Permit #2021080564
Permit Details
Status: COED
| Parcel Id: 07-11-31-7037-00910-0030 |
| CONDITIONED SPACE: 2616 sqft |
| GARAGE: 564 sqft |
| OPENED PORCH (WITH ROOF) : 407 sqft |
| OPENED PORCH (WITH ROOF) : 275 sqft |
| Total Square Footage: 3862 sqft |
| Block: 00910 |
| Subdivision: 2176 - SECTION 37-LAKEVIEW |
| Job Phone: (386)445-9393 |
| Location Address: 57 LAKE SUCCESS DR |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| Issue Date: 09/22/2021 |
| NOC: RECORDED |
| Applicant name: ANTONIO JR AMARAL |
| Owner: AMARAL HOMES & POOLS LLC |
|
Address 1370 PALM HARBOR PKWY PALM COAST, FL 32137 |
| Lot: 0030 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: SINGLE FAMILY RESIDENCE |
| Type: CN |
Contractor
AMARAL HOMES & POOLS, LLC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
13 Utility Drive PALM COAST, FL 32137 |
CBC058062 (Exp: 08/31/2026) | (386)445-9393 |
Sub Contractors
RICHARD H SIMMONS JR
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
PO BOX 1963 BUNNELL, FL 32110 |
ES12001217 (Exp: 08/31/2026) | 386-437-0607 | 386-437-1847 |
JONATHAN M PEARSON
| Status | Location Address | State License Number | Phone | Fax |
| ACTIVE |
209 N FORSYTH ST BUNNELL, FL 32110 |
CFC1425941 (Exp: 08/31/2026) | 386-597-0944 | 386-437-4996 |
THOMAS A REGULA
| Status | Location Address | State License Number | Phone | Fax |
| INACTIVE |
11320 PHILLIPS PKWY DRIVE E JACKSONVILLE, FL 32256 |
CMC1250075 (Exp: 08/31/2026) | 904-278-0339 | 904-278-0366 |
ANTONIO AMARAL JR
| Status | Location Address | State License Number |
| ACTIVE |
1370 PALM HARBOR PKWY PALM COAST, FL 32137 |
CCC058004 (Exp: 08/31/2026) |
Inspection History
| Type | Request Date | Result | Inspector |
| BLD - BUILDING FINAL | 11/14/2023 | FINAL APPROVED | JSTEWART |
| Note: 11/13/2023 - PREVIOUS INSPECTION NOTES 11/13/23- 1. Bedrooms need a Light or a Outlet that is controlled by a switch for a light. 2. Attic access light needs a bulb please. 3. Please obtain revision of energy calcs for ODU installed. ( 60/50 ). 4. 105.11 Notice of termite protection, 5. INSULATION CERTIFICATE R303.1.1.2 | |||
| BLD - BUILDING FINAL | 11/13/2023 | Disapproved - NO FEE | JSTEWART |
| Note: 11/13/23- 1. Bedrooms need a Light or a Outlet that is controlled by a switch for a light. 2. Attic access light needs a bulb please. 3. Please obtain revision of energy calcs for ODU installed. ( 60/50 ). 4. 105.11 Notice of termite protection, 5. INSULATION CERTIFICATE R303.1.1.2 | |||
| U -UTILITY RESIDENTIAL FINAL | 11/13/2023 | FINAL APPROVED | DHANEY |
| Note: 10/5/2023 - PREVIOUS INSPECTION NOTES Pep tank pump not working - alarm is ok . Advised sewer Dept. . | |||
| WALL SHEATHING | 11/13/2023 | APPROVED - AS NOTED | JSTEWART |
| Note: 11/13/23- Not needed | |||
| U -UTILITY RESIDENTIAL FINAL | 10/05/2023 | Disapproved - NO FEE | DHANEY |
| Note: Pep tank pump not working - alarm is ok . Advised sewer Dept. . | |||
| U-CROSS CONNECTION | 10/05/2023 | APPROVED | DHANEY |
| ROW - FINAL APRON (AFTER POUR) | 09/26/2023 | APPROVED | RGROSS |
| ROW- FINAL SURVEY/GRADING CERTIFICATION | 09/26/2023 | APPROVED - AS NOTED | RGROSS |
| Note: Drainage conveyance graded to flow both to the front and back. Large drainage ditch in the rear and surrounding topography made more sense. | |||
| ROW FIELD SURVEY /GRADING CERTIFICATION | 09/26/2023 | APPROVED | RGROSS |
| Note: Inspector Notes from Inspection 9463 Drainage conveyance graded to flow both to the front and back. Large drainage ditch in the rear and surrounding topography made more sense. | |||
| ROW - STORMWATER FINAL | 09/26/2023 | APPROVED | RGROSS |
| Note: See note on Final Survey B drainage pattern. | |||
| ELECTRIC - EARLY POWER | 03/27/2023 | APPROVED - AS NOTED | TSTAUFFACHER |
| Note: 03/27/2023_ approved released to FPL at 2:27 PM 3/24/2023 - PREVIOUS INSPECTION NOTES | |||
| ELECTRIC - EARLY POWER | 03/24/2023 | CANCELLED BY APPLICANT | RMARTIN |
| ROW- PRE-APRON (PRE-POUR) | 02/23/2023 | APPROVED | PFLANAGAN |
| Note: IT'S THE CONTRACTORS RESPONSIBILITY TO CHECK THE CULVERT PIPE ELEVATIONS BEFORE POURING CONCRETE FOR THE DRIVEWAY. --------------------------------------------------------------------------------- 2/21/2023 - PREVIOUS INSPECTION NOTES THE RIGHT SIDE INVERT OF THE CULVERT IS OUT OF TOLERANCE WITH THE SWALE PLAN DETAIL --------------------------------------------------------------------------------- 2/13/2023 - PREVIOUS INSPECTION NOTES THIS IS NOT READY FOR AN INSPECTION. PLEASE SEE PHOTOS DATED 2/13/2023 FOR THE INSPECTION RESULTS | |||
| ROW- PRE-APRON (PRE-POUR) | 02/21/2023 | Disapproved -FEE REQUIRED | PFLANAGAN |
| Note: THE RIGHT SIDE INVERT OF THE CULVERT IS OUT OF TOLERANCE WITH THE SWALE PLAN DETAIL --------------------------------------------------------------------------------- 2/13/2023 - PREVIOUS INSPECTION NOTES THIS IS NOT READY FOR AN INSPECTION. PLEASE SEE PHOTOS DATED 2/13/2023 FOR THE INSPECTION RESULTS | |||
| ROW- PRE-APRON (PRE-POUR) | 02/13/2023 | Disapproved -FEE REQUIRED | PFLANAGAN |
| Note: THIS IS NOT READY FOR AN INSPECTION. PLEASE SEE PHOTOS DATED 2/13/2023 FOR THE INSPECTION RESULTS | |||
| U - SEWER TIE IN | 01/10/2023 | APPROVED | MGIBSON |
| GRAVITY SEWER TEST | 01/10/2023 | APPROVED | MGIBSON |
| PEP TANK INSTALLATION REQUEST | 12/15/2022 | APPROVED | CSTONE |
| LATH/BRICK/ WATER BARRIER | 10/28/2022 | APPROVED | FWILLIS |
| Note: Inspector Notes from Inspection 2490 Inspector Notes from Inspection 2420 9/20/2022 - PREVIOUS INSPECTION NOTES 1. Failed 5' head pressure test FBC 2503.5.1 2. Slab needs to be sealed where electrical conduit runs from wall to island in kitchen 3. All thread not attached in garage wood load bearing wall 4. Front door missing glass 10/13/22 2. Front door missing glass 10/21/22 check glass on front door at final | |||
| INSULATION | 10/21/2022 | APPROVED - AS NOTED | RMARTIN |
| Note: Inspector Notes from Inspection 2420 9/20/2022 - PREVIOUS INSPECTION NOTES 1. Failed 5' head pressure test FBC 2503.5.1 2. Slab needs to be sealed where electrical conduit runs from wall to island in kitchen 3. All thread not attached in garage wood load bearing wall 4. Front door missing glass 10/13/22 2. Front door missing glass 10/21/22 check glass on front door at final | |||
| ALL ROUGH | 10/13/2022 | APPROVED - AS NOTED | MKRASKI |
| Note: 9/20/2022 - PREVIOUS INSPECTION NOTES 1. Failed 5' head pressure test FBC 2503.5.1 2. Slab needs to be sealed where electrical conduit runs from wall to island in kitchen 3. All thread not attached in garage wood load bearing wall 4. Front door missing glass 10/13/22 1. Failed 5' head pressure FBC 2503.5.1 2. Front door missing glass Check on insulation Stopped inspection | |||
| ALL ROUGH | 09/20/2022 | Disapproved - NO FEE | MKRASKI |
| Note: 1. Failed 5' head pressure test FBC 2503.5.1 2. Slab needs to be sealed where electrical conduit runs from wall to island in kitchen 3. All thread not attached in garage wood load bearing wall 4. Front door missing glass Stopped inspection | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 09/19/2022 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION VIEWED GUSSETS AND PLY WOOD ABOVE TRUSS'S ALL ARE GOOD. WAITING FOR ENGINEERING. | |||
| ROOF VALLEY & METAL | 09/19/2022 | APPROVED | FWILLIS |
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | 03/24/2022 | Disapproved - NO FEE | FWILLIS |
| Note: VIEWED GUSSETS AND PLY WOOD ABOVE TRUSS'S ALL ARE GOOD. WAITING FOR ENGINEERING. | |||
| TIE BEAM / LINTEL | 02/07/2022 | APPROVED | FWILLIS |
| FOUND SURVEY APPROVED (OFFICE) | 12/08/2021 | APPROVED | TBAKER |
| MONOLITHIC SLAB | 11/23/2021 | APPROVED | FWILLIS |
| Note: THIS IS A REINSPECTION | |||
| MONOLITHIC SLAB | 11/22/2021 | CANCELLED BY APPLICANT | FWILLIS |
| PLUMBING 1ST ROUGH UNDERGROUND | 11/16/2021 | APPROVED | MGIBSON |
| WATER METER INSTALLATION REQUEST | 10/01/2021 | APPROVED | CSTONE |
Review History
| Department | Status | Date In | Date Out |
| MECH | COMPLETE | 11/14/2023 | 11/14/2023 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 09/12/2022 | 09/12/2022 |
| Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| BLD | HOLD | 09/09/2022 | 09/12/2022 |
| Note: Held By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM | |||
| BLD | HOLD | 09/06/2022 | 09/07/2022 |
| Note: Held By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM All comments below per the 2020 Florida Building Code PLAN REVIEW COMMENTS: 1. Plans submitted are digitally signed. Copies of an architects stamp is not accepted. Please resubmit signed and sealed drawings from the architect of record. | |||
| ENGIN1 | COMPLETE | 12/07/2021 | 12/08/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 12/07/2021 | 12/07/2021 |
| Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 08/31/2021 | 09/02/2021 |
| Note: Released By: HAROLD ALLEN - - HALLEN@PALMCOASTGOV.COM | |||
| BLD | HOLD | 08/20/2021 | 08/23/2021 |
| Note: Held By: HAROLD ALLEN - - HALLEN@PALMCOASTGOV.COM REVIEW COMMENTS: Repeat Comment Various Product Approvals have multiple approvals. A revision is required to reflect the approval is used (16503.(?) F.S. 553.842. | |||
| ZON | COMPLETE | 08/20/2021 | 08/20/2021 |
| Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 08/20/2021 | 08/27/2021 |
| Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM | |||
| BLD | HOLD | 08/12/2021 | 08/13/2021 |
| Note: Held By: HAROLD ALLEN - - HALLEN@PALMCOASTGOV.COM REVIEW COMMENTS: Various Product Approvals submitted are not current. Please revise the Product Approvals and resubmit. Product Approval for roof tiles are different on the Roofing Worksheet then on the Product Approval listing per F.S. 553.842. | |||
| CUSVC | COMPLETE | 08/12/2021 | 08/19/2021 |
| Note: Released By: ALYSSA ROSCOE - - | |||
| ELEC | COMPLETE | 08/12/2021 | 08/13/2021 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 08/12/2021 | 08/12/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM | |||
| LOCATE | COMPLETE | 08/12/2021 | 08/16/2021 |
| Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 08/12/2021 | 08/13/2021 |
| Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SW1 | COMPLETE | 08/12/2021 | 08/19/2021 |
| Note: Released By: KALEN RUTH - (386)566-1273 - KKRUTH@PALMCOASTGOV.COM | |||
| ZON | HOLD | 08/12/2021 | 08/13/2021 |
| Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM On site plan submited the A/C pad is in the 5' utility easement. Please provide the 2' encroachment license agreement for the mechanical equiptment. Must be signed by all persons on the deed, witnessed and notarized. | |||
| SWALE | COMPLETE | 08/12/2021 | 11/30/2021 |
| Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| EXTENSION | ¤40.00 | 11/14/2023 |
| SW ENG REINSPECTION 30 | ¤30.00 | 11/14/2023 |
| SW ENG REINSPECTION 30 | ¤30.00 | 11/14/2023 |
| SW ENG - REVIEW 20 | ¤20.00 | 09/22/2021 |
| SW ENG RES REVIEW 200 | ¤200.00 | 09/22/2021 |
| 3% TRANS IMPACT FEE CREDIT | (¤51.54) | 09/22/2021 |
| SEWER CREDIT | (¤1,466.00) | 09/22/2021 |
| SEWER INSPECTION | ¤25.00 | 09/22/2021 |
| SEWER CAPITAL FACILITY | ¤4,664.55 | 09/22/2021 |
| WATER CAPITAL FACILITY FEE | ¤3,424.45 | 09/22/2021 |
| SITE PLAN 30 | ¤30.00 | 09/22/2021 |
| METER - DEPOSIT | ¤60.00 | 09/22/2021 |
| WATER- TURN ON | ¤25.00 | 09/22/2021 |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | 09/22/2021 |
| INSPECTION - RESIDENTIAL | ¤937.75 | 09/22/2021 |
| PLAN REVIEW - RESIDENTIAL | ¤265.98 | 09/22/2021 |
| CONNECTION FEES | ¤1,017.83 | 09/22/2021 |
| 3% FIRE IMPACT FEE CREDIT | (¤11.01) | 09/22/2021 |
| IMPACT FEE FIRE | ¤367.00 | 09/22/2021 |
| IMPACT FEE PARKS | ¤1,199.12 | 09/22/2021 |
| IMPACT FEE SCHOOL | ¤3,600.00 | 09/22/2021 |
| RECORDING FEE REIMBURSE DOC | ¤35.50 | 09/22/2021 |
| IMPACT FEE TRANSPORTATION | ¤1,718.00 | 09/22/2021 |
| WATER -IRRIGATION INSPECTION | ¤25.00 | 09/22/2021 |
| 3% PARKS IMPACT FEE CREDIT | (¤35.97) | 09/22/2021 |
| SURCHARGE FS 533.721 | ¤12.96 | 09/22/2021 |
| SURCHARGE - FS 468.631 | ¤19.44 | 09/22/2021 |
| SW ENG - FOUNDATION SURVEY | ¤20.00 | 09/22/2021 |
| SW ENG INSPECTION 60 | ¤60.00 | 09/22/2021 |
| SW ENG PRE APRON | ¤30.00 | 09/22/2021 |
| Fees | Total Due: ¤0.00 | Total Paid: ¤16,323.06 |