I want to search for...
Permit #2021040301
Permit Details
Status: CANCEL
| Parcel Id: 35-11-31-4075-00000-0830 |
| CONDITIONED SPACE: 936 sqft |
| CONDITIONED SPACE: 1929 sqft |
| GARAGE: 859 sqft |
| OPENED PORCH (WITH ROOF) : 213 sqft |
| OPENED PORCH (WITH ROOF) : 33 sqft |
| Total Square Footage: 3970 sqft |
| Block: 00000 |
| Subdivision: 2296 - MARINA DEL PALMA SUBDIVISION |
| Job Phone: 386-947-4481 |
| Location Address: 31 DEL PALMA DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 04/27/2021 |
| NOC: RECORDED |
| Applicant name: ERIC CHRISTOPHER OLSEN |
| Owner: PETYO ROBERT A & JOYCE C FERFECKI H&W |
|
Address 53 NAUTILUS DR FLAGLER BEACH, FL 32136 |
| Lot: 0830 |
| Contracted Stated Job Value: ¤425,000.00 |
| Job Description: single family residence. |
| Type: CN |
Contractor
OLSEN CUSTOM HOMES AND CONSULTING INC
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
CGC1508852 (Exp: 08/31/2026) | 386-947-4481 | (386)947-4484 |
Sub Contractors
BERT S MCLAUGHLIN
| Status | Location Address | State License Number | Phone |
| ACTIVE |
131 MAGNOLIA AVE DAYTONA BEACH, FL 32114 |
EC13006455 (Exp: 08/31/2026) | 386-265-2687 |
MARK A RUGGIERO
| Status | Location Address | State License Number | Phone |
| INACTIVE |
411 6TH STREET HOLLY HILL , FL 32117 |
01612 (Exp: 07/23/2023) | 386-252-5555 |
JAMES WILLIAM ANSORGE
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
5307 COUNTY ROAD 304 BUNNELL, FL 32110 |
CFC1426785 (Exp: 08/31/2026) | 386-233-5287 | 386-492-1830 |
SANTOS L HERNANDEZ
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
946 SHADDICK DRIVE ORANGE CITY, FL 32763 |
CCC1328011 (Exp: 08/31/2026) | 386-218-4942 | 386-218-4937 |
Inspection History
| Type | Request Date | Result | Inspector |
| PROJECT STATUS (OFFICE USE) | 06/17/2021 | PARTIALLY APPROVED | RGROSS |
| Note: Please verify if any work has commenced and take a picture of the lot. 6/17/21 - If this is 31. Had to count from exitsisting construction at 41. This is Lot 83 per post. Lot cleared by no construction started. No doc box to verify address. Photo's attached. | |||
| WATER METER INSTALLATION REQUEST | 05/18/2021 | APPROVED | CSTONE |
| U-CROSS CONNECTION | |||
| ROW- PRE-APRON (PRE-POUR) | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| U - SEWER TIE IN | |||
| ROW - STORMWATER FINAL | |||
| U -UTILITY RESIDENTIAL FINAL | |||
| FOUND SURVEY APPROVED (OFFICE) | |||
| FINAL SURVEY (OFFICE USE ONLY) | |||
| PROJECT STATUS (OFFICE USE) | |||
| Note: THIS IS A REINSPECTION Please verify if any work has commenced and take a picture of the lot. 6/17/21 - If this is 31. Had to count from exitsisting construction at 41. This is Lot 83 per post. Lot cleared by no construction started. No doc box to verify address. Photo's attached. | |||
| PLUMBING 1ST ROUGH UNDERGROUND | |||
| GRAVITY SEWER TEST | |||
| ELECTRIC - EARLY POWER | |||
| MONOLITHIC SLAB | |||
| LATH/BRICK/ WATER BARRIER | |||
| TIE BEAM / LINTEL | |||
| ALL ROUGH | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | |||
| ROOF VALLEY & METAL | |||
| INSULATION | |||
| BLD - BUILDING FINAL |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 04/26/2021 | 04/26/2021 |
| Note: Released By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM | |||
| ZON | HOLD | 04/22/2021 | 04/22/2021 |
| Note: Held By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM Concrete pad is still located in the 5ft easement on right side. | |||
| ZON | HOLD | 04/21/2021 | 04/22/2021 |
| Note: Held By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM Concrete pad is still located in the 5ft easement on right side. Landscape plan does not match site plan. The locations of the pads do not match. | |||
| SW1 | COMPLETE | 04/21/2021 | 04/22/2021 |
| Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 04/14/2021 | 04/21/2021 |
| Note: Held By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM All corrections that needed to be made were not done so go over the stormwater checklist and fix any unchecked box. | |||
| ZON | HOLD | 04/14/2021 | 04/14/2021 |
| Note: Held By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM Concrete pad is still located in the 5ft easement on right side. Please provide a new landscape plan showing the location changes | |||
| URB | COMPLETE | 04/13/2021 | 04/13/2021 |
| Note: Released By: JOHN BEAUDET - (386)986-2456 - | |||
| CUSVC | COMPLETE | 04/06/2021 | 04/07/2021 |
| Note: Released By: HALEIGH HAND - - | |||
| ENGIN1 | COMPLETE | 04/06/2021 | 04/07/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@CI.PALM-COAST.FL.US | |||
| LOCATE | COMPLETE | 04/06/2021 | 04/12/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| SW1 | HOLD | 04/06/2021 | 04/12/2021 |
| Note: Held By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM See highlighted items on Checklist in the attachments. | |||
| ZON | HOLD | 04/06/2021 | 04/13/2021 |
| Note: Held By: ALISHA MOBLEY - (386)986-4733 - AMOBLEY@PALMCOASTGOV.COM Lot square footage appears to be missing on site plan This lot has four Flood panel numbers. They should all be listed on survey/site plan Please provide the material being used for driveway on site plan Please provide the width and material of front entry walkway on site plan There is a special 5' drainage easement on the right side of this lot. AC and concrete pad are located in this easement. This easement is not the typical 5' that the mechanical pads are allowed in. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| BUILDING DISCOUNT 100% | (¤125.00) | 04/27/2021 |
| IMPACT FEE FIRE | ¤367.00 | 04/27/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 04/27/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 04/27/2021 |
| IMPACT FEE TRANSPORTATION | ¤3,139.00 | 04/27/2021 |
| PERMIT FEE | ¤125.00 | 04/27/2021 |
| SITE PLAN 20 | ¤20.00 | 04/27/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 04/27/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 04/27/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 04/27/2021 |
| SEWER INSPECTION | ¤25.00 | 04/15/2021 |
| SEWER CAPITAL FACILITY | ¤2,432.74 | 04/15/2021 |
| WATER CAPITAL FACILITY FEE | ¤2,274.74 | 04/15/2021 |
| METER - DEPOSIT | ¤60.00 | 04/15/2021 |
| WATER-METER | ¤441.07 | 04/15/2021 |
| CONNECTION FEES | ¤25.00 | 04/15/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤13,667.67 |