I want to search for...

Permit #2021070648

Permit Details

Status: COED

Parcel Id: 07-11-31-7059-00350-0040
CONDITIONED SPACE: 2117 sqft
GARAGE: 686 sqft
OPENED PORCH (WITH ROOF) : 186 sqft
OPENED PORCH (WITH ROOF) : 38 sqft
Total Square Footage: 3027 sqft
Block: 00350
Subdivision: -
Job Phone: (386)437-1508
Location Address: 47 SEA FRONT TR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 07/27/2021
NOC: RECORDED
Applicant name: TAMMI SUE MARQUIS
Owner: JM PROPERTIES X LLC

Address

PO BOX 9

CISSNA PARK, IL 60924

Lot: 0040
Contracted Stated Job Value: ¤210,000.00
Job Description: Residential Home
Type: CN

Contractor

GULFSTREAM HOMES & CONSTRUCTION, LLC
Status Location Address State License Number Phone Fax
INACTIVE

PO BOX 1092

BUNNELL, FL 32110

CRC1326418 (Exp: 08/31/2026) (386)437-1508 386-437-9769

Sub Contractors

JAMES CRAIG FISHER
Status Location Address State License Number Phone
ACTIVE

PO BOX 451

BUNNELL, FL 32110

CAC1819807 (Exp: 08/31/2026) 386-222-9549
JONATHAN M PEARSON
Status Location Address State License Number Phone Fax
ACTIVE

209 N FORSYTH ST

BUNNELL, FL 32110

CFC1425941 (Exp: 08/31/2026) 386-597-0944 386-437-4996
ARTHUR J PASCOE
Status Location Address State License Number Phone
ACTIVE

PO BOX 730007

ORMOND BEACH, FL 32174

EC13007168 (Exp: 08/31/2026) 386-547-6439
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 09/23/2022 FINAL APPROVED BTAYLOR
BLD - BUILDING FINAL 09/22/2022 CANCELLED BY APPLICANT WEB
ROW - STORMWATER FINAL 09/19/2022 APPROVED PFLANAGAN
Note: THEY ARE WORKING ON BERM AT THE TIME OF INSPECTION PASSING AS NOTED --------------------------------------------------------------------------------------------------------------------------- 9/16/22 THE BERM IS STILL THERE ----------------------------------------------------------------------------------------------------------------------------- NOTE TO INSPECTOR THE LITTLE BERM AT THE FENCE ON LEFT SIDE NEED TO BE GONE FROM BACK OF HOUSE TO THE FRONT OF HOUSE
U -UTILITY RESIDENTIAL FINAL 09/16/2022 FINAL APPROVED DHANEY
ROW - STORMWATER FINAL 09/16/2022 Disapproved - NO FEE PFLANAGAN
Note: 9/16/22 THE BERM IS STILL THERE ----------------------------------------------------------------------------------------------------------------------------- NOTE TO INSPECTOR THE LITTLE BERM AT THE FENCE ON LEFT SIDE NEED TO BE GONE FROM BACK OF HOUSE TO THE FRONT OF HOUSE
U-CROSS CONNECTION 09/16/2022 APPROVED - AS NOTED JHARDING
Note: No irrigation,no cross connections.
ROW - FINAL APRON (AFTER POUR) 09/16/2022 APPROVED PFLANAGAN
ROW- PROJECT STATUS 09/15/2022 APPROVED PFLANAGAN
ROW- FINAL SURVEY/GRADING CERTIFICATION 09/15/2022 Disapproved - NO FEE PFLANAGAN
Note: NEED TO REGRADE LEFT SITE SO IT MATCES THE SITE PLAN. THE SITE PLAN CALLS FOR A COMMON SWALE AT THE PROPERTY LINE DO TO THE VACANT LOT TO THE LEFT OF YOUR PROPERTY. IF YOU ALREADY HAVE THE DRAINAGE CONVEYANCE ON THE PROPERTY LINE THEN YOU NEED TO GET YOUR SURVEYORS TO SHOW IT ON THE FINAL SURVEY THEN. BUT THAT IS UP TO YOU TO DETERMINE.
ROW- FINAL SURVEY/GRADING CERTIFICATION 09/15/2022 APPROVED PFLANAGAN
Note: AFTER LOOKING AT THE LOT MEET THE CM ON SITE THERE ARE GOING TO FIX THE PROBLEM WITH THE LITTLE BURM ON THE LEFT SIDE OF HOME ---------------------------------------------------------------------------------------------------------------------------- 9/15/2022 - PREVIOUS INSPECTION NOTES NEED TO REGRADE LEFT SITE SO IT MATCES THE SITE PLAN. THE SITE PLAN CALLS FOR A COMMON SWALE AT THE PROPERTY LINE DO TO THE VACANT LOT TO THE LEFT OF YOUR PROPERTY. IF YOU ALREADY HAVE THE DRAINAGE CONVEYANCE ON THE PROPERTY LINE THEN YOU NEED TO GET YOUR SURVEYORS TO SHOW IT ON THE FINAL SURVEY THEN. BUT THAT IS UP TO YOU TO DETERMINE.
ROW- PRE-APRON (PRE-POUR) 08/29/2022 APPROVED PFLANAGAN
Note: 8/29/22 ITS THE CONTRACTORS RESPONSIBILITY TO CHECK CULVERT PIPE ELEVATIONS BORE POUR CONCRETE ----------------------------------------------------------------------------------------------------------------------------------- 8/24/22 THE LEFT INVERT IS OUT OF TOLERANCE FROM THE SWALE DIAGRAM NEED TO RESET CULVERT TO MATCH THE SWALE DIAGRAM
ROW- PRE-APRON (PRE-POUR) 08/24/2022 Disapproved -FEE REQUIRED PFLANAGAN
Note: 8/24/22 THE LEFT INVERT IS OUT OF TOLERANCE FROM THE SWALE DIAGRAM NEED TO RESET CULVERT TO MATCH THE SWALE DIAGRAM
ELECTRIC - EARLY POWER 08/24/2022 APPROVED JMUNSON
GRAVITY SEWER TEST 08/02/2022 APPROVED MGIBSON
U - SEWER TIE IN 08/02/2022 APPROVED MGIBSON
PEP TANK INSTALLATION REQUEST 06/08/2022 APPROVED CSTONE
INSULATION 05/19/2022 APPROVED KSANDOE
LATH/BRICK/ WATER BARRIER 05/11/2022 APPROVED TSTAUFFACHER
ALL ROUGH 05/06/2022 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION Missing protection plate in front right room on wall near front door Electrical service not complete
ALL ROUGH 05/04/2022 Disapproved - NO FEE TSTAUFFACHER
Note: Missing protection plate in front right room on wall near front door Electrical service not complete
ROOF VALLEY & METAL 04/18/2022 APPROVED TSTAUFFACHER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 04/04/2022 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION Multiple items not complete//spoke with super on job
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/14/2022 Disapproved - NO FEE TSTAUFFACHER
Note: Multiple items not complete//spoke with super on job
FOUND SURVEY APPROVED (OFFICE) 02/11/2022 APPROVED TBAKER
WALL SHEATHING 01/26/2022 APPROVED TSTAUFFACHER
TIE BEAM / LINTEL 01/05/2022 APPROVED TSTAUFFACHER
Note: THIS IS A REINSPECTION Front left column vertical dowels not epoxied. Pulled up easily. Drill and epoxy according to plan specifications
TIE BEAM / LINTEL 01/04/2022 Disapproved -FEE REQUIRED TSTAUFFACHER
Note: Front left column vertical dowels not epoxied. Pulled up easily. Drill and epoxy according to plan specifications
MONOLITHIC SLAB 11/18/2021 APPROVED TSTAUFFACHER
PLUMBING 1ST ROUGH UNDERGROUND 11/16/2021 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 10/13/2021 APPROVED CSTONE

Review History

Department Status Date In Date Out
MECH COMPLETE 04/14/2022 04/18/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
ENGIN1 COMPLETE 02/10/2022 02/11/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 02/10/2022 02/10/2022
Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM
ZON COMPLETE 07/26/2021 07/26/2021
Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM
BLD COMPLETE 07/14/2021 07/18/2021
Note: Released By: JPI
CUSVC COMPLETE 07/14/2021 07/21/2021
Note: Released By: HALEIGH HAND - -
ELEC COMPLETE 07/14/2021 07/15/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 07/14/2021 07/14/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 07/14/2021 07/15/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 07/14/2021 07/15/2021
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 07/14/2021 07/20/2021
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ZON HOLD 07/14/2021 07/23/2021
Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM Landscape Plan does not indicate what sod type will used at the property.
SWALE COMPLETE 07/14/2021 10/05/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
PLAN REVIEW - REVISION ¤32.50 09/09/2022
REINSPECTION RESIDENTIAL ¤40.00 09/09/2022
REINSPECTION RESIDENTIAL ¤40.00 09/09/2022
SW ENG REINSPECTION 30 ¤30.00 09/09/2022
STORM WATER PERMIT FEES ¤80.00 07/27/2021
3% TRANS IMPACT FEE CREDIT (¤51.54) 07/27/2021
SEWER CREDIT (¤2,794.99) 07/27/2021
SEWER INSPECTION ¤25.00 07/27/2021
SEWER CAPITAL FACILITY ¤4,664.55 07/27/2021
WATER CAPITAL FACILITY FEE ¤3,424.45 07/27/2021
METER - DEPOSIT ¤60.00 07/27/2021
WATER- TURN ON ¤25.00 07/27/2021
ADMIN FEE ¤20.00 07/27/2021
CONNECTION FEES ¤1,017.83 07/27/2021
BUILDING DISCOUNT 100% (¤1,342.40) 07/27/2021
ELECTRIC FEE ¤223.20 07/27/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 07/27/2021
IMPACT FEE FIRE ¤367.00 07/27/2021
IMPACT FEE PARKS ¤1,199.12 07/27/2021
IMPACT FEE SCHOOL ¤3,600.00 07/27/2021
IMPACT FEE TRANSPORTATION ¤1,718.00 07/27/2021
MECHANICAL FEE ¤223.20 07/27/2021
WATER -IRRIGATION INSPECTION ¤25.00 07/27/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 07/27/2021
PLAN CHECK FEE ¤108.80 07/27/2021
PLUMBING FEE ¤223.20 07/27/2021
NEW RESIDENTIAL INSPECTIONS ¤544.00 07/27/2021
SITE PLAN 20 ¤20.00 07/27/2021
SURCHARGE FS 533.721 ¤2.00 07/27/2021
SURCHARGE - FS 468.631 ¤2.00 07/27/2021
Fees Total Due: ¤0.00 Total Paid: ¤13,478.94