Status: FINAL
| Parcel Id: 07-11-31-7013-00200-0240 |
| Total Square Footage: 800 sqft |
| Block: 00200 |
| Subdivision: 2192 - SECTION 13-BELLE TERRE |
| Job Phone: 386-227-2646 |
| Location Address: 75 BRUNSWICK LN |
| Type: DR - DRIVEWAY |
| Issue Date: 06/10/2021 |
| NOC: Unknown |
| Applicant name: JUAN P BARTOLOME HERNANDEZ |
| Owner: PRONESTI EMMA |
|
Address 75 BRUNSWICK LANE PALM COAST, FL 32137 |
| Lot: 0240 |
| Contracted Stated Job Value: ¤1,000.00 |
| Job Description: CONCRETE CIRCULAR DRIVEWAY |
| Type: CN |
Contractor
A TOUCH OF SPAIN INC
| Status | Location Address | Phone |
| INACTIVE |
74 SEVEN WONDERS TRAIL , |
386-227-2646 |
Inspection History
| Type | Request Date | Result | Inspector |
| U -UTILITY RESIDENTIAL FINAL | 09/15/2021 | FINAL APPROVED | JHARDING |
| ROW - FINAL INSPECTION | 09/10/2021 | APPROVED | KRUTH |
| Note: THIS IS A REINSPECTION the rocks that are in the swale are blocking the pipe on the right and the concrete in the swale accross the street needs to be hauled off and re sod the swale | |||
| ROW - FINAL APRON (AFTER POUR) | 08/23/2021 | APPROVED | KRUTH |
| ROW - FINAL INSPECTION | 08/23/2021 | Disapproved -FEE REQUIRED | KRUTH |
| Note: the rocks that are in the swale are blocking the pipe on the right and the concrete in the swale accross the street needs to be hauled off and re sod the swale | |||
| ROW- PRE-APRON (PRE-POUR) | 07/12/2021 | APPROVED - AS NOTED | RGROSS |
| Note: THIS IS A REINSPECTION 7/12/21 - Bucket out any water in the mitered ends. Install a board under the mitered end back board so no concrete can escape from the pour area. On site with homeowner. | |||
| ROW- PRE-APRON (PRE-POUR) | 07/06/2021 | CANCELLED BY APPLICANT | KRUTH |
Review History
| Department | Status | Date In | Date Out |
| ZON | COMPLETE | 06/09/2021 | 06/10/2021 |
| Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 06/03/2021 | 06/07/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| UTL | COMPLETE | 06/03/2021 | 06/08/2021 |
| Note: Released By: LARRY FITZGERALD - - LFITZGERALD@PALMCOASTGOV.COM | |||
| ZON | HOLD | 06/03/2021 | 06/04/2021 |
| Note: Held By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM 1. The maximum width for a circular driveway is 18'. It appears you are connecting the proposed circular driveway to the existing walkway which would make the driveway exceed the maximum width. 2. The site plan must demonstrate that there is a minimum of 5' setback from the front property line to the bottom arc of the new circular driveway. |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| SW ENG REINSPECTION 20 | ¤20.00 | 09/14/2021 |
| STORM WATER PERMIT FEES | ¤40.00 | 06/10/2021 |
| ADMIN FEE | ¤20.00 | 06/10/2021 |
| BUILDING DISCOUNT 100% | (¤20.00) | 06/10/2021 |
| SITE PLAN 20 | ¤20.00 | 06/10/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 06/10/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 06/10/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤84.00 |