Permit #2021071172

Permit Details

Status: COED

Parcel Id: 07-11-31-7009-00040-0060
Total Square Footage: 2983 sqft
Block: 00040
Subdivision: 2208 - SECTION 9-FLORIDA PARK
Job Phone: 904-407-3634
Location Address: 5 FARR PL
Type: RF - REROOF
Issue Date: 07/28/2021
NOC: RECORDED
Applicant name: RUBEN DIONISIO LAVARIAS
Owner: GRIFFIS ZACHARY L & HANNAH GRIFFIS H&W

Address

5 FARR PLACE

PALM COAST, FL 32137

Lot: 0060
Contracted Stated Job Value: ¤16,500.00
Job Description: Re-Roof /42 Squares/7/12 pitch/ Owens Corning Duration Shingles/ FL 10674R13
Type: CN

Contractor

TURNKEY ROOFING OF FLORIDA
Status Location Address State License Number Phone
INACTIVE

9838 OLD BAYMEADOWS RD #322

JACKSONVILLE, FL 32256

CCC1331925 (Exp: 08/31/2026) 904-407-3634

Inspection History

Type Request Date Result Inspector
ROOF FINAL 10/06/2021 FINAL APPROVED DCUSHING
ROW - FINAL INSPECTION 09/15/2021 APPROVED KRUTH
ROW - FINAL INSPECTION 09/03/2021 APPROVED KRUTH
ROOF IN PROGRESS- MIDROOF 09/02/2021 APPROVED RMARTIN
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION Midroof destructive inspection required… roof was completed and shingles were applied prior to midroof inspection. Contractor will need to be onsite for next midroof inspection with approved documents, roofing worksheet, and astm and installation documents for a destructive inspection with materials and personnel on site to remove shingles and replace as directed by inspector. 8-31-21... 9/2/21 approved Midroof inspection was missed and shingles were applied prior to approval. Met crew onsite for destructive inspection and found underlayment did not meet the requirements for spacing on nails and ecceeded spacing between some rows where crew opened the roof, and nails were not 12 OC where they needed to be and were not 6 OC at overlaps). Owens Corning Shingles not nailed as per manufacturer details. Must remove all applied shingles and replace underlayment in that area and place up to 25% shingles for inspection.
ROOF IN PROGRESS- MIDROOF 08/31/2021 Disapproved - NO FEE WMILLER
Note: THIS IS A REINSPECTION Midroof destructive inspection required… roof was completed and shingles were applied prior to midroof inspection. Contractor will need to be onsite for next midroof inspection with approved documents, roofing worksheet, and astm and installation documents for a destructive inspection with materials and personnel on site to remove shingles and replace as directed by inspector. 8-31-21... Midroof inspection was missed and shingles were applied prior to approval. Met crew onsite for destructive inspection and found underlayment did not meet the requirements for spacing on nails and ecceeded spacing between some rows where crew opened the roof, and nails were not 12 OC where they needed to be and were not 6 OC at overlaps). Owens Corning Shingles not nailed as per manufacturer details. Must remove all applied shingles and replace underlayment in that area and place up to 25% shingles for inspection.
DEMOLITION 08/30/2021 CANCELLED BY INSPECTOR WMILLER
Note: wrong inspection called and was called in for the wrong per Joe
ROOF IN PROGRESS- MIDROOF 08/26/2021 Disapproved - NO FEE WMILLER
Note: Midroof destructive inspection required… roof was completed and shingles were applied prior to midroof inspection. Contractor will need to be onsite for next midroof inspection with approved documents, roofing worksheet, and astm and installation documents for a destructive inspection with materials and personnel on site to remove shingles and replace as directed by inspector.
ROOF AFFIDAVIT 08/17/2021 APPROVED STHOMAS

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMIN FEE ¤20.00 07/28/2021
BUILDING DISCOUNT 100% (¤60.00) 07/28/2021
INSPECTION 40 ¤40.00 07/28/2021
SURCHARGE FS 533.721 ¤2.00 07/28/2021
SURCHARGE - FS 468.631 ¤2.00 07/28/2021
Fees Total Due: ¤0.00 Total Paid: ¤4.00