130

SCC131149810 (Exp: 08/31/2026) 850-640-9350 866-344-3908

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 08/05/2021 FINAL APPROVED JWALKER
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION 3X3 POST IS ATTACHED TO BRACKET WITH (2) 3/8" X 3 1/2" CARRIAGE BOLTS Only 1 carriage bolt used per post. Install 2 per or submitt engineering revision. The gutter used is not the specified gutter on drawing. Leaving the FOAM ends of the insulated panels exposed. The anchors are to be 24" o.c. at gutter use correct gutter and proper spacing of anchors 3" C CHANNEL IS ATTACHED TO BLOCK STRUCTURE WITH 2-1/4" X 1/4" TAPCONS 6" FROM ENDS 24" O.C. & TO 3" INSULATED ROOF WITH (6) #10 1" PER SIDE Not able to view how the 3" channel was connected to home due to concelment. 7/20/21 The ends of the panels where the foam was exposed has not been properly capped as per the drawings. A drip edge was used which is still allowing water intrusion to the foam at the bottom of the panel Remove gutters and use capping that seal ends completely. Or provide manufactures worksheet showing drip edge installation as installed.
BLD - BUILDING FINAL 07/20/2021 Disapproved -FEE REQUIRED JWALKER
Note: THIS IS A REINSPECTION 3X3 POST IS ATTACHED TO BRACKET WITH (2) 3/8" X 3 1/2" CARRIAGE BOLTS Only 1 carriage bolt used per post. Install 2 per or submitt engineering revision. The gutter used is not the specified gutter on drawing. Leaving the FOAM ends of the insulated panels exposed. The anchors are to be 24" o.c. at gutter use correct gutter and proper spacing of anchors 3" C CHANNEL IS ATTACHED TO BLOCK STRUCTURE WITH 2-1/4" X 1/4" TAPCONS 6" FROM ENDS 24" O.C. & TO 3" INSULATED ROOF WITH (6) #10 1" PER SIDE Not able to view how the 3" channel was connected to home due to concelment. 7/20/21 The ends of the panels where the foam was exposed has not been properly capped as per the drawings. A drip edge was used which is still allowing water intrusion to the foam at the bottom of the panel Remove gutters and use capping that seal ends completely. Or provide manufactures worksheet showing drip edge installation as installed.
BLD - BUILDING FINAL 06/11/2021 Disapproved -FEE REQUIRED JWALKER
Note: 3X3 POST IS ATTACHED TO BRACKET WITH (2) 3/8" X 3 1/2" CARRIAGE BOLTS Only 1 carriage bolt used per post. Install 2 per or submitt engineering revision. The gutter used is not the specified gutter on drawing. Leaving the FOAM ends of the insulated panels exposed. The anchors are to be 24" o.c. at gutter use correct gutter and proper spacing of anchors 3" C CHANNEL IS ATTACHED TO BLOCK STRUCTURE WITH 2-1/4" X 1/4" TAPCONS 6" FROM ENDS 24" O.C. & TO 3" INSULATED ROOF WITH (6) #10 1" PER SIDE Not able to view how the 3" channel was connected to home due to concelment.
ROW - STORMWATER FINAL 06/10/2021 APPROVED RGROSS
U -UTILITY RESIDENTIAL FINAL 06/10/2021 FINAL APPROVED LFITZGERALD

Review History

Department Status Date In Date Out
BLD COMPLETE 07/07/2021 07/13/2021
Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM
BLD COMPLETE 04/16/2021 04/23/2021
Note: Released By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM
BLD HOLD 04/06/2021 04/12/2021
Note: Held By: FRED REODICA - (386)986-4734 - FREODICA@PALMCOASTGOV.COM 1. Provide product approval of composite roofing material per F. S. 553.84. 2. Provide size of footer, and dimensions on screen enclosure plan to coodinate with site plan for clarity per FBC 7th Ed. Sec. 107.2.1.
SW1 COMPLETE 04/06/2021 04/12/2021
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ZON HOLD 04/06/2021 04/06/2021
Note: Held By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM Provide setback from right side of proposed improvement to property line. It appears to extend past the side of the home.
ZON COMPLETE 04/06/2021 04/06/2021
Note: Released By: TRACEY DOAK - (386)986-2473 - TDOAK@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
REINSPECTION FEE ¤40.00 08/04/2021
REINSPECTION FEE ¤40.00 06/25/2021
ADMIN FEE ¤20.00 06/02/2021
BUILDING DISCOUNT 100% (¤100.00) 06/02/2021
PLAN CHECK FEE ¤40.00 06/02/2021
REMODEL/ADDITION/ACCES INSPECT ¤40.00 06/02/2021
SITE PLAN 20 ¤20.00 06/02/2021
SURCHARGE FS 533.721 ¤2.00 06/02/2021
SURCHARGE - FS 468.631 ¤2.00 06/02/2021
STORM WATER PERMIT FEES ¤80.00 06/02/2021
Fees Total Due: ¤0.00 Total Paid: ¤184.00