Permit #2021050364

Permit Details

Status: COED

Parcel Id: 07-11-31-7025-00320-0150
CONDITIONED SPACE: 1024 sqft
CONDITIONED SPACE: 1250 sqft
GARAGE: 413 sqft
OPENED PORCH (WITH ROOF) : 72 sqft
Total Square Footage: 2759 sqft
Block: 00320
Subdivision: 2189 - SECTION 25-PINE GROVE
Job Phone: 321-249-3126
Location Address: 18 PEPPER LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 05/19/2021
NOC: RECORDED
Applicant name: MOREY C DOYLE
Owner: WJHFL LLC

Address

3091 GOVERNORS LAKE DR SUITE 300

NORCROSS, GA 30071

Lot: 0150
Contracted Stated Job Value: ¤159,180.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

WADE JURNEY HOMES
Status Location Address State License Number Phone
CANCEL

3091 GOVERNORS LAKE DRIVE

NORCROSS, GA 30071

CGC1517458 (Exp: 08/31/2022) 321-249-3126

Sub Contractors

DANIEL P GREGOIRE
Status Location Address State License Number Phone
INACTIVE

64 W. CENTRAL AVENUE

LAKE WALES, FL 33853

CFC057378 (Exp: 08/31/2024) (863)696-3737
EDWIN R INSALACO
Status Location Address Mailing Address State License Number Phone Fax
CANCEL

3191 MAGUIRE BLVD

ORLANDO, FL 32803

STE 200

ORLANDO, FL 32803

EC13001310 (Exp: 08/31/2024) 321-441-7990 407-426-9741
MICHAEL LEE RAFFENSBERGER
Status Location Address State License Number Phone Fax
CANCEL

7725 SANDSCOVE CT

WINTER PARK, FL 32792

CAC1819723 (Exp: 08/31/2024) 407-629-6920 407-629-9307
IAN ALAN BRENNER
Status Location Address Mailing Address State License Number Phone
ACTIVE

691 GARDEN COMMERCE PKWY

WINTER GARDEN, FL 34787

STE 170

WINTER GARDEN, FL 34787

CCC1331270 (Exp: 08/31/2026) 407-649-1333

Inspection History

Type Request Date Result Inspector
PLUMBING FINAL 12/17/2021 Approval - Private Provider PPROVIDER
HVAC FINAL 12/17/2021 Approval - Private Provider PPROVIDER
ELECTRIC FINAL 12/17/2021 Approval - Private Provider PPROVIDER
U -UTILITY RESIDENTIAL FINAL 12/17/2021 FINAL APPROVED JHARDING
ROW FIELD SURVEY /GRADING CERTIFICATION 12/16/2021 APPROVED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD.
ROW - STORMWATER FINAL 12/16/2021 APPROVED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD.
ROW - FINAL APRON (AFTER POUR) 12/16/2021 APPROVED GBERTOLA
Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD.
FINAL SURVEY (OFFICE USE ONLY) 12/16/2021 APPROVED GBERTOLA
ELECTRIC - EARLY POWER 12/03/2021 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 11/22/2021 Approval - Private Provider PPROVIDER
GRAVITY SEWER TEST 11/17/2021 CANCELLED BY APPLICANT WEB
U - SEWER TIE IN 11/17/2021 APPROVED MGIBSON
ROW- PRE-APRON (PRE-POUR) 11/16/2021 APPROVED - AS NOTED GBERTOLA
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION APRON WAY TOO SOFT TO POUR. BUILDER MAY WANT TO PUT ROCK AND/OR ROADBASE TO STABILIZE GROUND FOR BETTER COMPACTION CHECK THAT MATERIAL IS COMPACTED IN THE ENTIRE AREA TO BE POURED. MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. Land Development Code Technical Manual, Section 900.04 (A) REBARS MISSING,CHECK THAT AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. Land Development Code Technical M anual, Drawing 300.E Section A-A 11/12/2021=FORM BOARD BY THE EDGE OF THE ROAD ON THE LEFT SIDE NEED TO BE CLOSER TO THE EDGE OF THE ROAD PICTURE ATTACHED CULVERT ELEVATION IS GOOD CULVERT TOLERANCE IS GOOD 11/16/2021=AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING.
ROW- PROJECT STATUS 11/16/2021 APPROVED - AS NOTED CTROHA
Note: I supervised the inspection peformed by Gabriel Bertola. I found these inspections to be done professionally and follow City standards
ROW- PRE-APRON (PRE-POUR) 11/12/2021 Disapproved -FEE REQUIRED GBERTOLA
Note: THIS IS A REINSPECTION APRON WAY TOO SOFT TO POUR. BUILDER MAY WANT TO PUT ROCK AND/OR ROADBASE TO STABILIZE GROUND FOR BETTER COMPACTION CHECK THAT MATERIAL IS COMPACTED IN THE ENTIRE AREA TO BE POURED. MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. Land Development Code Technical Manual, Section 900.04 (A) REBARS MISSING,CHECK THAT AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. Land Development Code Technical M anual, Drawing 300.E Section A-A 11/12/2021=FORM BOARD BY THE EDGE OF THE ROAD ON THE LEFT SIDE NEED TO BE CLOSER TO THE EDGE OF IS NO STAIGHT NEED TO FOLLOW THE ROAD AT THE EDGE THE ROAD PICTURE ATTACHED CULVERT ELEVATION IS GOOD
ROW- PRE-APRON (PRE-POUR) 11/09/2021 Disapproved -FEE REQUIRED GBERTOLA
Note: APRON WAY TOO SOFT TO POUR. BUILDER MAY WANT TO PUT ROCK AND/OR ROADBASE TO STABILIZE GROUND FOR BETTER COMPACTION CHECK THAT MATERIAL IS COMPACTED IN THE ENTIRE AREA TO BE POURED. MATERIAL SHOULD BE COMPACTED AROUND PIPE ABOUT 1/2 WAY UP THE SIDE OF THE PIPE. Land Development Code Technical Manual, Section 900.04 (A) REBARS MISSING,CHECK THAT AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. Land Development Code Technical Manual, Drawing 300.E Section A-A CULVERT TOLERANCE IS GOOD
WATER METER INSTALLATION REQUEST 11/08/2021 APPROVED CSTONE
U-CROSS CONNECTION 11/08/2021 APPROVED - AS NOTED JHARDING
Note: No irrigation, no cross connections.
FOUND SURVEY APPROVED (OFFICE) 11/05/2021 APPROVED TBAKER
INSULATION 10/20/2021 Approval - Private Provider PPROVIDER
ALL ROUGH 10/18/2021 Approval - Private Provider PPROVIDER
LATH/BRICK/ WATER BARRIER 10/11/2021 Approval - Private Provider PPROVIDER
ROOF VALLEY & METAL 10/05/2021 Approval - Private Provider PPROVIDER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 09/28/2021 Approval - Private Provider PPROVIDER
TIE BEAM / LINTEL 09/10/2021 Approval - Private Provider LMUSGROVE
MONOLITHIC SLAB 08/23/2021 Approval - Private Provider PPROVIDER
PLUMBING 1ST ROUGH UNDERGROUND 08/12/2021 Approval - Private Provider PPROVIDER
BLD - BUILDING FINAL

Review History

Department Status Date In Date Out
ENGIN1 COMPLETE 11/05/2021 11/05/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 11/05/2021 11/05/2021
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
SW1 COMPLETE 05/19/2021 05/19/2021
Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM
SWALE COMPLETE 05/13/2021 07/24/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/13/2021 05/13/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 05/13/2021 05/13/2021
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
BLD COMPLETE 05/06/2021 05/07/2021
Note: Released By: JPI
CUSVC COMPLETE 05/06/2021 05/12/2021
Note: Released By: HALEIGH HAND - -
ELEC COMPLETE 05/06/2021 05/07/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 HOLD 05/06/2021 05/06/2021
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM No benchmark on survey
LOCATE COMPLETE 05/06/2021 05/07/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 05/06/2021 05/07/2021
Note: Released By: CHRIS PISCITELLI - - CPISCITELLI@PALMCOASTGOV.COM
SW1 HOLD 05/06/2021 05/13/2021
Note: Held By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM An on-site, third order, easily identifiable benchmark referenced to NAVD 1988 (e.g. .An on-site, third order, easily identifiable benchmark referenced to NAVD 1988 (e.g. fire hydrant, nail in power pole.) Pavement nails will not be accepted as benchmarks.(D)
ZON HOLD 05/06/2021 05/10/2021
Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Right side setback missing on site plan/survey
BADMIN HOLD 05/06/2021 05/06/2021
Note: Held By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM In the future, please be sure to name your documents according to the document submittal guidelines on the webpage for the portal. I changed the names for this one. Also, do not upload the general note sheet. and we do not require a plumbing riser diagram any longer.
BADMIN COMPLETE 05/06/2021 05/06/2021
Note: Released By: BARBIE BEMBRY - (386)986-3780 - BUILDINGDIVISION@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
SW ENG REINSPECTION 30 ¤30.00 12/08/2021
SW ENG REINSPECTION 30 ¤30.00 12/08/2021
STORM WATER PERMIT FEES ¤80.00 05/19/2021
3% TRANS IMPACT FEE CREDIT (¤51.54) 05/19/2021
SEWER CREDIT (¤2,465.75) 05/19/2021
SEWER INSPECTION ¤25.00 05/19/2021
SEWER CAPITAL FACILITY ¤4,664.55 05/19/2021
WATER CAPITAL FACILITY FEE ¤3,424.45 05/19/2021
METER - DEPOSIT ¤60.00 05/19/2021
WATER- TURN ON ¤25.00 05/19/2021
ADMIN FEE ¤20.00 05/19/2021
CONNECTION FEES ¤1,017.83 05/19/2021
BUILDING DISCOUNT 100% (¤1,342.40) 05/19/2021
ELECTRIC FEE ¤223.20 05/19/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 05/19/2021
IMPACT FEE FIRE ¤367.00 05/19/2021
IMPACT FEE PARKS ¤1,199.12 05/19/2021
IMPACT FEE SCHOOL ¤3,600.00 05/19/2021
IMPACT FEE TRANSPORTATION ¤1,718.00 05/19/2021
MECHANICAL FEE ¤223.20 05/19/2021
WATER -IRRIGATION INSPECTION ¤25.00 05/19/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 05/19/2021
PLAN CHECK FEE ¤108.80 05/19/2021
PLUMBING FEE ¤223.20 05/19/2021
NEW RESIDENTIAL INSPECTIONS ¤544.00 05/19/2021
SITE PLAN 20 ¤20.00 05/19/2021
SURCHARGE FS 533.721 ¤2.00 05/19/2021
SURCHARGE - FS 468.631 ¤2.00 05/19/2021
Fees Total Due: ¤0.00 Total Paid: ¤13,725.68