Permit #2021080911

Permit Details

Status: FINAL

Block: 00000
Subdivision: -
Job Phone: 407-916-7235
Location Address: 100 ADVENTHEALTH WAY
Type: CSD - COMMERCIAL SITE DEVELOPMENT
Issue Date: 09/14/2021
NOC: RECORDED
Applicant name: BRUCE ROBERT ADAMS
Owner: MEMORIAL HOSPITAL-FLAGLER INC

Address

60 MEMORIAL MEDICAL PKWY

PALM COAST, FL 32164

Lot: 0100
Job Description: SITE WORK- ADVENTHEALTH HOSPITAL
Type: CN

Contractor

THE ROBINS & MORTON GROUP
Status Location Address Mailing Address State License Number Phone
ACTIVE

423 S KELLER RD

ORLANDO, FL 32810

#200

ORLANDO, FL 32810

CGC1523017 (Exp: 08/31/2026) 407-916-7235

Inspection History

Type Request Date Result Inspector
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 06/08/2023 APPROVED - AS NOTED LFITZGERALD
Note: Eastbound pad now correct- other outstanding items to be installed by end of day per Chelsea 6/6/2023 - PREVIOUS INSPECTION NOTES Eastbound pad now demo'd-pouring slab tomorrow-will reinspect/missing pipe stands for both backflow preventors 5/31/2023 - PREVIOUS INSPECTION NOTES NOTE-MIN CLEARANCE FOR AIR RELEASE VALVE -EASTBOUND BACKFLOW -NOT CORRECT(9IN VERSUS 12IN)/PIPE STANDS NOT YET INSTALLED ON BOTH BACKFLOW-POTABLE DEVICE 5/4/2023 - PREVIOUS INSPECTION NOTES water line tone -satisfactory(Gemstone) 2/2/2023 - PREVIOUS INSPECTION NOTES 10 inch bore mandrel pulled -ok and pressure test ok 1/20/2023 - PREVIOUS INSPECTION NOTES 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 06/06/2023 PARTIALLY APPROVED LFITZGERALD
Note: Eastbound pad now demo'd-pouring slab tomorrow-will reinspect/missing pipe stands for both backflow preventors 5/31/2023 - PREVIOUS INSPECTION NOTES NOTE-MIN CLEARANCE FOR AIR RELEASE VALVE -EASTBOUND BACKFLOW -NOT CORRECT(9IN VERSUS 12IN)/PIPE STANDS NOT YET INSTALLED ON BOTH BACKFLOW-POTABLE DEVICE 5/4/2023 - PREVIOUS INSPECTION NOTES water line tone -satisfactory(Gemstone) 2/2/2023 - PREVIOUS INSPECTION NOTES 10 inch bore mandrel pulled -ok and pressure test ok 1/20/2023 - PREVIOUS INSPECTION NOTES 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
MAINT BOND ACCEPTANCE (OFFICE) 06/06/2023 APPROVED DRAMIREZ
CLOSE OUT DOCUMENTS 06/06/2023 APPROVED DRAMIREZ
LDSC- LANDSCAPE FINAL 06/05/2023 FINAL APPROVED RPICATAGI
Note: Approval is conditioned on the following plant replacementd 62 Loropatelam chinensis 'Ruby" @ 3 gal size on south side of of east parking area 2 Podocarpus macrophylla # 30" ht in healing garden 1 Sabal Palmetto at northeast entry
UC-FINAL SITE INSPECTION 06/05/2023 APPROVED - AS NOTED LFITZGERALD
Note: 1)items to be comopleted by Halifax and 4C'S -NOTED IN E-MAIL TO THEM. ALSO,NOTE TO EOR-ALLIANT-drainage issue at Bridgehaven to be monitored and corrections to be made if neccessary
ROW - FINAL INSPECTION 06/05/2023 APPROVED - AS NOTED LFITZGERALD
Note: Westbound ROW-north side where water tap was made-seed/straw all bare areas and install 2 signs along Eastbound and remove 2MOT signs at westbound
LDSC-IRRIGATION FINAL 06/02/2023 CANCELLED BY INSPECTOR RPICATAGI
Note: Landscape AsBuilts have been submitted and reviewed
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 06/01/2023 APPROVED DRAMIREZ
Note: Approved under 5427
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 05/31/2023 APPROVED DRAMIREZ
Note: As-builts approved under application #5450
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 05/31/2023 PARTIALLY APPROVED LFITZGERALD
Note: NOTE-MIN CLEARANCE FOR AIR RELEASE VALVE -EASTBOUND BACKFLOW -NOT CORRECT(9IN VERSUS 12IN)/PIPE STANDS NOT YET INSTALLED ON BOTH BACKFLOW-POTABLE DEVICE 5/4/2023 - PREVIOUS INSPECTION NOTES water line tone -satisfactory(Gemstone) 2/2/2023 - PREVIOUS INSPECTION NOTES 10 inch bore mandrel pulled -ok and pressure test ok 1/20/2023 - PREVIOUS INSPECTION NOTES 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
U-GREASE INTERCEPTOR FLOW/DYE TESTED 05/23/2023 APPROVED - AS NOTED LFITZGERALD
Note: assisted by Don who was in kitchen on 2nd floor placing dye in all proposed grease compartments
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 05/22/2023 APPROVED FWILLIS
BLD- ADA PARKING 05/22/2023 APPROVED FWILLIS
BLD - ADA COMPLIANT 05/22/2023 APPROVED FWILLIS
BLD- ADA SIGNAGECONTROL 05/22/2023 APPROVED FWILLIS
BLD- ADA VEHICULAR WAY 05/22/2023 APPROVED FWILLIS
BLD - ADA SIGNAGE- INFOR/DIRECT 05/22/2023 APPROVED FWILLIS
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 05/22/2023 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION-edge line along westbound turn lane was supposed to be white not yellow according to the approved plans-discussed with city traffic engineer-Michael G.-will be allowed/missing(2)signs in eastbound ROW-that were there prior to turning into a turn lane:(1) stating DO NOT ENTER and OTHER facing Goodwill stating Right turn only(was installed when Goodwill was constructed-will be noted on Final punch list and TBD-ADA mat for concrete landing next to existing westbound tree and possible STOP sign just west of ambulance parking where there is a stop bar/STOP written on asphalt/possible stop sign at stop bar across from Emergency entrance/possible stop sign on concrete parking oposite loading dock where thwer is a stop bar only.ALL POSSIBLE AND REQUIRED ITEMS TO BE ADRESED IN FINAL PUNCH OUT. started paving now at North east parking bay over storm retention
UROW- CURBING & GUTTER 05/11/2023 APPROVED - AS NOTED LFITZGERALD
Note: last area at Market now completed 3/29/2023 - PREVIOUS INSPECTION NOTES curbing at SW/SE Entrances 2/7/2023 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION continue with curbing at west areas start placing modified F curb at North East parking rea
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 05/11/2023 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION -All areas now paved/sodded a couple of areas need repair-Francisco informed
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 05/11/2023 APPROVED - AS NOTED LFITZGERALD
Note: last area between MOB/Hospital completed 4/11/2023 - PREVIOUS INSPECTION NOTES sidewalks at:Bridgehaven/westbound entrance area/east tie in to existing at SEentrance 3/28/2023 - PREVIOUS INSPECTION NOTES Not ready 2/7/2023 - PREVIOUS INSPECTION NOTES heliport pad now with concrete 2/7/2023 - PREVIOUS INSPECTION NOTES sidewalks along west side and misc areas 12/7/2022 - PREVIOUS INSPECTION NOTES sidewalk along eastbound side/other misc. along buildinf-eastside
UROW -FINAL GRADE PRIOR SOD 05/04/2023 FINAL APPROVED LFITZGERALD
Note: 3/28/2023 - PREVIOUS INSPECTION NOTES Not ready for this inspection.
U-WATER METER INSTALLATION/VERIFICATION 05/04/2023 APPROVED LFITZGERALD
Note: 4/21/2023 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION FDEP clearence now approved THIS IS A REINSPECTION main now installed from BFP-eastbound to MOB-North side/Pig flushed from BFP-Eastbound side to NECorner of hospital Estbound side-2in potable RPZ installed/waiting on 8in meter(s) for the 8in RPZ(they were not in the RPZ assembly(were not ordered
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 05/04/2023 PARTIALLY APPROVED LFITZGERALD
Note: water line tone -satisfactory(Gemstone) 2/2/2023 - PREVIOUS INSPECTION NOTES 10 inch bore mandrel pulled -ok and pressure test ok 1/20/2023 - PREVIOUS INSPECTION NOTES 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
UC-MOT MAINTENANCE OF TRAFFIC 05/03/2023 APPROVED - AS NOTED LFITZGERALD
Note: all ROW/Turn lanes along roadways adjacent to site now completed 4/4/2023 - PREVIOUS INSPECTION NOTES 4-3=westbound inside lane closure for Market ALF entrance/2nd lift turn lane;4-4 eastbound inside lane closure for grade shoulder with Gradall 3/31/2023 - PREVIOUS INSPECTION NOTES Eastbound-left thru lane closed in order pave 2nd lift -hospital turn lane into SE entrance;Westbound-left thru lane closed in order to reconstrucut Market ALF Entrance-base only 12/13/2022 - PREVIOUS INSPECTION NOTES lane closure-left lane-now in progress for eastbound PCPKWY for new turn lane
UC-SUBSTANTIAL WALK-THRU 05/03/2023 APPROVED - AS NOTED LFITZGERALD
Note: walk thru with-4C's,Alliant, Halifax and Robbins-punch list generated for appropriate parties
UC- PRELIMINARY AS-BUILTS 05/03/2023 APPROVED - AS NOTED LFITZGERALD
Note: all but water as-builts submitted electronically for inspector review-Robbins to submit;paper copy for all as-builts submitted for walk thru
LDSC-PRE-PLANTING TREE QUALITY 04/26/2023 APPROVED - AS NOTED RPICATAGI
Note: 4/18/2023 - PREVIOUS INSPECTION NOTES Sabal Palms
LDSC- LANDSCAPE / IRRIGATION AS-BUILT 04/21/2023 CANCELLED BY APPLICANT LFITZGERALD
Note: not ready yet
U-GRAVITY SEWER INSTALL/TESTING 04/21/2023 APPROVED - AS NOTED LFITZGERALD
Note: FDEP clearance now approved 3/9/2023 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION finish TV/Mandrel/Air Test for MH 10-11,7-8,8-9 THIS IS A REINSPECTION -started relaying from mh 10 to mh11 THIS IS A REINSPECTION air test for mh 2,3,4,5 stub out,6,7 THIS IS A REINSPECTION mh10 installed/tied into existing 10in line THIS IS A REINSPECTION 8in now installed from mh3 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
PROJECT CLOSE OUT MEETING (386-986-3750) 04/21/2023 APPROVED - AS NOTED LFITZGERALD
Note: 2nd meeting-Chris -Alliant now attended with same folks as 1st time-all feel confident will be able to achieve successful close out now that all issues have been discussed 3/9/2023 - PREVIOUS INSPECTION NOTES city staff present along with Chelsea-utility contractor.Jack with Halifax and Jon with Robbins-Morton. EOR =Chris accepted meeting invite but did not attend. All parameters for MOB-TCO and over all site/hospital CO were iscussed. Anothe rmeeting to be scheduled April 17th to facilitate smooth completion of site/building close out.
UC-ASPHALT PRE PLACEMENT 04/21/2023 APPROVED - AS NOTED LFITZGERALD
Note: All asphalt now placed 4/18/2023 - PREVIOUS INSPECTION NOTES now paving center parking areas -east of MOB and Hospital 4/11/2023 - PREVIOUS INSPECTION NOTES no asphalt placement to note?? 4/5/2023 - PREVIOUS INSPECTION NOTES 4-4 pave both lifts at SWentrance 4/4/2023 - PREVIOUS INSPECTION NOTES 4-3=pave Market ALF/westbound turn lanes/2nd lift SEentrance/1st lift of east drive thru road;4-4 paving south/east 1st lift/2nd lifts misc. 3/31/2023 - PREVIOUS INSPECTION NOTES eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
U-WATER METER INSTALLATION/VERIFICATION 04/21/2023 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION FDEP clearence now approved THIS IS A REINSPECTION main now installed from BFP-eastbound to MOB-North side/Pig flushed from BFP-Eastbound side to NECorner of hospital Estbound side-2in potable RPZ installed/waiting on 8in meter(s) for the 8in RPZ(they were not in the RPZ assembly(were not ordered
UC-ASPHALT PRE PLACEMENT 04/18/2023 PARTIALLY APPROVED LFITZGERALD
Note: now paving center parking areas -east of MOB and Hospital 4/11/2023 - PREVIOUS INSPECTION NOTES no asphalt placement to note?? 4/5/2023 - PREVIOUS INSPECTION NOTES 4-4 pave both lifts at SWentrance 4/4/2023 - PREVIOUS INSPECTION NOTES 4-3=pave Market ALF/westbound turn lanes/2nd lift SEentrance/1st lift of east drive thru road;4-4 paving south/east 1st lift/2nd lifts misc. 3/31/2023 - PREVIOUS INSPECTION NOTES eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
LDSC-PRE-PLANTING TREE QUALITY 04/18/2023 PARTIALLY APPROVED LFITZGERALD
Note: Sabal Palms
UC-ASPHALT PRE PLACEMENT 04/11/2023 PARTIALLY APPROVED LFITZGERALD
Note: no asphalt placement to note?? 4/5/2023 - PREVIOUS INSPECTION NOTES 4-4 pave both lifts at SWentrance 4/4/2023 - PREVIOUS INSPECTION NOTES 4-3=pave Market ALF/westbound turn lanes/2nd lift SEentrance/1st lift of east drive thru road;4-4 paving south/east 1st lift/2nd lifts misc. 3/31/2023 - PREVIOUS INSPECTION NOTES eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 04/11/2023 PARTIALLY APPROVED LFITZGERALD
Note: sidewalks at:Bridgehaven/westbound entrance area/east tie in to existing at SEentrance 3/28/2023 - PREVIOUS INSPECTION NOTES Not ready 2/7/2023 - PREVIOUS INSPECTION NOTES heliport pad now with concrete 2/7/2023 - PREVIOUS INSPECTION NOTES sidewalks along west side and misc areas 12/7/2022 - PREVIOUS INSPECTION NOTES sidewalk along eastbound side/other misc. along buildinf-eastside
UC-ASPHALT PRE PLACEMENT 04/05/2023 PARTIALLY APPROVED LFITZGERALD
Note: 4-4 pave both lifts at SWentrance 4/4/2023 - PREVIOUS INSPECTION NOTES 4-3=pave Market ALF/westbound turn lanes/2nd lift SEentrance/1st lift of east drive thru road;4-4 paving south/east 1st lift/2nd lifts misc. 3/31/2023 - PREVIOUS INSPECTION NOTES eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
LDSC-PRE-PLANTING TREE QUALITY 04/05/2023 APPROVED RPICATAGI
Note: 3/30/2023 1:46:54 PM- PREVIOUS INSPECTION NOTES 2/14/2023 - PREVIOUS INSPECTION NOTES Rick-myself oaks/magnolia's/crepe's/japanese privot's 3/30/23 - No truck loaded with trees was present on the site.
UC-ASPHALT PRE PLACEMENT 04/04/2023 PARTIALLY APPROVED LFITZGERALD
Note: 4-3=pave Market ALF/westbound turn lanes/2nd lift SEentrance/1st lift of east drive thru road;4-4 paving south/east 1st lift/2nd lifts misc. 3/31/2023 - PREVIOUS INSPECTION NOTES eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
UC-MOT MAINTENANCE OF TRAFFIC 04/04/2023 PARTIALLY APPROVED LFITZGERALD
Note: 4-3=westbound inside lane closure for Market ALF entrance/2nd lift turn lane;4-4 eastbound inside lane closure for grade shoulder with Gradall 3/31/2023 - PREVIOUS INSPECTION NOTES Eastbound-left thru lane closed in order pave 2nd lift -hospital turn lane into SE entrance;Westbound-left thru lane closed in order to reconstrucut Market ALF Entrance-base only 12/13/2022 - PREVIOUS INSPECTION NOTES lane closure-left lane-now in progress for eastbound PCPKWY for new turn lane
UC-ASPHALT PRE PLACEMENT 03/31/2023 PARTIALLY APPROVED LFITZGERALD
Note: eastbound turn lane-2nd lift/SEentranceto both lifts to part of SWentrance-1st lift 3/30/2023 - PREVIOUS INSPECTION NOTES now paving 2nd lift-SWentr and SEentr.-1st lift-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
BLD - UNDERGROUND SITE LIGHTING CONDUITS 03/31/2023 APPROVED RMARTIN
BLD - SITE STRUCTURE - TRASH DUMPSTER 03/31/2023 APPROVED FWILLIS
UC-MOT MAINTENANCE OF TRAFFIC 03/31/2023 PARTIALLY APPROVED LFITZGERALD
Note: Eastbound-left thru lane closed in order pave 2nd lift -hospital turn lane into SE entrance;Westbound-left thru lane closed in order to reconstrucut Market ALF Entrance-base only 12/13/2022 - PREVIOUS INSPECTION NOTES lane closure-left lane-now in progress for eastbound PCPKWY for new turn lane
BLD - SITE LIGHTING-PLACEMENT/FOUNDATION 03/30/2023 APPROVED RMARTIN
Note: 3/29/2023 - PREVIOUS INSPECTION NOTES
LDSC-PRE-PLANTING TREE QUALITY 03/30/2023 PARTIALLY APPROVED RPICATAGI
Note: 2/14/2023 - PREVIOUS INSPECTION NOTES Rick-myself oaks/magnolia's/crepe's/japanese privot's 3/30/23 - No truck loaded with trees was present on the site.
UC-ASPHALT PRE PLACEMENT 03/30/2023 PARTIALLY APPROVED LFITZGERALD
Note: now paving 2nd lift-SWentr and misc areas in west parking-Cal tech on site 3/29/2023 - PREVIOUS INSPECTION NOTES continuing on 2nd lift west parking areas/Orielly entrance
UC-ASPHALT PRE PLACEMENT 03/29/2023 PARTIALLY APPROVED LFITZGERALD
Note: continuing on 2nd lift west parking areas/Orielly entrance
UROW- CURBING & GUTTER 03/29/2023 PARTIALLY APPROVED LFITZGERALD
Note: curbing at SW/SE Entrances 2/7/2023 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION continue with curbing at west areas start placing modified F curb at North East parking rea
BLD - SITE LIGHTING-POLE SET/FIXTURE 03/29/2023 APPROVED RMARTIN
BLD - SITE LIGHTING-PLACEMENT/FOUNDATION 03/29/2023 CANCELLED BY APPLICANT RMARTIN
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 03/28/2023 CANCELLED BY APPLICANT JHARDING
Note: Not ready 2/7/2023 - PREVIOUS INSPECTION NOTES heliport pad now with concrete 2/7/2023 - PREVIOUS INSPECTION NOTES sidewalks along west side and misc areas 12/7/2022 - PREVIOUS INSPECTION NOTES sidewalk along eastbound side/other misc. along buildinf-eastside
UROW -FINAL GRADE PRIOR SOD 03/28/2023 CANCELLED BY APPLICANT JHARDING
Note: Not ready for this inspection.
UC-ASPHALT PRE PLACEMENT 03/28/2023 APPROVED JHARDING
Note: 3/24/2023 - PREVIOUS INSPECTION NOTES now paving new O'Rielly entrance-in part-misc. areas in west parking areas 3/1/2023 - PREVIOUS INSPECTION NOTES now paving NW entrance/thru road east side/SEparking area/NW parking area-informed Jack-HPI- of required asphalt placement monotoring/obtaining samples for analysis
UC-ASPHALT PRE PLACEMENT 03/24/2023 PARTIALLY APPROVED LFITZGERALD
Note: now paving new O'Rielly entrance-in part-misc. areas in west parking areas 3/1/2023 - PREVIOUS INSPECTION NOTES now paving NW entrance/thru road east side/SEparking area/NW parking area-informed Jack-HPI- of required asphalt placement monotoring/obtaining samples for analysis
PROJECT CLOSE OUT MEETING (386-986-3750) 03/09/2023 PARTIALLY APPROVED LFITZGERALD
Note: city staff present along with Chelsea-utility contractor.Jack with Halifax and Jon with Robbins-Morton. EOR =Chris accepted meeting invite but did not attend. All parameters for MOB-TCO and over all site/hospital CO were iscussed. Anothe rmeeting to be scheduled April 17th to facilitate smooth completion of site/building close out.
U-GRAVITY SEWER INSTALL/TESTING 03/09/2023 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION finish TV/Mandrel/Air Test for MH 10-11,7-8,8-9 THIS IS A REINSPECTION -started relaying from mh 10 to mh11 THIS IS A REINSPECTION air test for mh 2,3,4,5 stub out,6,7 THIS IS A REINSPECTION mh10 installed/tied into existing 10in line THIS IS A REINSPECTION 8in now installed from mh3 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
UC-ASPHALT PRE PLACEMENT 03/01/2023 PARTIALLY APPROVED LFITZGERALD
Note: now paving NW entrance/thru road east side/SEparking area/NW parking area-informed Jack-HPI- of required asphalt placement monotoring/obtaining samples for analysis
U-WATER MAIN DISINFECTION 02/21/2023 APPROVED - AS NOTED LFITZGERALD
Note: Bore pipe plus now disinfected on Thursday-FEB.9TH by Phil Story-photos recieved
U-WATER MAIN DISINFECTION SAMPLING 02/21/2023 APPROVED - AS NOTED LFITZGERALD
Note: BORE PIPE PLUS-Sampled day 1 on Monday-city holiday-photos recieved-Herb/Day 2 now sampled
U-WATER MAIN DISINFECTION 02/16/2023 APPROVED - AS NOTED LFITZGERALD
Note: Now bore pipe /fittings/pvc pieces chlorinated by Phil up to westbound BF 12/5/2022 - PREVIOUS INSPECTION NOTES WM now chlorinated from eastbound tap to westbound backflow
UC-DRAINAGE PIPE PLACEMENT/LAMPING 02/15/2023 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION all remaining now installed THIS IS A REINSPECTION-continuing to CB-15 and CB-16 until they cant place due to stuff in the way THIS IS A REINSPECTION -start under ground retention system-NEast area THIS IS A REINSPECTION 60in installed from JMH6 to JMH7/also 15in to JMH 7 from existing THIS IS A REINSPECTION 60 in installed from JMH 5 to JMH 6 THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 02/15/2023 APPROVED - AS NOTED LFITZGERALD
Note: THIS IS A REINSPECTION all remaining now installed THIS IS A REINSPECTION-now continuing with CB-15 and onward until run out of accessible areas THIS IS A REINSPECTION-start under ground retention with CB-12 THIS IS A REINSPECTION- JMH 7 now installed THIS IS A REINSPECTION JMH5 and JMH6 now installed THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
LDSC-PRE-PLANTING TREE QUALITY 02/14/2023 PARTIALLY APPROVED LFITZGERALD
Note: inspected by Rick-myself oaks/magnolia's/crepe's/japanese privot's
LANDSCAPE PRE-CONSTRUCTION MEETING 02/14/2023 APPROVED - AS NOTED LFITZGERALD
Note: Rick and i met with Ryan-Verde Go and discussed install/close out parameters 12/7/2022 - PREVIOUS INSPECTION NOTES
UC-CONSTRUCTION ENTRANCE 02/13/2023 APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 2 are now in , 1 at SW along Bridgehaven and 1 at SE along PalmCoast pkwy eastbound
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 02/07/2023 PARTIALLY APPROVED LFITZGERALD
Note: sidewalks along west side MOB-and misc areas-also along south side streetside/also north side street side 12/7/2022 - PREVIOUS INSPECTION NOTES sidewalk along eastbound side/other misc. along buildinf-eastside
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 02/07/2023 PARTIALLY APPROVED LFITZGERALD
Note: heliport pad now with concrete 2/7/2023 - PREVIOUS INSPECTION NOTES sidewalks along west side and misc areas 12/7/2022 - PREVIOUS INSPECTION NOTES sidewalk along eastbound side/other misc. along buildinf-eastside
UROW- CURBING & GUTTER 02/07/2023 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION continue with curbing at west areas start placing modified F curb at North East parking rea
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 02/02/2023 PARTIALLY APPROVED LFITZGERALD
Note: 10 inch bore mandrel pulled -ok and pressure test ok 1/20/2023 - PREVIOUS INSPECTION NOTES 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 01/20/2023 PARTIALLY APPROVED LFITZGERALD
Note: 10 inch bore installed -westbound/10x8 wet tap done/tie into bore done/pig flush -bore-done 11/30/2022 - PREVIOUS INSPECTION NOTES THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
UC-MOT MAINTENANCE OF TRAFFIC 12/13/2022 PARTIALLY APPROVED LFITZGERALD
Note: lane closure-left lane-now in progress for eastbound PCPKWY for new turn lane
U-WATER MAIN DISINFECTION SAMPLING 12/08/2022 APPROVED - AS NOTED LFITZGERALD
Note: day 2 sampling -sample 4 location(MOB service-FAILED-sample again 12-10-22) 12/7/2022 - PREVIOUS INSPECTION NOTES Day 1 sampling-eastbound BF to westbound BF(5 sample points)
U-WATER MAIN DISINFECTION SAMPLING 12/07/2022 PARTIALLY APPROVED LFITZGERALD
Note: Day 1 sampling-eastbound BF to westbound BF(5 sample points)
LANDSCAPE PRE-CONSTRUCTION MEETING 12/07/2022 CANCELLED BY APPLICANT LFITZGERALD
UROW - FORM BOARD/CONCRETE (NON STRUCTURAL) 12/07/2022 PARTIALLY APPROVED LFITZGERALD
Note: sidewalk along eastbound side/other misc. along buildinf-eastside
U-WATER MAIN DISINFECTION 12/05/2022 PARTIALLY APPROVED LFITZGERALD
Note: WM now chlorinated from eastbound tap to westbound backflow
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 11/30/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION WM now connected to westbound BF/pig flushed to BF/pressure tested from BF to BF THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
U-GREASE INTERCEPTOR INSTALLED/PLUMBED 11/03/2022 APPROVED LFITZGERALD
Note: 11/2/2022 - PREVIOUS INSPECTION NOTES hard /pressureT fittings used in the 4inch pvc infflueny/efflunt piping inside the grease traps-sanitary(sweeping) T'S required per spec. line item 6h-SS 29A literture of utility standards
U-GREASE INTERCEPTOR INSTALLED/PLUMBED 11/02/2022 Disapproved - NO FEE LFITZGERALD
Note: hard /pressureT fittings used in the 4inch pvc infflueny/efflunt piping inside the grease traps-sanitary(sweeping) T'S required per spec. line item 6h
BLD - GREASE INTERCEPTOR PLUMBING & VENTING 11/02/2022 APPROVED MGIBSON
BLD - GREASE INTERCEPTOR VENTING 11/02/2022 APPROVED MGIBSON
U-GREASE INTERCEPTOR PRE-INSTALLATION 10/10/2022 APPROVED - AS NOTED LFITZGERALD
Note: 1-2500 gal grease tank installed with rock on bottom/baffle hole 2ft from btm(1ft required) and 13in from left side wall(required to be in center)-will inspect during plum inspection 10/6/2022 - PREVIOUS INSPECTION NOTES 1 -1500 gal tank installed with rock on bottom
U-GREASE INTERCEPTOR PRE-INSTALLATION 10/06/2022 PARTIALLY APPROVED LFITZGERALD
Note: 1 -1500 gal tank installed with rock on bottom
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 08/10/2022 PARTIALLY APPROVED LFITZGERALD
Note: started paving now at North east parking bay over storm retention
UROW- CURBING & GUTTER 07/21/2022 PARTIALLY APPROVED LFITZGERALD
Note: start placing modified F curb at North East parking rea
U-WATER METER INSTALLATION/VERIFICATION 07/11/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION main now installed from BFP-eastbound to MOB-North side/Pig flushed from BFP-Eastbound side to NECorner of hospital Estbound side-2in potable RPZ installed/waiting on 8in meter(s) for the 8in RPZ(they were not in the RPZ assembly(were not ordered
U-WATER METER INSTALLATION/VERIFICATION 06/16/2022 PARTIALLY APPROVED LFITZGERALD
Note: Estbound side-2in potable RPZ installed/waiting on 8in meter(s) for the 8in RPZ(they were not in the RPZ assembly(were not ordered
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 06/16/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION -8in x 8in wet tap-Eastbound plus 8in pipe tied into RPZ start install of 6in fire/8in potable RPZ-Eastbound side
U-WATER MAIN INSTALLATION/TESTING/BACKFLOW PREVENTOR 06/14/2022 PARTIALLY APPROVED LFITZGERALD
Note: start install of 6in fire/8in potable RPZ-Eastbound side
UC-DRAINAGE PIPE PLACEMENT/LAMPING 06/08/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-continuing to CB-15 and CB-16 until they cant place due to stuff in the way THIS IS A REINSPECTION -start under ground retention system-NEast area THIS IS A REINSPECTION 60in installed from JMH6 to JMH7/also 15in to JMH 7 from existing THIS IS A REINSPECTION 60 in installed from JMH 5 to JMH 6 THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 06/08/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-now continuing with CB-15 and onward until run out of accessible areas THIS IS A REINSPECTION-start under ground retention with CB-12 THIS IS A REINSPECTION- JMH 7 now installed THIS IS A REINSPECTION JMH5 and JMH6 now installed THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
U-GRAVITY SEWER INSTALL/TESTING 06/02/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION -started relaying from mh 10 to mh11 THIS IS A REINSPECTION air test for mh 2,3,4,5 stub out,6,7 THIS IS A REINSPECTION mh10 installed/tied into existing 10in line THIS IS A REINSPECTION 8in now installed from mh3 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
UC-DRAINAGE STRUCT PLACMNT 05/04/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-start under ground retention with CB-12 THIS IS A REINSPECTION- JMH 7 now installed THIS IS A REINSPECTION JMH5 and JMH6 now installed THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 05/04/2022 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION -start under ground retention system-NEast area-DCS-1Stucture THIS IS A REINSPECTION 60in installed from JMH6 to JMH7/also 15in to JMH 7 from existing THIS IS A REINSPECTION 60 in installed from JMH 5 to JMH 6 THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
U-GRAVITY SEWER INSTALL/TESTING 12/22/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION air test for mh 2,3,4,5 stub out,6,7 THIS IS A REINSPECTION mh10 installed/tied into existing 10in line THIS IS A REINSPECTION 8in now installed from mh3 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 12/16/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION mh10 installed/tied into existing 10in line THIS IS A REINSPECTION 8in now installed from mh3 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
UC-DRAINAGE PIPE PLACEMENT/LAMPING 11/17/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 60in installed from JMH6 to JMH7/also 15in to JMH 7 from existing THIS IS A REINSPECTION 60 in installed from JMH 5 to JMH 6 THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 11/16/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- JMH 7 now installed THIS IS A REINSPECTION JMH5 and JMH6 now installed THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 11/09/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 60 in installed from JMH 5 to JMH 6 THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 11/09/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION JMH5 and JMH6 now installed THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE STRUCT PLACMNT 10/29/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- CB1 and CB2 now installed THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 10/29/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- 15in from CB1 and CB2 to JMH1 THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 10/26/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- 24in from CB27 to CB26 continuing up to existing MES/8in drain pipe out of CB26 THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 10/26/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION- CB26 and JMH1 installed THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE STRUCT PLACMNT 10/19/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-JMH4 and CB27installed DCS-1installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 10/19/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION-36in from MES to JMH4 to CB27 MES to DCS-1 installed
UC-DRAINAGE PIPE PLACEMENT/LAMPING 10/14/2021 PARTIALLY APPROVED LFITZGERALD
Note: MES to DCS-1 installed
UC-DRAINAGE STRUCT PLACMNT 10/14/2021 PARTIALLY APPROVED LFITZGERALD
Note: DCS-1installed
U-GRAVITY SEWER INSTALL/TESTING 10/04/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 8in now installed from mh5 to installed mh6 and mh 7 THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 09/30/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 8in now installed from mh4 to installed mh5 THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 09/29/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 8in now installed from mh3 to installed mh4 THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 09/27/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 8in now installed from mh2 to installed mh3 THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 09/22/2021 PARTIALLY APPROVED LFITZGERALD
Note: THIS IS A REINSPECTION 8in now installed from mh1 to installed mh2 sewer mh1 now installed/tied into existing10in sewer main
U-GRAVITY SEWER INSTALL/TESTING 09/21/2021 PARTIALLY APPROVED LFITZGERALD
Note: sewer mh1 now installed/tied into existing10in sewer main
UC-CONSTRUCTION ENTRANCE 09/17/2021 PARTIALLY APPROVED LFITZGERALD
Note: 2 are now in , 1 at SW along Bridgehaven and 1 at SE along PalmCoast pkwy eastbound
LDSC-TREE BARRICADE 09/17/2021 APPROVED LFITZGERALD
ROW - EROSION CONTROL / INLET PROTE/SILT FENCE 09/17/2021 PARTIALLY APPROVED LFITZGERALD
Note: a couple of areas need repair-Francisco informed
PLAN - PRE-CON 386-986-3750 09/13/2021 APPROVED LFITZGERALD

Review History

Department Status Date In Date Out
BLD COMPLETE 08/17/2021 08/18/2021
Note: Released By: PATRICK BUCKLEY - (386)986-3786 - PBUCKLEY@PALMCOASTGOV.COM
ELEC COMPLETE 08/17/2021 08/17/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
PLENG COMPLETE 08/17/2021 08/17/2021
Note: Released By: DENNIS R. LEAP, P.E. - - DLEAP@PALMCOASTGOV.COM
PLLA COMPLETE 08/17/2021 08/18/2021
Note: Released By: DAMARIS RAMIREZ - (386)986-3750 - DRAMIREZ@PALMCOASTGOV.COM
UD1 COMPLETE 08/17/2021 08/18/2021
Note: Released By: CHRIS JOHNSON - - CJOHNSON@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMINISTRATIVE- SITE DEVELOP ¤125.00 09/14/2021
INSPECTION - GENERAL ¤520.00 09/14/2021
SITE INSPECTION ¤840.00 09/14/2021
SITE PLAN 30 ¤30.00 09/14/2021
Fees Total Due: ¤0.00 Total Paid: ¤1,515.00