Permit #2021090575

Permit Details

Status: COED

Parcel Id: 16-11-31-1260-00000-0020
CONDITIONED SPACE: 2654 sqft
GARAGE: 726 sqft
OPENED PORCH (WITH ROOF) : 502 sqft
OPENED PORCH (WITH ROOF) : 72 sqft
Total Square Footage: 3954 sqft
Block: 00000
Subdivision: 2081 - Creekside Village at Grand Haven
Job Phone: 386-445-2012
Location Address: 5 CREEKSIDE DR
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 09/28/2021
NOC: RECORDED
Applicant name: JOHN NICHOLAS CORDASCI
Owner: LEON B & LINDA L LUSSIER

Address

200 RIVERFRONT DRIVE UNIT A-301

PALM COAST, FL 32137

Lot: 0020
Contracted Stated Job Value: ¤434,529.00
Job Description: Single family residence
Type: CN

Contractor

SKYWAY BUILDERS INC
Status Location Address State License Number Phone
INACTIVE

PO BOX 354786

PALM COAST, FL 32135

CBC1263769 (Exp: 08/31/2024) 386-445-2012

Sub Contractors

MARK JOHN LUTCZA
Status Location Address State License Number Phone
ACTIVE

26 ROYAL LEAF LANE

PALM COAST, FL 32164

EC13005145 (Exp: 08/31/2026) 386-586-0770
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
THOMAS A REGULA
Status Location Address State License Number Phone Fax
INACTIVE

11320 PHILLIPS PKWY DRIVE E

JACKSONVILLE, FL 32256

CMC1250075 (Exp: 08/31/2026) 904-278-0339 904-278-0366
DANIEL DAVID RUTKOWSKI III
Status Location Address State License Number Phone Fax
ACTIVE

1687 STATE AVENUE

HOLLY HILL, FL 32117

CCC1328639 (Exp: 08/31/2026) 386-290-7490 386-256-0001
TRAVIS MIDDLETON
Status Location Address State License Number Phone Fax
CANCEL

2680 HIGHWAY 17 SOUTH

CRESCENT CITY, FL 32112

00714 (Exp: 11/24/2022) 386-698-1033 386-698-1077

Inspection History

Type Request Date Result Inspector
WALL SHEATHING 01/24/2023 APPROVED TSTAUFFACHER
BLD - BUILDING FINAL 01/20/2023 FINAL APPROVED TSTAUFFACHER
ROW - STORMWATER FINAL 01/19/2023 FINAL APPROVED PFLANAGAN
Note: ALL AREAS HAVE BEEN FIXED ------------------------------------------------------------------- 1/17/2023 - PREVIOUS INSPECTION NOTES 01/17/23=in the back of the property both side need to remove the mulch from the drainage conveyance and add sodd. Flat work, i.e., slabs, walkways, hardscaping, patios, decking or AC pads are not allowed in any utility easements. Additionally, decorative objects, columns, light poles, mulch, stones, plantings or landscaping of any kind, is not allowed in the Right of Way Section 300.03 Lot Grading Permit Requirements (Improved Properties) C.F
U -UTILITY RESIDENTIAL FINAL 01/17/2023 FINAL APPROVED LFITZGERALD
ROW - STORMWATER FINAL 01/17/2023 Disapproved - NO FEE GBERTOLA
Note: 01/17/23=in the back of the property both side need to remove the mulch from the drainage conveyance and add sodd. Flat work, i.e., slabs, walkways, hardscaping, patios, decking or AC pads are not allowed in any utility easements. Additionally, decorative objects, columns, light poles, mulch, stones, plantings or landscaping of any kind, is not allowed in the Right of Way Section 300.03 Lot Grading Permit Requirements (Improved Properties) C.F
U-CROSS CONNECTION 01/17/2023 APPROVED - AS NOTED LFITZGERALD
Note: well irrigation-no cross connection
ROW FIELD SURVEY /GRADING CERTIFICATION 01/12/2023 APPROVED PFLANAGAN
ROW - FINAL APRON (AFTER POUR) 01/12/2023 APPROVED PFLANAGAN
FINAL SURVEY (OFFICE USE ONLY) 01/12/2023 APPROVED PFLANAGAN
ROW- PRE-APRON (PRE-POUR) 11/07/2022 APPROVED PFLANAGAN
Note: 11/4/2022 - PREVIOUS INSPECTION NOTES ** 11/04/22 SITE PLAN CALLS FOR A 14 FOOT PAVER DRIVEWAY WITH PAVER BANDING NO PAVER RESTRAINTS HAVE BEEN DUG OUT, APPEARS TO BE A DISCREPANCY WITH HOW SITE PLAN READS AND WORK TO BE DONE ** ALSO A UTILITY BOX IN SIDEWALK POUR ON LEFT SIDE NEEDS TO BE MOVED ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECIAL INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. DISREGARD ATTACHED PHOTOS. 11/4/2022 - PREVIOUS INSPECTION NOTES ** 11/04/22 DISAPPROVED PRE-POUR FOR APRON AS THE APRON HAS ALREADY BEEN POUR WITH NO INSPECTION ** ALSO PAVER BASE SPREAD NOT ENOUGH DEPTH AND LITTLE TO NO COMPACTION
ROW- PAVER RESTRAINTS 11/07/2022 APPROVED PFLANAGAN
Note: NO PAVERS CONCRETE DRIVEWAY -------------------------------------------------------------------------------------------- 11/4/2022 - PREVIOUS INSPECTION NOTES 11/4/2022 - PREVIOUS INSPECTION NOTES ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECIAL INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. ** 11/04/22 PAVER RESTRAINTS POUR WITH NO PRE POUR INSPECTION OF RAVE RESTRAINTS
ROW- PAVER RESTRAINTS 11/04/2022 Disapproved -FEE REQUIRED EMADISON
Note: ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECIAL INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. ** 11/04/22 PAVER RESTRAINTS POUR WITH NO PRE POUR INSPECTION OF RAVE RESTRAINTS
ROW- PAVER RESTRAINTS 11/04/2022 CANCELLED BY APPLICANT EMADISON
Note: 11/4/2022 - PREVIOUS INSPECTION NOTES ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECIAL INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. ** 11/04/22 PAVER RESTRAINTS POUR WITH NO PRE POUR INSPECTION OF RAVE RESTRAINTS
ROW- PRE-APRON (PRE-POUR) 11/04/2022 Disapproved -FEE REQUIRED EMADISON
Note: ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECTION INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. ** 11/04/22 DISAPPROVED PRE-POUR FOR APRON AS THE APRON HAS ALREADY BEEN POUR WITH NO INSPECTION ** ALSO PAVER BASE SPREAD NOT ENOUGH DEPTH AND LITTLE TO NO COMPACTION
ROW- PRE-APRON (PRE-POUR) 11/04/2022 Disapproved - NO FEE EMADISON
Note: ** 11/04/22 SITE PLAN CALLS FOR A 14 FOOT PAVER DRIVEWAY WITH PAVER BANDING NO PAVER RESTRAINTS HAVE BEEN DUG OUT, APPEARS TO BE A DISCREPANCY WITH HOW SITE PLAN READS AND WORK TO BE DONE ** ALSO A UTILITY BOX IN SIDEWALK POUR ON LEFT SIDE NEEDS TO BE MOVED ** 11/04/22 BUILDER PLEASE DISREARD PREVIOUS DISAPPROVED INSPECIAL INSPECTOR ERROR RESULTED WRONG INSPECTION WILL REMOVE FEES. DISREGARD ATTACHED PHOTOS. 11/4/2022 - PREVIOUS INSPECTION NOTES ** 11/04/22 DISAPPROVED PRE-POUR FOR APRON AS THE APRON HAS ALREADY BEEN POUR WITH NO INSPECTION ** ALSO PAVER BASE SPREAD NOT ENOUGH DEPTH AND LITTLE TO NO COMPACTION
U - SEWER TIE IN 10/25/2022 APPROVED MGIBSON
GRAVITY SEWER TEST 10/25/2022 APPROVED MGIBSON
ELECTRIC - EARLY POWER 06/21/2022 APPROVED AGAETANO
LATH/BRICK/ WATER BARRIER 05/10/2022 APPROVED DCUSHING
INSULATION 05/10/2022 APPROVED DCUSHING
Note: THIS IS A REINSPECTION THIS IS A REINSPECTION cancelled per John
INSULATION 05/09/2022 CANCELLED BY APPLICANT AGAETANO
Note: THIS IS A REINSPECTION cancelled per John
INSULATION 05/06/2022 CANCELLED BY APPLICANT LMILLER
Note: cancelled per John
ALL ROUGH 04/20/2022 APPROVED - AS NOTED LMILLER
Note: need the following by insulation, 1. Box out arount dryer exhaust 2. missing window in Laundry room 3. need to complete framing around all windows and doors
ELECTRIC-TUG 02/08/2022 APPROVED - AS NOTED RMARTIN
Note: EMAILED FPL RELEASED POWER 3:15
ROOF SHEATHING / BRACES/TIES/DOWN CELL 01/21/2022 APPROVED LMILLER
Note: THIS IS A REINSPECTION Please provide a full set of approved drawings and energineering packet. Drawings in the box are wet and wrinkled. Energy packet not on site. 01-21-22... notes above resolved
ROOF VALLEY & METAL 01/21/2022 APPROVED LMILLER
ROOF SHEATHING / BRACES/TIES/DOWN CELL 01/19/2022 Disapproved - NO FEE AGAETANO
Note: Please provide a full set of approved drawings and energineering packet. Drawings in the box are wet and wrinkled. Energy packet not on site.
TIE BEAM / LINTEL 12/28/2021 APPROVED AGAETANO
FOUND SURVEY APPROVED (OFFICE) 12/15/2021 APPROVED AMOBLEY
MONOLITHIC SLAB 12/01/2021 APPROVED LMILLER
PLUMBING 1ST ROUGH UNDERGROUND 11/22/2021 APPROVED MGIBSON
WATER METER INSTALLATION REQUEST 10/14/2021 APPROVED CSTONE

Review History

Department Status Date In Date Out
SW1 COMPLETE 11/15/2022 11/15/2022
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
ENGIN1 COMPLETE 11/04/2022 11/04/2022
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
SW1 HOLD 11/04/2022 11/15/2022
Note: Held By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM FFE must be 12 Inches above the crown of the road
ZON COMPLETE 11/04/2022 11/04/2022
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
ENGIN1 COMPLETE 12/14/2021 12/15/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
ZON COMPLETE 12/14/2021 12/15/2021
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM
SW1 COMPLETE 09/21/2021 09/21/2021
Note: Released By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM
BLD COMPLETE 09/14/2021 09/15/2021
Note: Released By: HAROLD ALLEN - (386)986-2357 - HALLEN@PALMCOASTGOV.COM
CUSVC COMPLETE 09/14/2021 09/20/2021
Note: Released By: HALEIGH HAND - -
ELEC COMPLETE 09/14/2021 09/15/2021
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 09/14/2021 09/14/2021
Note: Released By: TIM BAKER - (386)986-4726 - TBAKER@PALMCOASTGOV.COM
LOCATE COMPLETE 09/14/2021 09/15/2021
Note: Released By: CANDACE STONE - - CSTONE@PALMCOASTGOV.COM
MECH COMPLETE 09/14/2021 09/15/2021
Note: Released By: CHRIS PISCITELLI - (386)986-3782 - CPISCITELLI@PALMCOASTGOV.COM
SW1 HOLD 09/14/2021 09/17/2021
Note: Held By: ROBERT GROSS - (386)986-4769 - RGROSS@PALMCOASTGOV.COM See SW1 Checklist. FFE must be a minimum of 12 inches above the crown of the road.
ZON COMPLETE 09/14/2021 09/16/2021
Note: Released By: ALISHA MOBLEY - (386)986-3751 - AMOBLEY@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
SW ENG REINSPECTION 20 ¤20.00 01/23/2023
SW ENG - REVIEW 20 ¤20.00 09/28/2021
SW ENG RES REVIEW 200 ¤200.00 09/28/2021
3% TRANS IMPACT FEE CREDIT (¤94.17) 09/28/2021
SEWER INSPECTION ¤25.00 09/28/2021
SITE PLAN 30 ¤30.00 09/28/2021
METER - DEPOSIT ¤60.00 09/28/2021
WATER-METER ¤441.07 09/28/2021
ADMINISTRATIVE RESIDENTIAL ¤30.00 09/28/2021
INSPECTION - RESIDENTIAL ¤1,196.25 09/28/2021
PLAN REVIEW - RESIDENTIAL ¤339.30 09/28/2021
CONNECTION FEES ¤25.00 09/28/2021
3% FIRE IMPACT FEE CREDIT (¤11.01) 09/28/2021
IMPACT FEE FIRE ¤367.00 09/28/2021
IMPACT FEE PARKS ¤1,199.12 09/28/2021
IMPACT FEE SCHOOL ¤3,600.00 09/28/2021
IMPACT FEE TRANSPORTATION ¤3,139.00 09/28/2021
3% PARKS IMPACT FEE CREDIT (¤35.97) 09/28/2021
SURCHARGE FS 533.721 ¤16.36 09/28/2021
SURCHARGE - FS 468.631 ¤24.55 09/28/2021
SW ENG - FOUNDATION SURVEY ¤20.00 09/28/2021
SW ENG INSPECTION 60 ¤60.00 09/28/2021
SW ENG PRE APRON ¤30.00 09/28/2021
Fees Total Due: ¤0.00 Total Paid: ¤10,701.50