I want to search for...

Permit #2021041353

Permit Details

Status: COED

Parcel Id: 07-11-31-7013-00030-0110
CONDITIONED SPACE: 1449 sqft
GARAGE: 418 sqft
OPENED PORCH (WITH ROOF) : 84 sqft
Total Square Footage: 1951 sqft
Block: 00030
Subdivision: 2192 - SECTION 13-BELLE TERRE
Job Phone: 321-249-3126
Location Address: 19 BRACKEN LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 05/05/2021
NOC: RECORDED
Applicant name: MOREY C DOYLE
Owner: WJHFL LLC D/B/A WJH LLC A DELAWARE

Address

3091 GOVERNORS LAKE DRIVE SUITE 300

NORCROSS, GA 30071

Lot: 0110
Contracted Stated Job Value: ¤101,430.00
Job Description: Single Family Residence
Type: CN

Contractor

WADE JURNEY HOMES
Status Location Address State License Number Phone
CANCEL

3091 GOVERNORS LAKE DRIVE

NORCROSS, GA 30071

CGC1517458 (Exp: 08/31/2022) 321-249-3126

Sub Contractors

EDWIN R INSALACO
Status Location Address Mailing Address State License Number Phone Fax
CANCEL

3191 MAGUIRE BLVD

ORLANDO, FL 32803

STE 200

ORLANDO, FL 32803

EC13001310 (Exp: 08/31/2024) 321-441-7990 407-426-9741
MICHAEL LEE RAFFENSBERGER
Status Location Address State License Number Phone Fax
CANCEL

7725 SANDSCOVE CT

WINTER PARK, FL 32792

CAC1819723 (Exp: 08/31/2024) 407-629-6920 407-629-9307
DANIEL P GREGOIRE
Status Location Address State License Number Phone
INACTIVE

64 W. CENTRAL AVENUE

LAKE WALES, FL 33853

CFC057378 (Exp: 08/31/2024) (863)696-3737
IAN ALAN BRENNER
Status Location Address Mailing Address State License Number Phone
ACTIVE

691 GARDEN COMMERCE PKWY

WINTER GARDEN, FL 34787

STE 170

WINTER GARDEN, FL 34787

CCC1331270 (Exp: 08/31/2026) 407-649-1333

Inspection History

Type Request Date Result Inspector
ROW - FINAL APRON (AFTER POUR) 10/28/2021 APPROVED KRUTH
Note: THIS IS A REINSPECTION the expansion cuts are not in the drive way sod is not around the driveway for sediment erosion corrections made
ROW FIELD SURVEY /GRADING CERTIFICATION 10/28/2021 APPROVED - AS NOTED KRUTH
Note: left side swale is too high at the property line lower the swale sod is to be lower than the edge of the road and it as 3 tenths higher on the left side sod is not finished corrections made 10/28
ROW - STORMWATER FINAL 10/28/2021 APPROVED KRUTH
Note: THIS IS A REINSPECTION these inspections are to be scheduled when work is completed
ROW FIELD SURVEY /GRADING CERTIFICATION 10/27/2021 Disapproved -FEE REQUIRED KRUTH
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION left side swale is too high at the property line lower the swale sod is to be lower than the edge of the road and it as 3 tenths higher on the left side sod is not finished
U -UTILITY RESIDENTIAL FINAL 10/27/2021 FINAL APPROVED DHANEY
Note: THIS IS A REINSPECTION Can not locate sewer clean out at street arera . Corrections made.
ROW FIELD SURVEY /GRADING CERTIFICATION 10/26/2021 Disapproved -FEE REQUIRED KRUTH
Note: THIS IS A REINSPECTION left side swale is too high at the property line lower the swale sod is to be lower than the edge of the road and it as 3 tenths higher on the left side
ROW - FINAL APRON (AFTER POUR) 10/26/2021 Disapproved - NO FEE KRUTH
Note: the expansion cuts are not in the drive way sod is not around the driveway for sediment erosion
U -UTILITY RESIDENTIAL FINAL 10/26/2021 Disapproved - NO FEE DHANEY
Note: Can not locate sewer clean out at street arera .
ROW - STORMWATER FINAL 10/26/2021 Disapproved - NO FEE KRUTH
Note: these inspections are to be scheduled when work is completed
BLD - BUILDING FINAL 10/26/2021 Approval - Private Provider PPROVIDER
FINAL SURVEY (OFFICE USE ONLY) 10/25/2021 APPROVED KRUTH
ROW FIELD SURVEY /GRADING CERTIFICATION 10/25/2021 Disapproved -FEE REQUIRED KRUTH
Note: left side swale is too high at the property line lower the swale sod is to be lower than the edge of the road and it as 3 tenths higher on the left side
ROW- PRE-APRON (PRE-POUR) 10/12/2021 APPROVED - AS NOTED KRUTH
Note: the pipe is bent really bad on the left side this needs to be fixed before you pour pipe is good at the time of the inspection It is the BUILDER'S RESPONSIBILITY: to recheck elevations and pipe size, to insure that an obstruction does not exist upstream and or downstream, that the culvert pipe is set to and or follows the swale plan, form the driveway to the approved site plan and follow the approved driveway detail sheet provided by the City of Palm Coast. PRIOR to placement of concrete.
GRAVITY SEWER TEST 10/11/2021 Approval - Private Provider PPROVIDER
U - SEWER TIE IN 10/07/2021 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 10/06/2021 APPROVED - AS NOTED CSTONE
Note: already installed
LATH/BRICK/ WATER BARRIER 10/05/2021 Approval - Private Provider PPROVIDER
U-CROSS CONNECTION 10/04/2021 APPROVED DHANEY
FOUND SURVEY APPROVED (OFFICE) 10/04/2021 APPROVED TBAKER
ELECTRIC - EARLY POWER 09/20/2021 Approval - Private Provider PPROVIDER
INSULATION 09/17/2021 Approval - Private Provider PPROVIDER
ALL ROUGH 08/11/2021 Approval - Private Provider PPROVIDER
ROOF VALLEY & METAL 07/26/2021 Approval - Private Provider PPROVIDER
WALL SHEATHING 07/21/2021 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 07/21/2021 Approval - Private Provider PPROVIDER
TIE BEAM / LINTEL 07/08/2021 Approval - Private Provider PPROVIDER
MONOLITHIC SLAB 06/30/2021 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH UNDERGROUND 06/28/2021 Approval - Private Provider PPROVIDER

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 10/01/2021 10/04/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 10/01/2021 10/01/2021
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
CUSVC COMPLETE 05/01/2021 05/03/2021
Note: Released By: HALEIGH HAND - -
ZON COMPLETE 05/01/2021 05/04/2021
Note: Released By: ESTELLE LENS - (386)986-3751 -
LOCATE COMPLETE 05/01/2021 05/03/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/01/2021 05/03/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 COMPLETE 05/01/2021 05/05/2021
Note: Released By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM
BLD COMPLETE 04/23/2021 04/29/2021
Note: Released By: JPI
CUSVC HOLD 04/23/2021 04/27/2021
Note: Held By: HALEIGH HAND - - Please correct the utility application to reflect the correct parcel number.
ELEC COMPLETE 04/23/2021 04/26/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 04/23/2021 04/23/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 04/23/2021 04/28/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 04/23/2021 04/26/2021
Note: Released By: CHRIS PISCITELLI - - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 04/23/2021 04/29/2021
Note: Released By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM
ZON HOLD 04/23/2021 04/28/2021
Note: Held By: ESTELLE LENS - (386)986-2655 - Need to correct FEMA map panel number (...0136E)
SWALE COMPLETE 04/23/2021 05/05/2021
Note: Released By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
SW ENG - FIELD SURVEY INSPECT ¤20.00 10/27/2021
SW ENG - FIELD SURVEY INSPECT ¤20.00 10/26/2021
SW ENG - FIELD SURVEY INSPECT ¤20.00 10/26/2021
SW ENG - FIELD SURVEY INSPECT ¤20.00 10/26/2021
STORM WATER PERMIT FEES ¤80.00 05/05/2021
3% TRANS IMPACT FEE CREDIT (¤51.54) 05/05/2021
SEWER INSPECTION ¤25.00 05/05/2021
SEWER CAPITAL FACILITY ¤4,664.55 05/05/2021
WATER CAPITAL FACILITY FEE ¤3,424.45 05/05/2021
METER - DEPOSIT ¤60.00 05/05/2021
WATER- TURN ON ¤25.00 05/05/2021
ADMIN FEE ¤20.00 05/05/2021
CONNECTION FEES ¤1,017.83 05/05/2021
BUILDING DISCOUNT 100% (¤960.20) 05/05/2021
ELECTRIC FEE ¤168.60 05/05/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 05/05/2021
IMPACT FEE FIRE ¤367.00 05/05/2021
IMPACT FEE PARKS ¤1,199.12 05/05/2021
IMPACT FEE SCHOOL ¤3,600.00 05/05/2021
IMPACT FEE TRANSPORTATION ¤1,718.00 05/05/2021
MECHANICAL FEE ¤168.60 05/05/2021
WATER -IRRIGATION INSPECTION ¤25.00 05/05/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 05/05/2021
PLAN CHECK FEE ¤72.40 05/05/2021
PLUMBING FEE ¤168.60 05/05/2021
NEW RESIDENTIAL INSPECTIONS ¤362.00 05/05/2021
SITE PLAN 20 ¤20.00 05/05/2021
SURCHARGE FS 533.721 ¤2.00 05/05/2021
SURCHARGE - FS 468.631 ¤2.00 05/05/2021
Fees Total Due: ¤0.00 Total Paid: ¤16,211.43