Permit #2021090285

Permit Details

Status: COED

Parcel Id: 07-11-31-7009-00210-0210
CONDITIONED SPACE: 2291 sqft
GARAGE: 592 sqft
OPENED PORCH (WITH ROOF) : 197 sqft
OPENED PORCH (WITH ROOF) : 87 sqft
Total Square Footage: 3167 sqft
Block: 00210
Subdivision: 2208 - SECTION 9-FLORIDA PARK
Job Phone: 321-271-9033
Location Address: 58 FALLEN OAK LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 12/09/2021
NOC: RECORDED
Applicant name: KEITH E TANNER
Owner: VINTAGE ESTATE HOMES LLC A FLORIDA LIMITED

Address

4885 N WIKCHAM RD

MELBOURNE, FL 32940

Lot: 0210
Contracted Stated Job Value: ¤250,000.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

MERCEDES PREMIER HOMES, LLC
Status Location Address Mailing Address State License Number Phone
INACTIVE

4885 N WICKHAM RD

MELBOURNE, FL 32940

STE 101

MELBOURNE, FL 32940

CGC1516602 (Exp: 08/31/2024) 321-610-3924

Sub Contractors

SANTOS L HERNANDEZ
Status Location Address State License Number Phone Fax
ACTIVE

946 SHADDICK DRIVE

ORANGE CITY, FL 32763

CCC1328011 (Exp: 08/31/2026) 386-218-4942 386-218-4937
JOSEPH C WRIGHT
Status Location Address Mailing Address State License Number Phone Fax
ACTIVE

15 HARGROVE LANE

PALM COAST, FL 32137

UNIT 3 D

PALM COAST, FL 32137

EC13003278 (Exp: 08/31/2026) 386-447-9644 386-447-9633
JEFFREY TROY SABAKA
Status Location Address State License Number Phone Fax
ACTIVE

2191 DEERWOOD ACRES DR

ST AUGUSTINE, FL 32084

CFC1427439 (Exp: 08/31/2026) 904-838-2218 904-819-0965
JASON LEE JAMES
Status Location Address State License Number Phone
ACTIVE

217 N WESTMONTE DR SUITE 1007

ALTAMONTE SPRINGS, FL 32714

CAC1820196 (Exp: 08/31/2026) 407-404-4000

Inspection History

Type Request Date Result Inspector
BLD - BUILDING FINAL 09/08/2022 FINAL APPROVED AGAETANO
Note: THIS IS A REINSPECTION 09-07-2022 1. No hot water. 2. Master bedroom has two outlets not working. Under the window and the USB outlet.
BLD - BUILDING FINAL 09/07/2022 Disapproved - NO FEE AGAETANO
Note: 09-07-2022 1. No hot water. 2. Master bedroom has two outlets not working. Under the window and the USB outlet.
ROW - STORMWATER FINAL 09/02/2022 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION 9/2/22 - Builder to add another row of sod on the edge of the swale (road side) before the building final. Will also remove the sediment from the street at the end of the driveway. Inspector will check later. Inspector will add another Stormwater if work is not completed. Approving as-noted as a courtesy to get the Bldg Final Scheduled. 8/31/22 - NOTE TO INSPECTOR: Photo's were taken of the attempted swale repair at house 60 on 8/31/22 and attached to this inspection. If the swale still looks like this at the time of inspection then they did not bring in enough fill to match the preexisting grade. 8/30/22 - *Swale regraded at 60 needs finished. Fill and sod needed to match the original grade. *Due to the history of washout and flooding that house # 60 experienced during the construction and the sharp slope from the large rear lawn, the burm on the left side from the rear of the house to the rear property line needs to be much higher and defined so as not to flood the neighbor. *All bare earth areas just outside the left property line needs to be sodded at the Inspectors discression that seed and straw will not hold during rainy season. New inspection due to canceled inspection Inspector Notes from Inspection 9465 Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
ROW - STORMWATER FINAL 08/30/2022 Disapproved -FEE REQUIRED RGROSS
Note: 8/30/22 - *Swale regraded at 60 needs finished. Fill and sod needed to match the original grade. *Due to the history of washout and flooding that house # 60 experienced during the construction and the sharp slope from the large rear lawn, the burm on the left side from the rear of the house to the rear property line needs to be much higher and defined so as not to flood the neighbor. *All bare earth areas just outside the left property line needs to be sodded at the Inspectors discression that seed and straw will not hold during rainy season. New inspection due to canceled inspection Inspector Notes from Inspection 9465 Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
ROW - FINAL APRON (AFTER POUR) 08/30/2022 APPROVED RGROSS
Note: New inspection due to canceled inspection Inspector Notes from Inspection 9465 Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
ROW - FINAL APRON (AFTER POUR) 08/26/2022 CANCELLED BY APPLICANT WEB
Note: Inspector Notes from Inspection 9465 Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
U-CROSS CONNECTION 08/26/2022 APPROVED DHANEY
U -UTILITY RESIDENTIAL FINAL 08/26/2022 FINAL APPROVED DHANEY
ROW - STORMWATER FINAL 08/26/2022 CANCELLED BY APPLICANT WEB
Note: Inspector Notes from Inspection 9465 Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
ROW- FINAL SURVEY/GRADING CERTIFICATION 08/24/2022 APPROVED EMADISON
Note: Inspector Notes from Inspection 9270 THIS IS A REINSPECTION THIS IS A REINSPECTION **08/04/22 SITE NOT READY TOO WET AND PIPE BURIED BY WASHED OUT MATERIAL ** SEE ATTACHED PHOTOS ** 08/03/22 SITE NOT READY FOR INSPECTION 8/4/22 - 11:24am. This was rescheduled and approved the same day by Robert as a courtesy because of the infamous road on which the builder was trying to pour. Notoreous for difficulty with ground water. Photo attached showing the length of effort put forth by the builder to bring the pre-pour up to code. Phot attached. READY TO POUR
ROW FIELD SURVEY /GRADING CERTIFICATION 08/24/2022 APPROVED - AS NOTED RGROSS
Note: Note to Builder: BEFORE the Final Row inspection house number 60 needs the ENTIRE front swale regraded and re-soded. Wahout sand and silt from this new constructions has ruined her swale grade. The Culvert at house 60 also needs cleaned of silt.
ELECTRIC - EARLY POWER 08/23/2022 APPROVED AGAETANO
Note: THIS IS A REINSPECTION House needs to be unlocked 08-23-2022. FPL notified at 10:52
ELECTRIC - EARLY POWER 08/19/2022 Disapproved -FEE REQUIRED JMUNSON
Note: House needs to be unlocked
ROW- PRE-APRON (PRE-POUR) 08/04/2022 CANCELLED BY APPLICANT EMADISON
Note: THIS IS A REINSPECTION **08/04/22 SITE NOT READY TOO WET AND PIPE BURIED BY WASHED OUT MATERIAL ** SEE ATTACHED PHOTOS ** 08/03/22 SITE NOT READY FOR INSPECTION
ROW- PRE-APRON (PRE-POUR) 08/04/2022 APPROVED - AS NOTED RGROSS
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION **08/04/22 SITE NOT READY TOO WET AND PIPE BURIED BY WASHED OUT MATERIAL ** SEE ATTACHED PHOTOS ** 08/03/22 SITE NOT READY FOR INSPECTION 8/4/22 - 11:24am. This was rescheduled and approved the same day by Robert as a courtesy because of the infamous road on which the builder was trying to pour. Notoreous for difficulty with ground water. Photo attached showing the length of effort put forth by the builder to bring the pre-pour up to code. Phot attached. READY TO POUR
ROW- PRE-APRON (PRE-POUR) 08/03/2022 CANCELLED BY APPLICANT EMADISON
Note: ** 08/03/22 SITE NOT READY FOR INSPECTION
U - SEWER TIE IN 07/21/2022 APPROVED MGIBSON
Note: THIS IS A REINSPECTION Cannot see connection at the street. Area has been backfilled.
U - SEWER TIE IN 07/13/2022 CANCELLED BY APPLICANT WEB
U - SEWER TIE IN 07/13/2022 Disapproved - NO FEE AGAETANO
Note: Cannot see connection at the street. Area has been backfilled.
INSULATION 05/31/2022 APPROVED LMILLER
ALL ROUGH 05/20/2022 APPROVED AGAETANO
Note: THIS IS A REINSPECTION missing too much a/c duct
LATH/BRICK/ WATER BARRIER 05/20/2022 APPROVED AGAETANO
ALL ROUGH 04/22/2022 Disapproved - NO FEE RMARTIN
Note: missing too much a/c duct
ROW - DRAINAGE 03/21/2022 APPROVED - AS NOTED KRUTH
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION the silt fences have failed and flooded both neighbors and let alot of dirt go onto adjacent properties this needs to be fixed today next inspection 3/14 nothing done dirt in the road is causing dangerous road hazards needs to be removed or the city will do it next inspection 3/15/22
ROW - DRAINAGE 03/18/2022 Disapproved -FEE REQUIRED KRUTH
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION THIS IS A REINSPECTION the silt fences have failed and flooded both neighbors and let alot of dirt go onto adjacent properties this needs to be fixed today next inspection 3/14 nothing done dirt in the road is causing dangerous road hazards needs to be removed or the city will do it next inspection 3/15/22
ROW - DRAINAGE 03/15/2022 Disapproved -FEE REQUIRED KRUTH
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION the silt fences have failed and flooded both neighbors and let alot of dirt go onto adjacent properties this needs to be fixed today next inspection 3/14 nothing done dirt in the road is causing dangerous road hazards needs to be removed or the city will do it next inspection 3/15/22
ROW - DRAINAGE 03/14/2022 Disapproved -FEE REQUIRED KRUTH
Note: THIS IS A REINSPECTION the silt fences have failed and flooded both neighbors and let alot of dirt go onto adjacent properties this needs to be fixed today next inspection 3/14 nothing done dirt in the road is causing dangerous road hazards needs to be removed or the city will do it next inspection 3/15/22
ROW - DRAINAGE 03/11/2022 Disapproved -FEE REQUIRED KRUTH
Note: the silt fences have failed and flooded both neighbors and let alot of dirt go onto adjacent properties this needs to be fixed today next inspection 3/14
ROOF SHEATHING / BRACES/TIES/DOWN CELL 03/10/2022 APPROVED - AS NOTED AGAETANO
Note: 1. Truss A3 calls for 2 Heta 20. Check at insulation. 2. Please have a dry set of approved drawings on site for future inspections.
ROOF VALLEY & METAL 03/10/2022 APPROVED AGAETANO
WALL SHEATHING 03/09/2022 APPROVED AGAETANO
Note: THIS IS A REINSPECTION Wall sheathing not nailed properly on the left side of the entry.
WALL SHEATHING 03/08/2022 CANCELLED BY APPLICANT WEB
WALL SHEATHING 03/08/2022 Disapproved - NO FEE AGAETANO
Note: Wall sheathing not nailed properly on the left side of the entry.
FOUND SURVEY APPROVED (OFFICE) 03/08/2022 APPROVED AMOBLEY
ROW - DRAINAGE 03/01/2022 APPROVED KRUTH
Note: THIS IS A REINSPECTION Inspect for swale obstructions Establish a consistant flow line swale is blocked and needs a drainage pipe pipe is clear and free of obstruction
ROW - DRAINAGE 02/25/2022 Disapproved -FEE REQUIRED KRUTH
Note: Inspect for swale obstructions Establish a consistant flow line swale is blocked and needs a drainage pipe
TIE BEAM / LINTEL 02/22/2022 APPROVED AGAETANO
MONOLITHIC SLAB 01/31/2022 APPROVED FWILLIS
PLUMBING 1ST ROUGH UNDERGROUND 01/27/2022 APPROVED MGIBSON
GRAVITY SEWER TEST 01/27/2022 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 12/29/2021 APPROVED CSTONE

Review History

Department Status Date In Date Out
MECH COMPLETE 09/06/2022 09/06/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
MECH HOLD 09/02/2022 09/02/2022
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Provide entire energy calc and heatload with duct layout
MECH HOLD 08/24/2022 08/24/2022
Note: Held By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM Indoor design temp on heatload must be a minimum of 75 degrees per R302.1 FBC Energy Conservation 2020 7Th edition
ENGIN1 COMPLETE 03/08/2022 03/08/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 03/08/2022 03/08/2022
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ENGIN1 COMPLETE 03/04/2022 03/07/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
MECH COMPLETE 03/04/2022 03/07/2022
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
ENGIN1 HOLD 02/22/2022 02/23/2022
Note: Held By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM Slab elevation on foundation survey is 10' higher than approved site plan. Please revise and resubmit.
ZON COMPLETE 02/22/2022 02/22/2022
Note: Released By: TRACEY DOAK - (386)986-3751 - TDOAK@PALMCOASTGOV.COM
ZON COMPLETE 10/28/2021 10/29/2021
Note: Released By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM
ZON HOLD 10/25/2021 10/26/2021
Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM Please compare all three together landscape plan still doesn't match
SW1 COMPLETE 10/25/2021 10/28/2021
Note: Released By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM
ENGIN1 COMPLETE 10/25/2021 10/26/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON HOLD 09/22/2021 09/22/2021
Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM 2nd request: lanscape plan to match site plan and survey still missing
ENGIN1 COMPLETE 09/22/2021 09/22/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 HOLD 09/22/2021 09/30/2021
Note: Held By: GABRIEL BERTOLA - (386)225-3840 - GBERTOLA@PALMCOASTGOV.COM Check the site plan for detail See uploaded Stormwater checklist in attachments for correction. Make corrections on all unchecked items.
SWALE COMPLETE 09/08/2021 11/17/2021
Note: Released By: JOHN HOWARD - - JHOWARD@PALMCOASTGOV.COM
BLD COMPLETE 09/07/2021 09/08/2021
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
CUSVC COMPLETE 09/07/2021 09/13/2021
Note: Released By: HALEIGH HAND - -
ELEC COMPLETE 09/07/2021 09/08/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 09/07/2021 09/08/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 09/07/2021 09/09/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 09/07/2021 09/08/2021
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
SW1 COMPLETE 09/07/2021 09/14/2021
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ZON HOLD 09/07/2021 09/08/2021
Note: Held By: CINDY CHIRI-GONCALVES - - CGONCALVES@PALMCOASTGOV.COM Site Plan and landscape and floor plan do not match. Please compare all three together you will find that the patio levels with house on site plan but the floor plan bedroom 4 sticks out of patio area and on lanscape the 4th bedroom is behind patio. These plans need to all match.

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
CONTRACTOR CHANGE ¤40.00 09/06/2022
CONTRACTOR CHANGE ¤40.00 09/06/2022
PLAN REVIEW - REVISION ¤65.00 09/06/2022
REINSPECTION RESIDENTIAL ¤40.00 09/06/2022
SW ENG REINSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 09/06/2022
SW ENG - INSPECTION 20 ¤20.00 03/08/2022
SW ENG - INSPECTION 20 ¤20.00 03/08/2022
CONNECTION FEES ¤1,017.83 12/09/2021
METER - DEPOSIT ¤60.00 12/09/2021
WATER- TURN ON ¤25.00 12/09/2021
ADMINISTRATIVE RESIDENTIAL ¤30.00 12/09/2021
INSPECTION - RESIDENTIAL ¤797.50 12/09/2021
PLAN REVIEW - RESIDENTIAL ¤226.20 12/09/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 12/09/2021
IMPACT FEE FIRE ¤367.00 12/09/2021
IMPACT FEE PARKS ¤1,199.12 12/09/2021
IMPACT FEE SCHOOL ¤3,600.00 12/09/2021
IMPACT FEE TRANSPORTATION ¤1,718.00 12/09/2021
WATER -IRRIGATION INSPECTION ¤25.00 12/09/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 12/09/2021
SURCHARGE FS 533.721 ¤11.11 12/09/2021
SURCHARGE - FS 468.631 ¤16.67 12/09/2021
SW ENG - FOUNDATION SURVEY ¤20.00 12/09/2021
SW ENG INSPECTION 60 ¤60.00 12/09/2021
SW ENG PRE APRON ¤30.00 12/09/2021
SW ENG - REVIEW 20 ¤20.00 12/09/2021
SW ENG RES REVIEW 200 ¤200.00 12/09/2021
3% TRANS IMPACT FEE CREDIT (¤51.54) 12/09/2021
SEWER INSPECTION ¤25.00 12/09/2021
SEWER CAPITAL FACILITY ¤4,664.55 12/09/2021
WATER CAPITAL FACILITY FEE ¤3,424.45 12/09/2021
SITE PLAN 30 ¤30.00 12/09/2021
Fees Total Due: ¤0.00 Total Paid: ¤17,813.91