Permit #2021061040
Permit Details
Status: COED
| Parcel Id: 16-11-31-1260-00000-0370 |
| CONDITIONED SPACE: 2545 sqft |
| GARAGE: 954 sqft |
| OPENED PORCH (WITH ROOF) : 44 sqft |
| OPENED PORCH (WITH ROOF) : 743 sqft |
| Total Square Footage: 4286 sqft |
| Block: 00000 |
| Subdivision: 2081 - Creekside Village at Grand Haven |
| Job Phone: 386-445-2012 |
| Location Address: 48 CREEKSIDE DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 07/30/2021 |
| NOC: RECORDED |
| Applicant name: JOHN NICHOLAS CORDASCI |
| Owner: VELARDI DONALD & NANCY VELARDI H&W |
|
Address 29 MARLIN DRIVE PALM COAST, FL 32137 |
| Lot: 0370 |
| Contracted Stated Job Value: ¤459,719.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
SKYWAY BUILDERS INC
| Status | Location Address | State License Number | Phone |
| INACTIVE |
PO BOX 354786 PALM COAST, FL 32135 |
CBC1263769 (Exp: 08/31/2024) | 386-445-2012 |
Sub Contractors
MARK JOHN LUTCZA
| Status | Location Address | State License Number | Phone |
| ACTIVE |
26 ROYAL LEAF LANE PALM COAST, FL 32164 |
EC13005145 (Exp: 08/31/2026) | 386-586-0770 |
THOMAS A REGULA
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
11320 PHILLIPS PKWY DRIVE E JACKSONVILLE, FL 32256 |
CMC1250075 (Exp: 08/31/2026) | 904-278-0339 | 904-278-0366 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
DANIEL DAVID RUTKOWSKI III
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
1687 STATE AVENUE HOLLY HILL, FL 32117 |
CCC1328639 (Exp: 08/31/2026) | 386-290-7490 | 386-256-0001 |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 10/12/2022 | FINAL APPROVED | DCUSHING |
| BLD - BUILDING FINAL | 10/11/2022 | CANCELLED BY APPLICANT | WEB |
| ROW - STORMWATER FINAL | 10/10/2022 | APPROVED | GBERTOLA |
| Note: AT THE TIME OF THE INSPECTION EVERYTHING LOOK GOOD | |||
| U -UTILITY RESIDENTIAL FINAL | 10/10/2022 | FINAL APPROVED | LFITZGERALD |
| U-CROSS CONNECTION | 10/10/2022 | APPROVED - AS NOTED | LFITZGERALD |
| Note: well irrigation-no cross connection | |||
| ROW - FINAL APRON (AFTER POUR) | 10/07/2022 | APPROVED | PFLANAGAN |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 10/07/2022 | APPROVED | PFLANAGAN |
| Note: | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 10/07/2022 | APPROVED | PFLANAGAN |
| ROW- PRE-APRON (PRE-POUR) | 09/09/2022 | Disapproved - NO FEE | GBERTOLA |
| Note: FOR THE DRIVEWAY PAVERS IS NOT A INSPECTION DONE AFTER THE PAVERS RESTRAINT. | |||
| ROW- PRE-APRON (PRE-POUR) | 09/09/2022 | APPROVED - AS NOTED | GBERTOLA |
| Note: SIDEWALK IS READY TO POUR 09/09/22=I JUST TALK TO JOHN FROM SKYWAY AND GOING TO APROVE THE SIDEWALK INSPECTION BUT WE GOING TO LOOK IN THE OTHER INSPECTION MISSING ..................................................................................................................................................................................................................................... FOR THE DRIVEWAY PAVERS IS NOT A INSPECTION DONE AFTER THE PAVERS RESTRAINT. | |||
| WINDOW NAILING | 09/02/2022 | APPROVED | DCUSHING |
| Note: THIS IS A REINSPECTION need to expose screws for inspection | |||
| ROW- PRE-APRON (PRE-POUR) | 08/30/2022 | CANCELLED BY APPLICANT | WEB |
| Note: Inspector Notes from Inspection 9271 READY TO POUR PAVER RESTRAINTS ONLY | |||
| ROW- PRE-APRON (PRE-POUR) | 08/30/2022 | APPROVED | PFLANAGAN |
| Note: New inspection due to canceled inspection Inspector Notes from Inspection 9271 READY TO POUR PAVER RESTRAINTS ONLY | |||
| ROW- PAVER RESTRAINTS | 08/01/2022 | APPROVED - AS NOTED | PFLANAGAN |
| Note: READY TO POUR PAVER RESTRAINTS ONLY | |||
| U - SEWER TIE IN | 06/29/2022 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 06/29/2022 | APPROVED | MGIBSON |
| LATH/BRICK/ WATER BARRIER | 05/17/2022 | APPROVED | LMILLER |
| Note: THIS IS A REINSPECTION still need to see flashing at slider when installed 5-17-22 notes above resolved | |||
| WINDOW NAILING | 05/17/2022 | Disapproved -FEE REQUIRED | LMILLER |
| Note: need to expose screws for inspection | |||
| ELECTRIC - EARLY POWER | 05/09/2022 | APPROVED | AGAETANO |
| Note: FPL notified at 1:22pm | |||
| LATH/BRICK/ WATER BARRIER | 04/08/2022 | PARTIALLY APPROVED | LMILLER |
| Note: still need to see flashing at slider when installed | |||
| WINDOW NAILING | 03/14/2022 | APPROVED - AS NOTED | AGAETANO |
| Note: All wiindows and doors approved except for back large SGD not installed. Window nailing will be added. | |||
| INSULATION | 03/14/2022 | APPROVED | AGAETANO |
| ALL ROUGH | 02/04/2022 | APPROVED | AGAETANO |
| Note: Added window inspection. | |||
| ELECTRIC-TUG | 12/15/2021 | APPROVED - AS NOTED | JMUNSON |
| Note: Emailed FPL at 11:14 am | |||
| ROOF VALLEY & METAL | 11/16/2021 | APPROVED | LMILLER |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 11/12/2021 | APPROVED | RMARTIN |
| TIE BEAM / LINTEL | 10/13/2021 | APPROVED | LMILLER |
| FOUND SURVEY APPROVED (OFFICE) | 09/29/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 09/15/2021 | APPROVED | TSTAUFFACHER |
| Note: | |||
| PLUMBING 1ST ROUGH UNDERGROUND | 09/13/2021 | APPROVED | MGIBSON |
| WATER METER INSTALLATION REQUEST | 08/17/2021 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| BLD | COMPLETE | 10/11/2022 | 10/11/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 09/28/2021 | 09/29/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 09/28/2021 | 09/28/2021 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 06/24/2021 | 06/24/2021 |
| Note: Released By: JPI PLAN REVIEW COMMENTS NO. 1 AND 2 FROM PREVIOUS BUILDING REVIEW HOLD HAVE BEEN REMOVED AS THE CITY HAS NOT HISTORICALLY REQUIRED THIS INFORMATION TO BE SHOWN ON PLANS. PLEASE RESPOND TO REMAINING COMMENT BELOW. THIS IS BEING CALLED BECAUSE THE PRESSURE ZONES AND NAILING SCHEDULES HAVE NOT BEEN UPDATED TO THE 2020 BUILDING CODE. 3. Provide roof pressure zone nailing schedule- FBC-R301.2(7). | |||
| SW1 | COMPLETE | 06/23/2021 | 06/23/2021 |
| Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 06/16/2021 | 06/23/2021 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | HOLD | 06/16/2021 | 06/22/2021 |
| Note: Held By: JPI 1. Indicate “EGRESS” windows/doors on the Floor Plan, Sht. 3 for ALL Bedrooms which corresponds with General Note “H” on Sht. 3. 2. Provide Door and Window Schedule on Sht. 3 - FBC 107.3.5. 3. Provide roof pressure zone nailing schedule- FBC-R301.2(7). | |||
| CUSVC | COMPLETE | 06/16/2021 | 06/24/2021 |
| Note: Released By: ALYSSA ROSCOE - - | |||
| ELEC | COMPLETE | 06/16/2021 | 06/17/2021 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 06/16/2021 | 06/17/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 06/16/2021 | 06/22/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 06/16/2021 | 06/17/2021 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| PLAN REVIEW - REVISION | ¤32.50 | 10/12/2022 |
| REINSPECTION RESIDENTIAL | ¤40.00 | 10/12/2022 |
| CONNECTION FEES | ¤25.00 | 07/30/2021 |
| BUILDING DISCOUNT 100% | (¤2,132.00) | 07/30/2021 |
| ELECTRIC FEE | ¤336.00 | 07/30/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 07/30/2021 |
| IMPACT FEE FIRE | ¤367.00 | 07/30/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 07/30/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 07/30/2021 |
| IMPACT FEE TRANSPORTATION | ¤3,139.00 | 07/30/2021 |
| MECHANICAL FEE | ¤336.00 | 07/30/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 07/30/2021 |
| PLAN CHECK FEE | ¤184.00 | 07/30/2021 |
| PLUMBING FEE | ¤336.00 | 07/30/2021 |
| NEW RESIDENTIAL INSPECTIONS | ¤920.00 | 07/30/2021 |
| SITE PLAN 20 | ¤20.00 | 07/30/2021 |
| SURCHARGE FS 533.721 | ¤2.00 | 07/30/2021 |
| SURCHARGE - FS 468.631 | ¤2.00 | 07/30/2021 |
| STORM WATER PERMIT FEES | ¤80.00 | 07/30/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤94.17) | 07/30/2021 |
| SEWER INSPECTION | ¤25.00 | 07/30/2021 |
| METER - DEPOSIT | ¤60.00 | 07/30/2021 |
| WATER-METER | ¤441.07 | 07/30/2021 |
| ADMIN FEE | ¤20.00 | 07/30/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤8,891.54 |