Permit #2021050864
Permit Details
Status: COED
| Parcel Id: 07-11-31-7030-00760-0060 |
| CONDITIONED SPACE: 1650 sqft |
| OPENED PORCH (WITH ROOF) : 81 sqft |
| GARAGE: 403 sqft |
| Total Square Footage: 2134 sqft |
| Block: 00760 |
| Subdivision: 2154 - SECTION 30-ROYAL PALMS |
| Job Phone: 321-249-3126 |
| Location Address: 114 RAMBLEWOOD DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 05/19/2021 |
| NOC: RECORDED |
| Applicant name: MOREY C DOYLE |
| Owner: ROEUN SAROEUN & NOLEDA TOUCH |
|
Address 6 POSTMAN LANE PALM COAST, FL 32164 |
| Lot: 0060 |
| Contracted Stated Job Value: ¤99,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
WADE JURNEY HOMES
| Status | Location Address | State License Number | Phone |
| CANCEL |
3091 GOVERNORS LAKE DRIVE NORCROSS, GA 30071 |
CGC1517458 (Exp: 08/31/2022) | 321-249-3126 |
Sub Contractors
IAN ALAN BRENNER
| Status | Location Address | Mailing Address | State License Number | Phone |
| ACTIVE |
691 GARDEN COMMERCE PKWY WINTER GARDEN, FL 34787 |
STE 170 WINTER GARDEN, FL 34787 |
CCC1331270 (Exp: 08/31/2026) | 407-649-1333 |
EDWIN R INSALACO
| Status | Location Address | Mailing Address | State License Number | Phone | Fax |
| CANCEL |
3191 MAGUIRE BLVD ORLANDO, FL 32803 |
STE 200 ORLANDO, FL 32803 |
EC13001310 (Exp: 08/31/2024) | 321-441-7990 | 407-426-9741 |
MICHAEL LEE RAFFENSBERGER
| Status | Location Address | State License Number | Phone | Fax |
| CANCEL |
7725 SANDSCOVE CT WINTER PARK, FL 32792 |
CAC1819723 (Exp: 08/31/2024) | 407-629-6920 | 407-629-9307 |
DANIEL P GREGOIRE
| Status | Location Address | State License Number | Phone |
| INACTIVE |
64 W. CENTRAL AVENUE LAKE WALES, FL 33853 |
CFC057378 (Exp: 08/31/2024) | (863)696-3737 |
Inspection History
| Type | Request Date | Result | Inspector |
| ROW - STORMWATER FINAL | 11/04/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION SWALE ON THE LEFT SIDE NEED TO Match existing grade, Swale not graded to match existing surounding grade IN THE BACK OF THE HOUSE AND RIGHT BACK CORNER, Not enough drainage away from the structure away from to the building. Water will stand next to and near the foundation. Needs more fall away from the structure. Sod elevations adjacent to the structure are 4” below the FFE for block and 6” for woodframe structures. (H) H.Florida Building Code, Residential, Chapter 4, R404.1.6I. 10/29/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTEs 11/04/2021=CORRECTION WERE MADE AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| U -UTILITY RESIDENTIAL FINAL | 10/29/2021 | FINAL APPROVED | LFITZGERALD |
| ROW - STORMWATER FINAL | 10/29/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: SWALE ON THE LEFT SIDE NEED TO Match existing grade, Swale not graded to match existing surounding grade IN THE BACK OF THE HOUSE AND RIGHT BACK CORNER, Not enough drainage away from the structure away from to the building. Water will stand next to and near the foundation. Needs more fall away from the structure. Sod elevations adjacent to the structure are 4” below the FFE for block and 6” for woodframe structures. (H) H.Florida Building Code, Residential, Chapter 4, R404.1.6I. 10/29/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTEs | |||
| PLUMBING FINAL | 10/29/2021 | Approval - Private Provider | PPROVIDER |
| HVAC FINAL | 10/29/2021 | Approval - Private Provider | PPROVIDER |
| ELECTRIC FINAL | 10/29/2021 | Approval - Private Provider | PPROVIDER |
| BLD - BUILDING FINAL | 10/29/2021 | Approval - Private Provider | PPROVIDER |
| ROW- PROJECT STATUS | 10/29/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: MEETING WITH JW SUPERVISOR | |||
| ROW - FINAL APRON (AFTER POUR) | 10/28/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 10/28/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| FINAL SURVEY (OFFICE USE ONLY) | 10/28/2021 | APPROVED | GBERTOLA |
| U-CROSS CONNECTION | 10/26/2021 | APPROVED - AS NOTED | LFITZGERALD |
| Note: no irrigation-no cross connection | |||
| GRAVITY SEWER TEST | 10/11/2021 | Approval - Private Provider | PPROVIDER |
| U - SEWER TIE IN | 10/08/2021 | APPROVED | JWALKER |
| ROW- PRE-APRON (PRE-POUR) | 10/06/2021 | APPROVED - AS NOTED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION NOT READY FOR INSPECTION. NOT FORMED YET 10/05/2021=MISSING REBARS THAT AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. NEED DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. CULVERT ELEVATION IS GOOD 10/06/2021=AT THE TIME OF THE INSPECTION CULVERT PIPE IS GOOD IS READY TO POUR, IF RAIN PLEASE, BUILDER SHOULD DOUBLE CHECK CULVERT ELEVATIONS BEFORE POURING | |||
| ROW- PRE-APRON (PRE-POUR) | 10/05/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION NOT READY FOR INSPECTION. NOT FORMED YET 10/05/2021=MISSING REBARS THAT AT LEAST 24 INCHES OF #4 REBAR IS PLACED UNDER EACH END OF THE PIPE. PIPE SHOULD BE DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. NEED DUG OUT 6 INCHES DEEP BY 6 INCHES LONG UNDER EACH END OF THE PIPE. CULVERT ELEVATION IS GOOD | |||
| ROW- PRE-APRON (PRE-POUR) | 10/04/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: NOT READY FOR INSPECTION. NOT FORMED YET | |||
| ELECTRIC - EARLY POWER | 09/30/2021 | Approval - Private Provider | PPROVIDER |
| INSULATION | 08/26/2021 | Approval - Private Provider | PPROVIDER |
| PEP TANK INSTALLATION REQUEST | 08/24/2021 | APPROVED | CSTONE |
| LATH/BRICK/ WATER BARRIER | 08/24/2021 | Approval - Private Provider | PPROVIDER |
| Note: 08/24/2021 Wire Lath Inspection passed. | |||
| ALL ROUGH | 08/23/2021 | Approval - Private Provider | PPROVIDER |
| FOUND SURVEY APPROVED (OFFICE) | 08/23/2021 | APPROVED | TBAKER |
| ROW - DRAINAGE | 08/16/2021 | APPROVED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021. 7/21/21 - Temporary Culvert Installed. Next inspection 7/29/21. 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 07/16/2021=ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE 07/202/2021=NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE = 07/202021=Erosion Control Inspection (inspection code # 119) ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE IF SILT FENCE IS NO DOWN IN 5 DAYS I WILL TRANSFER THIS TO CODE ENFORCEMENT ON 07/26/2021 | |||
| ROOF VALLEY & METAL | 08/11/2021 | Approval - Private Provider | PPROVIDER |
| Note: 08/11/2021 Roof Underlayment, Valley and Metal inspection passed. | |||
| WALL SHEATHING | 08/04/2021 | Approval - Private Provider | PPROVIDER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 08/04/2021 | Approval - Private Provider | PPROVIDER |
| ROW - DRAINAGE | 07/29/2021 | PARTIALLY APPROVED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021. 7/21/21 - Temporary Culvert Installed. Next inspection 7/29/21. 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 07/16/2021=ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE 07/202/2021=NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE = 07/202021=Erosion Control Inspection (inspection code # 119) ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE IF SILT IS NO DOWN IN 5 DAYS I WILL TRANSFER THIS TO CODE ENFORCEMENT ON 07/26/2021 | |||
| ROW - DRAINAGE | 07/21/2021 | PARTIALLY APPROVED | RGROSS |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021. 7/21/21 - Temporary Culvert Installed. Next inspection 7/29/21. 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 07/16/2021=ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE 07/202/2021=NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE = 07/202021=Erosion Control Inspection (inspection code # 119) ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE IF SILT IS NO DOWN IN 5 DAYS I WILL TRANSFER THIS TO CODE ENFORCEMENT ON 07/26/2021 | |||
| ROW - DRAINAGE | 07/20/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 07/16/2021=ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE 07/202/2021=NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE = 07/202021=Erosion Control Inspection (inspection code # 119) ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE IF SILT IS NO DOWN IN 5 DAYS I WILL TRANSFER THIS TO CODE ENFORCEMENT ON 07/26/2021 | |||
| ROW - DRAINAGE | 07/16/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 07/16/2021=ROW STILL NO OPEN PIPE IS DOWN BUT STILL A LOT DIRT IN FRONT OF THE PIPE NEED TO OPEN THE SWALE BOTH SIDE TO THE END OF YOUR PROPERTY , STILL NEED A SILT FENCE ALL AROUND THE CONSTRUCTION SITE INSPECTOR BE BACK ON 07/19/2021 | |||
| TIE BEAM / LINTEL | 07/14/2021 | Approval - Private Provider | PPROVIDER |
| ROW - DRAINAGE | 07/14/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 07/14/2021= NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY inspector be back on 07/16/2021 | |||
| ROW - DRAINAGE | 07/09/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 07/09/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE INSPECTOR BE BACK =07/14/2021 | |||
| ROW - DRAINAGE | 07/07/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 07/082021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE be back on 07/09/2021 | |||
| ROW - DRAINAGE | 07/06/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 07/06/2021=NOTHING HAS BEEN DONE SINCE THE LAST INSPECTION, NEED TO READ THE INPECTOR NOTE BUILDER NEEDS TO OPEN DRIANAGE ACROSS THE FRONT SWALE ROW NEED A PIPE ON THE GROUND MINIMUN 12 INCH, SWALE NEED TO BE OPENED, MAINTAINED AT THE END OF EVERY DAY NEED TO INSTALL SILT FENCE ALL AROUND THE CONSTRUCTION SITE BE BACK ON 07/08/2021 | |||
| MONOLITHIC SLAB | 07/01/2021 | Approval - Private Provider | PPROVIDER |
| ROW - DRAINAGE | 06/29/2021 | Disapproved -FEE REQUIRED | GBERTOLA |
| Note: THIS IS A REINSPECTION Drainage needs opened across the front of the construction project. Next inspection 6/28/21. 06/29/2021=NEED A TO INSTALL A SILT FENCE, NEED A PIPE IN THE FRONT BE BACK 07/06/2021 | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 06/28/2021 | Approval - Private Provider | PPROVIDER |
| Note: 06/28/2021 Underground plumbing inspection passed. | |||
| MONOLITHIC SLAB | 06/28/2021 | Approval - Private Provider | PPROVIDER |
| ROW - DRAINAGE | 06/22/2021 | Disapproved - NO FEE | RGROSS |
| Note: Drainage needs opened across the front of the construction project. Next inspection 6/25/21. | |||
| WATER METER INSTALLATION REQUEST | 06/02/2021 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| ENGIN1 | COMPLETE | 08/23/2021 | 08/23/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 08/23/2021 | 08/23/2021 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 05/19/2021 | 05/19/2021 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 05/14/2021 | 07/30/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 05/13/2021 | 05/14/2021 |
| Note: Released By: JPI | |||
| CUSVC | COMPLETE | 05/13/2021 | 05/14/2021 |
| Note: Released By: HALEIGH HAND - - | |||
| ELEC | COMPLETE | 05/13/2021 | 05/14/2021 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 05/13/2021 | 05/14/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 05/13/2021 | 05/18/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 05/13/2021 | 05/14/2021 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 05/13/2021 | 05/18/2021 |
| Note: Released By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM | |||
| ZON | HOLD | 05/13/2021 | 05/19/2021 |
| Note: Held By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM Section number missing in legal description on site plan/survey |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| STORMWATER REINSPECTION FEE | ¤40.00 | 11/03/2021 |
| SW ENG - FIELD SURVEY INSPECT | ¤20.00 | 11/03/2021 |
| SW ENG REINSPECTION 20 | ¤20.00 | 11/03/2021 |
| SW ENG REINSPECTION 30 | ¤30.00 | 11/03/2021 |
| SW ENG REINSPECTION 30 | ¤30.00 | 11/03/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 05/19/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤51.54) | 05/19/2021 |
| SEWER CREDIT | (¤1,147.00) | 05/19/2021 |
| SEWER INSPECTION | ¤25.00 | 05/19/2021 |
| SEWER CAPITAL FACILITY | ¤4,664.55 | 05/19/2021 |
| WATER CAPITAL FACILITY FEE | ¤3,424.45 | 05/19/2021 |
| METER - DEPOSIT | ¤60.00 | 05/19/2021 |
| WATER- TURN ON | ¤25.00 | 05/19/2021 |
| ADMIN FEE | ¤20.00 | 05/19/2021 |
| CONNECTION FEES | ¤1,017.83 | 05/19/2021 |
| BUILDING DISCOUNT 100% | (¤1,052.60) | 05/19/2021 |
| ELECTRIC FEE | ¤181.80 | 05/19/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 05/19/2021 |
| IMPACT FEE FIRE | ¤367.00 | 05/19/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 05/19/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 05/19/2021 |
| IMPACT FEE TRANSPORTATION | ¤1,718.00 | 05/19/2021 |
| MECHANICAL FEE | ¤181.80 | 05/19/2021 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 05/19/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 05/19/2021 |
| PLAN CHECK FEE | ¤81.20 | 05/19/2021 |
| PLUMBING FEE | ¤181.80 | 05/19/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤406.00 | 05/19/2021 |
| SITE PLAN 20 | ¤20.00 | 05/19/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 05/19/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 05/19/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤15,364.43 |